Registered19 Apr 2018
Promised30 Sept 2021
Completed14 Dec 2023

Timeline

Promised completion30 Sept 2021
Revised completion30 Sept 2021
Actual completion14 Dec 2023
Possession delay26 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,39,000
Project cost (in ₹ Lakhs)₹7,000 Lakhs
Project duration66 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Apr 2018

Inventory

Total units306660
Unit TypeUnitsCarpet Area (sqm)
2 BHK7668456.99
3 BHK22997666.8–87.17

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582282266
EmailAROCONGOLFVILLE@GMAIL.COM
Coordinator9582282277
AddressAROCON RAINBOW to be set up at Plot no GH-02, Block – H, Jaipuria Sunrise Greens, Vill. Shahpur Bamheta, District-Ghaziabad, Uttar Pradesh-201001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
65/ZONE-5/2014-1529 Sept 201428 Sept 201930 Sept 202128 Sept 2022
65/ZONE-5/2014-1529 Sept 201428 Sept 201930 Sept 202128 Sept 2022

Land Parcels

Khasra No.AreaPlot Type
14412140
1466253
1467890
14681010
14691380
14701150
1471264
14412140Khasra
1466253Khasra
1467890Khasra
14681010Khasra
14691380Khasra
14701150Khasra
1471264Khasra

Approved Unit Plan

Unit plan rows on file304
Total flats (sum of rows)306660
BlocksR1-A, R1-B
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
62730 Jan 2015

Frequently Asked Questions

What is the RERA registration number of AROCON RAINBOW?

The RERA registration number of AROCON RAINBOW is UPRERAPRJ15768, as recorded on the UP-RERA portal.

What is the RERA status of AROCON RAINBOW?

As reported by UP-RERA, the status of AROCON RAINBOW is "Registered".

Where is AROCON RAINBOW located?

As reported to UP-RERA, AROCON RAINBOW is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is AROCON RAINBOW completed?

As reported to UP-RERA, AROCON RAINBOW was completed on 14 Dec 2023.

Is AROCON RAINBOW delayed?

Measured against the latest completion date reported to UP-RERA, AROCON RAINBOW is 26 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026