Armaan Muskan

UPRERARegistered

Armaan Muskan is a RERA-registered residential project by M/s Shalimar KSMB Projects in Lucknow (RERA ID UPRERAPRJ717215). Registered with a completion deadline of 30 Sept 2024.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ717215
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start10 Nov 2020
Project duration47 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typePartnership Firm
Applicant addressTitanium Block Shalimar Corporate Park Vibhuti Khand Gomti Nagar Lucknow
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MAP20190701124636830

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  7. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered21 Nov 2020
Original completion5 Nov 2023
Revised completion30 Sept 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary19 Nov 2024
Registration fee₹48,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors232 · 2 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK23230-35
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
EWS · 1 BHK411630
LIG · 1 BHK411635
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
MM Architecture
License CA/2011/53000
D-102, Chhatarpur, New Delhi -110074
Engineer
C.S. Bhandari
Pocket-3, Sector 14,Dwarka-110078
Contractor
SA Construction
D 2/46-47,Shyama Shiv Square ,Vibhuti khand ,Gomti Nagar, Lucknow-226010
Sr.Development work declared to RERA
1Demarcation of Plots
This is single plot rhombus shaped , having total 1 no. of entry gate and 1 no. of exit gate from the 12 m wide front road and 5m and 6m internal roads. Site is surrounded by other plot on south , west and east sides.
2Boundary Wall
3.0 -3.6 m high and 230 mm thick boundary wall designed. Brick Work of inches and RCC work in column and beam may be used as per design. MS Board entrance and exit gates are developed with boundary.
3Road Work
Road with bituminous Cover/ High quality concrete pavers will be used as per design suggested by the Architect for internal road.
4Footpaths
All internal roads will have narrow footpath cement stone pavers or equivalent finishes.
5Water Supply Including Drinking Water Facilities
Ground Water will be used. End user will use their individual RO System as per their requirement. Overhead tanks shall be provided on building terrace for distribution through gravity.
6Sewer System
Centralized sewerage system shall be provided. All sewerage water shall be go to the STP for treatment. After treatment water shall be recycle and it will used in gardening , vehicle washing , overflow from the STP shall be connected with the Municipal sewerage system.
7Drain
Storm water system shall be provided. Storm water from the roads and other landscape area shall be connect to the storm water drain channel and go to the Rain water harvesting pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
There is one park area provided beside the plot.
9Tree Planting
Tree plantation shall be as per applicable norms to maintain greenary and natural view.
10Design For Electric Supply Including Street Lighting
We have designed the system as per Local electricity board and consider centralized Transformer, HT Panel, LT Panel, Feeder Pillar and back up common service like External lighting , STP, Pump room , etc.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Centralized sewerage system shall be provided. All sewerage water shall be go to the STP for treatment after tretament , water shall be recycle and it will use in gardening and vehicle washing, overflowform the STP shall be connect with the Municipal sewerage system.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
A well designed rain water harvesting system shall be provided for the solid waste management.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In STP and Pump room all the equipment shall have energy efficient motor.
16Fire Protection And Fire Safety System
All fire safety norms shall be complied.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Sewerage, Storm water and water supply system shall be provided. We have proposed common pump room , Transfer pumps to fill the domestic tanks . Water for domestic use and flushing go down through gravity from tanks. All sewage shall be go to the STP for recycling the water. Storm water for roofs, roads and other area shall be connect to the Storm water drain channel and go to the Rain water harvesting pit for recharge the Ground water and overflow shall be connect with Municipal drain.
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 30 Sept 2024.

Sanctioned by Lucknow Development Authority · 8,501 sqm of land · an approved plan of 2 blocks and 232 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MAP201907011246368301 Oct 201930 Sept 202430 Sept 20275 Nov 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Sept 2024.

#Granted fromExtended uptoNote
15 Nov 202330 Sept 2024—

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
2,3- Village Ghaila and No. 5- village Alinagar8501.36Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 410
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 14732
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 15534
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Reply against notice received
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Electricity Supply Plan and Layout plan showing STP
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Bank statement
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Affidavit
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 Oct 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New1 Oct 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New28 Sept 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New28 Sept 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New28 Sept 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New28 Sept 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New1 Oct 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 Sept 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New1 Oct 2020 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New21 Oct 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New28 Sept 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Sept 2020 ↗

Quarterly progress reports

16 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

16 quarterly progress reports are on file with UPRERA, covering 2020-Q3 to 2024-Q2.

QuarterConstructionCertificates
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameM/s Shalimar KSMB Projects
RolePromoter · current
RERA IDUPRERAPRM10366
PANACFFS5832H
CIN / TANLKNS11272C
Registered addressTitanium Block Shalimar Corporate Park Vibhuti Khand Gomti Nagar Lucknow
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Shalimar KSMB ProjectsBankPunjab National BankBranchVivek Khand Gomti Nagar LucknowA/C no.IFSCORBC0100687
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Armaan Muskan

Is Armaan Muskan RERA registered?

Yes. Armaan Muskan is registered with UPRERA under registration number UPRERAPRJ717215, registered on 21 Nov 2020. Estanzo reproduces that filing; it does not verify the work behind it.

Has Armaan Muskan been completed?

UPRERA still lists Armaan Muskan as Registered, so it is not shown as completed here. A completion certificate dated 19 Nov 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Armaan Muskan?

M/s Shalimar KSMB Projects is the promoter entity that filed Armaan Muskan with UPRERA (promoter RERA ID UPRERAPRM10366). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Armaan Muskan more time to complete?

UPRERA's record carries 1 completion extension for Armaan Muskan, the latest running to 30 Sept 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Armaan Muskan have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Armaan Muskan located?

Armaan Muskan is registered in Lucknow, as filed with UPRERA.

What configurations are available in Armaan Muskan?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Armaan Muskan?

The approved unit plan filed with UPRERA runs from 30 to 35 m² of carpet area (about 327 to 382 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Armaan Muskan?

The approved unit plan describes 2 blocks and 232 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Armaan Muskan?

About 110 units per acre: 232 planned units across 2.10 acres (8,501 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗