ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC is a RERA-registered residential project by R. R. Civil Tech Pvt Ltd in Lucknow (RERA ID UPRERAPRJ4754). Registered with a completion deadline of 28 Mar 2026.
RERA status as reported: Registered.Construction progress
Construction stayed at 32.3% across 4 consecutive filed quarters (Apr–Jun 2025 to Jan–Mar 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ4754 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 1 Jan 2018 |
| Original start | 2 Jul 2013 |
| Project duration | 99 months |
| Address | Sarojini Nagar, Lucknow |
| Tehsil | Sarojini Nagar |
| Applicant type | Company |
| Applicant address | Ground Floor, Raja Ram Kumar Plaza, 75 Hazratganj, Lucknow - 226001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Permit revalidated (2)
2 building permits sanctioned
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 29 Jul 2017 |
| Original completion | 30 Sept 2024 |
| Revised completion | 28 Mar 2026 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹86,000 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 448 | 65 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| B1 · 2 BHK | 14 | 112 | 65 |
| B2 · 2 BHK | 14 | 112 | 65 |
| B3 · 2 BHK | 14 | 112 | 65 |
| B4 · 2 BHK | 14 | 112 | 65 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Boundary Wall |
| 2 | Boundary Wall Brick-wall & MS Grill |
| 3 | Road Work Mix of Bitumen Road/Paver/CC |
| 4 | Footpaths Concrete Pavers |
| 5 | Water Supply Including Drinking Water Facilities Deep Water Bore-wells |
| 6 | Sewer System NP2 Concrete Hume Pipe Network |
| 7 | Drain NP2 Concrete Hume Pipe Network |
| 8 | Parks Lawns, Children Play Area, Combination of Indigenous and Ornamental Plants, Hardscape. |
| 9 | Tree Planting Combination of Indigenous and Ornamental Plants |
| 10 | Design For Electric Supply Including Street Lighting As per relevant Codes & Norms |
| 11 | Community Buildings N/A |
| 12 | Treatment and Disposal System of Sewage and Sullage water Connected to STP |
| 13 | Solid Waste Management And Disposal System House to House Connection |
| 14 | Water Conservation System Ground Water Recharge System |
| 15 | Energy Management System Including Use of Renewable Energy As per Prevailing Laws |
| 16 | Fire Protection And Fire Safety System As per NBC Norms |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services As per Broucher |
| 18 | Emergency Evacuation Services As per NBC Fire norms, Staircase & Assembly area |
| 19 | Other Miscellaneous Work Spacious Lobby, Security Cabin, Surveillance System |
Registered agents
24 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | ADVENTURES ENTERPRISES PVT LTD | UPRERAAGT11208 |
| 2 | AMIT KUMAR NISHAD | UPRERAAGT14016 |
| 3 | ANAND KUMAR SHUKLA | UPRERAAGT10831 |
| 4 | Bhan Pratap Singh C/o Pratap Associates | UPRERAAGT16163 |
| 5 | BOP REALTY PRIVATE LIMITED | UPRERAAGT10206 |
| 6 | BRIXWELL REALTY & CONSTRUCTION LLP | UPRERAAGT15068 |
| 7 | DAIWIK REALTORS | UPRERAAGT12075 |
| 8 | Gagan Tondon | UPRERAAGT14217 |
| 9 | GOLDEN ESTATE | UPRERAAGT10397 |
| 10 | INVESTORS CLINIC INFRATECH PRIVATE LIMITED | UPRERAAGT10052 |
| 11 | MANJARI AGARWAL | UPRERAAGT10603 |
| 12 | Mr. Janardan Agarwal | UPRERAAGT10555 |
| 13 | PIXEL GLOBAL INFRA PRIVATE LIMITED | UPRERAAGT13936 |
| 14 | RANVEER PROPERTIES | UPRERAAGT10234 |
| 15 | Sachin kumar Kanodia | UPRERAAGT15911 |
| 16 | SANJEEV KUMAR BANKA | UPRERAAGT10894 |
| 17 | SDR INFRA BUILD PVT LTD | UPRERAAGT11062 |
| 18 | SHAH MOHSIN KAMAL | UPRERAAGT14208 |
| 19 | SHREE SHRADDHA PROPERTIES | UPRERAAGT10301 |
| 20 | SILVER EDGE REAL ESTATE SOLUTION | UPRERAAGT12168 |
| 21 | STRAIGHTEDGE REAL ESTATE PRIVATE LIMITED | UPRERAAGT10067 |
| 22 | TULSI REAL ESTATE | UPRERAAGT13187 |
| 23 | Varun Properties Inc. | UPRERAAGT11985 |
| 24 | VIVEK ARORA | UPRERAAGT15945 |
Permits & extensions
2 permits
An approval and the date it runs to - not proof the work matching it was done.
2 sanctioning permits are on record with UPRERA, the latest valid to 21 Dec 2022. All 2 carry a revalidation, the latest valid to 21 Jun 2026.
Sanctioned by Lucknow Development Authority · 16,200 sqm of land · an approved plan of 4 blocks and 448 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 42781 | 22 Dec 2017 | 21 Dec 2022 | 21 Dec 2025 | 30 Sept 2024 | 22 Dec 2017 | |
| 42781 | 22 Dec 2017 | 21 Dec 2022 | 21 Jun 2026 | 29 Mar 2025 | 22 Dec 2017 valid to 21 Jun 2026 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 28 Mar 2026.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 30 Sept 2024 | 29 Mar 2025 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 29 Mar 2025 | 28 Mar 2026 | — |
Land & documents
46 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 259, 260, 261, 264, 265, 267, 268, 269, 270 & 325 | 16138.88 Sq. Meters | — |
| 259 | 2660 | Khasra |
| 260 | 3160 | Khasra |
| 261 | 1390 | Khasra |
| 264 | 3290 | Khasra |
| 265 | 4260 | Khasra |
| 267 | 1640 | Khasra |
| 268 | 6580 | Khasra |
| 269 | 5060 | Khasra |
| 270 | 2040 | Khasra |
| 325 | 3670 | Khasra |
17 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 1 Dec 2006.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 10426 | 21 Nov 2007 | self | — |
| 3729 | 9 Apr 2007 | self | — |
| 7389 | 14 Aug 2007 | self | — |
| 15550 | 24 Oct 2011 | self | — |
| 15568 | 25 Oct 2011 | self | — |
| 16042 | 5 Nov 2011 | self | — |
| 3727 | 9 Apr 2007 | self | — |
| 14746 | 31 Jul 2013 | self | — |
| 1691 | 21 Feb 2007 | other | — |
| 10631 | 13 Dec 2006 | other | — |
| 3659 | 7 Apr 2007 | other | — |
| 10214 | 1 Dec 2006 | other | — |
| 737 | 22 Jan 2007 | other | — |
| 2275 | 13 Mar 2007 | other | — |
| 11204 | 29 Dec 2006 | other | — |
| 125 | 7 May 2007 | other | — |
| 128 | 9 May 2007 | other | — |
| Sale deed · 10426 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 3729 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 15568 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 16042 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 15550 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 1691 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 7389 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 3659 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 10631 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 3727 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 737 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 10214 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 2275 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 11204 The registered deed by which the promoter bought the land. | PDF ↗ |
| Lease deed · 14746 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Registry document · 125 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 128 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Sale deed · 26253 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 8086 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 26255 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 8088 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 6 Jul 2018 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 6 Jul 2018 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 6 Jul 2018 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 6 Jul 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 11 Sept 2019 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 6 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 21 Aug 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 18 Aug 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 18 Aug 2018 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Jul 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jul 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jul 2017 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 29 Jul 2017 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | Old | 29 Jul 2017 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | Old | 29 Jul 2017 ↗ |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | Old | 29 Jul 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | YES |
| Fire safety (as filed with RERA) | YES |
| Health service | Sewerage, Drainage & Water Supply System provided as per norms |
| Renewable energy | PROVISION OF SOLAR WATER HEATING SYSTEM |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
24 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
24 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 32.3% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 32.3% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 32.3% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 32.3% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | R. R. Civil Tech Pvt Ltd |
| Role | Promoter · current |
| RERA ID | UPRERAPRM5860 |
| PAN | AADCR8302A |
| CIN / TAN | U45400UP2008PTC034469 |
| Name of chairman | Rahul Agarwal |
| Registered address | Ground Floor, Raja Ram Kumar Plaza, 75 Hazratganj, Lucknow - 226001 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | R R Civiltech Private Bliss Delight Bliss Delight (Coll)BankIndian BankBranchHazratganj, LucknowBranch addressHazratganj, LucknowBranch districtLucknow, Uttar PradeshA/C no.IFSCIDIBOOOH561 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | R R Civiltech Private Bliss Delight Bliss Delight (Rera)BankIndian BankBranchHazratganj, LucknowBranch addressHazratganj, LucknowBranch districtLucknow, Uttar PradeshA/C no.IFSCIDIBOOOH561 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | R R Civiltech Private Bliss Delight Bliss Delight (Expe)BankIndian BankBranchHazratganj, LucknowBranch addressHazratganj, LucknowBranch districtLucknow, Uttar PradeshA/C no.IFSCIDIBOOOH561 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 8 (Under Registration - 0 ) → 56 (Under Registration - 0 ) changed in Estanzo’s record | 21 Sept 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 21 Sept 2026 |
Common questions about ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC
Is ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC RERA registered?
Yes. ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC is registered with UPRERA under registration number UPRERAPRJ4754, registered on 29 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC?
The completion date filed with UPRERA is 28 Mar 2026. No completion certificate is on record yet.
Who is the builder of ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC?
R. R. Civil Tech Pvt Ltd is the promoter entity that filed ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC with UPRERA (promoter RERA ID UPRERAPRM5860). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC more time to complete?
UPRERA's record carries 2 completion extensions for ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC, the latest running to 28 Mar 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC located?
ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC is registered in Lucknow, as filed with UPRERA.
What configurations are available in ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC?
The unit plan filed with UPRERA lists 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
How many towers and units are planned in ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC?
The approved unit plan describes 4 blocks and 448 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is ANSALAPI-BLISS DELIGHT, BLOCK-1,2,3 & 4, GH-2, SEC?
About 112 units per acre: 448 planned units across 4.00 acres (16,200 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗