Timeline Bar
Registered12 Aug 2017
Promised21 Sept 2020
NCLT25 Feb 2025
Timeline
Promised completion21 Sept 2020
Revised completion21 Sept 2020
Actual completion—
Possession delay70 mo delay
Registration & Cost Details
Registration fee (in ₹)₹1,09,000
Project cost (in ₹ Lakhs)₹935 Lakhs
Project duration66 months
Project categoryResidential
Locality—
Original start date22 Sept 2015
Proposed start date22 Sept 2015
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator6389022192
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 38830 | 22 Sept 2015 | 13 Mar 2017 | 21 Sept 2020 | 13 Mar 2020 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 66, 67, 68, 69, 74, 75, 76, 79, 80, 81, 82 & 84 | 20712.06 Sq. Meter | — |
| 66 | 6700 | Khasra |
| 67 | 2150 | Khasra |
| 68 | 2400 | Khasra |
| 69 | 3790 | Khasra |
| 74 | 6820 | Khasra |
| 75 | 1450 | Khasra |
| 76 | 8990 | Khasra |
| 79 | 2010 | Khasra |
| 80 | 2010 | Khasra |
| 81 | 160 | Khasra |
| 82 | 6980 | Khasra |
| 84 | 770 | Khasra |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 1515 | 4 Feb 2010 | — | — |
| 3727 | 9 Apr 2007 | — | — |
| 6436 | 6 Jul 2007 | — | — |
| 11408 | 15 Jun 2010 | — | — |
| 13279 | 12 Nov 2009 | — | — |
| 15550 | 24 Oct 2011 | — | — |
| 17612 | 1 Dec 2011 | — | — |
| 628 | 19 Jan 2007 | — | — |
| 3662 | 7 Apr 2007 | — | — |
| 4831 | 16 May 2007 | — | — |
| 10287 | 4 Dec 2006 | — | — |
| 125 | 7 May 2007 | — | — |
| 128 | 9 May 2007 | — | — |
| 9870 | 22 Nov 2006 | — | — |
Frequently Asked Questions
What is the RERA registration number of ANSAL API-POCKET 3-SECTOR G-SGC LKO?
The RERA registration number of ANSAL API-POCKET 3-SECTOR G-SGC LKO is UPRERAPRJ10051, as recorded on the UP-RERA portal.
What is the RERA status of ANSAL API-POCKET 3-SECTOR G-SGC LKO?
As reported by UP-RERA, the status of ANSAL API-POCKET 3-SECTOR G-SGC LKO is "NCLT".
Where is ANSAL API-POCKET 3-SECTOR G-SGC LKO located?
As reported to UP-RERA, ANSAL API-POCKET 3-SECTOR G-SGC LKO is located at Lucknow, Lucknow, Uttar Pradesh.
When will ANSAL API-POCKET 3-SECTOR G-SGC LKO be completed?
The latest completion date reported to UP-RERA for ANSAL API-POCKET 3-SECTOR G-SGC LKO is 21 Sept 2020.
Is ANSAL API-POCKET 3-SECTOR G-SGC LKO delayed?
Measured against the latest completion date reported to UP-RERA, ANSAL API-POCKET 3-SECTOR G-SGC LKO is 70 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026