RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ4249
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Oct 2013
Original start1 Oct 2013
Project duration96 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressL-4, Green Park Extension, New Delhi - 110016
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. to

    Extension granted

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  9. Completion certificate filed

  10. 2 completion certificates filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion31 Mar 2020
Revised completion28 Sept 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary1 Dec 2021
Registration fee₹76,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors270 · 7 · 24 (units from plan)
  • 3 BHK214 79%
  • 4 BHK42 16%
  • PENTHOUSE14 5%
ConfigurationUnitsCarpet area
3 BHK214107-111
PENTHOUSE14123-156
4 BHK42140
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A1 · 3 BHK, PENTHOUSE, OTHER2036107-123
A2 · 3 BHK, PENTHOUSE, OTHER2035107-123
A3 · 3 BHK, PENTHOUSE, OTHER2442107-123
A5 · 3 BHK, PENTHOUSE, OTHER1526107-123
B1 · 3 BHK, PENTHOUSE, OTHER2445107-123
B2 · 4 BHK, 3 BHK, PENTHOUSE, OTHER2444111-156
B3 · 3 BHK, 4 BHK, PENTHOUSE, OTHER2442111-155
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Team 3
License CA/2006/38929
J-94, LG Floor, Saket, New Delhi-110017
Engineer
Technical Projects Consultants Pvt. Ltd.
B-74, Sector 57, Noida - 201301
Sr.Development work declared to RERA
1Demarcation of Plots
N/A
2Boundary Wall
Boundary wall has been designed & completed at Site.
3Road Work
All road work TRE-MIX has been completed at Site.
4Footpaths
Internal landscape footpaths have been completed.
5Water Supply Including Drinking Water Facilities
are being laid to all apartments
6Sewer System
Internally has been laid.
7Drain
All internal & external have been completed.
8Parks
There is a Green Area in the non Tower Zone, which Acts as a Park.
9Tree Planting
Planting of various types of Evergreen Trees have been planted in the monsoon.
10Design For Electric Supply Including Street Lighting
5 Mtr. & 3 Mtr. Poles Street Lights have been planned along the road.
11Community Buildings
A Club with all facility have been provided.
12Treatment and Disposal System of Sewage and Sullage water
AW STP has been planned in Basement Two.
13Solid Waste Management And Disposal System
An Organic Waste Composite Machine has been provided.
14Water Conservation System
Rain water harvesting has been planned at site.
15Energy Management System Including Use of Renewable Energy
Solar Power Panel has been installed for use of Renewable Energy.
16Fire Protection And Fire Safety System
Sprinklers & Smoke Detectors have been provided in all apartments.
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
Refuge Area have been planned as per specification.
19Other Miscellaneous Work
Addition Stack Car Parking has been provided.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2AADHAR PROPMART PRIVATE LIMITEDUPRERAAGT10142
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 30 Jun 2021.

Sanctioned by Noida Authority · 14,188 sqm of land · an approved plan of 7 blocks and 270 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Noida/MVN/2016/III-186/91430 Jun 201630 Jun 202130 Jun 202131 Mar 2020
Noida/MVN/2016/III-186/91430 Jun 201630 Jun 202130 Jun 202131 Mar 2020
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 28 Sept 2021.

#Granted fromExtended uptoNote
131 Mar 202030 Sept 2020Six months extension in view of force majeure caused by covid-19 pandemic
230 Sept 202031 Mar 2021—
331 Mar 202128 Sept 2021—

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
F-03314187.80Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 19 Dec 2007.

Registry no.DateTypeArea
395319 Dec 2007self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 3953
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New19 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New31 Jan 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 Jan 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New19 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New19 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New19 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New19 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New19 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New4 Feb 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New4 Feb 2019 ↗

Quarterly progress reports

2 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

2 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAmbience Private Limited
RolePromoter · current
RERA IDUPRERAPRM7226
PANAAACA0541K
CIN / TANU51503DL1986PTC023886
Name of chairmanMr. Raj Singh Gehlot
Registered addressL-4, Green Park Extension, New Delhi - 110016
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
AMBIENCE PVT LTDBankORIENTAL BANK OF COMMERCEBranchORIENTAL BANK OF COMMERCE LARGE CORPORATE BRANCH,E BLOCK,CONNAUGHT PLACE, NEW DELHIA/C no.IFSCORBC0100007
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Ambience Tiverton

Is Ambience Tiverton RERA registered?

Yes. Ambience Tiverton is registered with UPRERA under registration number UPRERAPRJ4249, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has Ambience Tiverton been completed?

UPRERA still lists Ambience Tiverton as Registered, so it is not shown as completed here. A completion certificate dated 1 Dec 2021 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Ambience Tiverton?

Ambience Private Limited is the promoter entity that filed Ambience Tiverton with UPRERA (promoter RERA ID UPRERAPRM7226). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Ambience Tiverton more time to complete?

UPRERA's record carries 3 completion extensions for Ambience Tiverton, the latest running to 28 Sept 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Ambience Tiverton have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Ambience Tiverton located?

Ambience Tiverton is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Ambience Tiverton?

The unit plan filed with UPRERA lists 3 BHK, PENTHOUSE, 4 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Ambience Tiverton?

The approved unit plan filed with UPRERA runs from 107 to 156 m² of carpet area (about 1,156 to 1,679 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Ambience Tiverton?

The approved unit plan describes 7 blocks and 270 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Ambience Tiverton?

About 77 units per acre: 270 planned units across 3.51 acres (14,188 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗