FIVEO

UPRERARegistered

FIVEO is a RERA-registered commercial project by GYGY DEVELOPERS PRIVATE LIMITED in SECTOR-50, NOIDA - 201303, Gautam Budh Nagar (RERA ID UPRERAPRJ662072). Registered with a completion deadline of 29 Aug 2029. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
35%Q2'25
42%Q3'25
55%Q4'25
64.84%Q1'26
81.05%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ662072
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Nov 2024
Project duration58 months
AddressPLOT NO. 1B, BLOCK NO. F,, SECTOR-50, NOIDA - 201303, Dadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant addressHouse No-21, Ground Floor, Block-F Pkt-17, Sector-08, Rohini, Delhi-110085
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2024/06/24/10803

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered11 Oct 2024
Original completion29 Aug 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹40,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 1 · 6 (from plan)
ConfigurationUnitsCarpet area
SHOP—11-153
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
FIVEO · SHOP6—11-153
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VIKAS VIJAY
License CA/2013/59892
K-47, KAILASH COLONY, DELHI-110048
Engineer
RAVI SHANKAR
H. NO. A-112, NOIDA, SECTOR-108, UTTAR PRADESH-201304
Contractor
GYGY DEVELOPRES PVT. LTD.
F-HOUSE NO-21, GROUND FLOOR, BLOCK-F, POCKET-17, SECTOR-8, ROHINI, NEW DELHI-110085
Sr.Development work declared to RERA
1Demarcation of Plots
Enclosed with Boundary wall height 1.2 M
2Boundary Wall
Combination of RCC Column with brick work, plaster/paint MS Railing
3Road Work
Road pattern is provided in such a way the approch to commercial is motorable and section consists of subgrade preparation with 1 layer GSB and 1 layer of Cement Concrete pavament/pavers as per design of Developers Consultant .
4Footpaths
Combinetion of Kerb stone/pavers/cement concrete as per design of Developres Architect.
5Water Supply Including Drinking Water Facilities
System for water is ground water and provided underground /overhead water tank with individual ROs to be installed by Allottee.
6Sewer System
Shop Hold Sewerage is collected through sewage lines upto the STP established for the project and after treatment the sluge and theated water obtained shall be used in green areas like green landscapes and also for flushing lines.
7Drain
Rain water collection shall be done from terrace thru storm water lines/covered drains at ground level and connected to rain harvesting pits.
8Parks
Provision of green area as per Design of Developers Architect.
9Tree Planting
Planned trees are 25 Nos. in open areas and along with boundary wall different types of trees shall be provided.
10Design For Electric Supply Including Street Lighting
Electrical connection for the shop from PVVNL or Its Licensee/sub-licensee and connection will be provided to customers thru prepaid meter and proportionate electricity infrastructure cost including feeder construction expenses, substations/panels/transformers/other equipments/expenses, cabling expenses, system loading charges, security charges etc as applicable shall be borne by the customers and further subject to regular payments of fixed electricity charges usage/consumption charges and energy losses/line distribution losses and payment of taxes/cess/duties/levy as applicable and demanded from time as per guidelines laid down by power supply company /government .
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Shall be connected to STP provided for treating household sewerage and the treated sludge/water is being used for green areas and flushing system
13Solid Waste Management And Disposal System
Shop to Shop collection system has been planned with a arrangement of separate collection of decomposable and non decomposable waste in separate bags and treatment arrangement for the same.
14Water Conservation System
As per Sanctioned Architect Design underground recharge pits with perforated filter media used for rain water harvesting provided.
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
Vertical risera with FHC shaft /sprinkler and connected to pump room with a provision of jockey/Main/Diesel pump as per NBC
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
Fire Staircase provided as per NBC
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Aug 2029.

Sanctioned by Noida Authority · 3,000 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2024/06/24/1080330 Aug 202429 Aug 202929 Aug 202929 Aug 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

19 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
F-1B3000Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · 874
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Lease deed · 12721
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Sept 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New10 Sept 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New10 Sept 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New11 Sept 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New10 Sept 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New10 Sept 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New26 Sept 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New10 Sept 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New12 Sept 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Sept 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New10 Sept 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New10 Sept 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New11 Oct 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New11 Sept 2024 ↗

Quarterly progress reports

7 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

7 quarterly progress reports are on file with UPRERA, covering 2024-Q3 to 2026-Q1.

QuarterConstructionCertificates
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q135%CA ↗ · Arch ↗ · Eng ↗
2025-Q242%CA ↗ · Arch ↗ · Eng ↗
2025-Q355%CA ↗ · Arch ↗ · Eng ↗
2025-Q464.84%CA ↗ · Arch ↗ · Eng ↗
2026-Q181.05%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGYGY DEVELOPERS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM306532
PANAALCG1654N
CIN / TANDELG30579D
Name of chairmanPRIYANKA GOYAT
Registered addressHouse No-21, Ground Floor, Block-F Pkt-17, Sector-08, Rohini, Delhi-110085
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
M/S GYGY DEVELOPERS PL COLL BNK A/C F FIVEOBankHDFC BANKBranchN2, SECTOR 11, OPPOSITE METRO HOSPITAL, NOIDA-201301Branch addressN2, SECTOR 11, OPPOSITE METRO HOSPITAL, NOIDA-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0001223Branch emaildeepak.sood@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
M/S GYGY DEVELOPERS PL SEP BNK A/C F FIVEOBankHDFC BANKBranchN2, SECTOR-11, OPPOSITE METRO HOSPITAL, NOIDA-201301Branch addressN2, SECTOR-11, OPPOSITE METRO HOSPITAL, NOIDA - 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0001223
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
M/S GYGY DEVELOPERS PL RERA TRN A/C F FIVEOBankHDFC BANKBranchN2, SECTOR-11, OPPOSITE METRO HOSPITAL, NOIDA-201301Branch addressN2, SECTOR-11, OPPOSITE METRO HOSPITAL, NOIDA - 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0001223
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)2 (Under Registration - 1 ) → 2 (Under Registration - 0 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)2 (Under Registration - 2 ) → 2 (Under Registration - 1 )
changed in Estanzo’s record
9 Sept 2026
Promoter’s complaints tally (all their projects)1 (Under Registration - 1 ) → 2 (Under Registration - 2 )
changed in Estanzo’s record
1 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 23 Sept 2026 · 3 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about FIVEO

Is FIVEO RERA registered?

Yes. FIVEO is registered with UPRERA under registration number UPRERAPRJ662072, registered on 11 Oct 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for FIVEO?

The completion date filed with UPRERA is 29 Aug 2029. No completion certificate is on record yet.

Who is the builder of FIVEO?

GYGY DEVELOPERS PRIVATE LIMITED is the promoter entity that filed FIVEO with UPRERA (promoter RERA ID UPRERAPRM306532). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does FIVEO show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Does FIVEO have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is FIVEO located?

FIVEO is registered in SECTOR-50, NOIDA - 201303, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in FIVEO?

The unit plan filed with UPRERA lists SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in FIVEO?

The approved unit plan filed with UPRERA runs from 11 to 153 m² of carpet area (about 119 to 1,645 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗