Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ2833
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Apr 2017
Original start1 Apr 2017
Project duration84 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressThe Golden Gate, H-1, NH-24, Jaipuria Sunrise Greens, Opp Columbia Aisa Hospital, Ghaziabda, UP-201002
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated

    65/ZONE-5/2014-15

  2. 4 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. valid to

    Permit revalidated

    G.O.N/4/2020/693

  9. to

    Extension granted

  10. Completion certificate filed

  11. Completion certificate filed

  12. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion31 Dec 2021
Revised completion28 Mar 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary4 Feb 2024
Registration fee₹31,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors228 · 2 · 19 (units from plan)
  • 2 BHK152 67%
  • 3 BHK76 33%
ConfigurationUnitsCarpet area
2 BHK15261-68
3 BHK7682-95
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
K1 · 2 BHK, 3 BHK1911461-95
K2 · 2 BHK, 3 BHK1911461-95
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Gaurav Singla
License CA/2012/55623
H-169, Sector-63, Noida
Engineer
V. D. Sharma
2/335, VASUNDHARA, Ghaziabad
Contractor
M/s Shakya Super Construction Pvt Ltd
53, Basement, Vinobapuri, Lajpat Nagar-II, New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
As per sanctioned plan
2Boundary Wall
As per sanctioned plan
3Road Work
As per sanctioned plan
4Footpaths
As per sanctioned plan
5Water Supply Including Drinking Water Facilities
As per sanctioned plan
6Sewer System
As per sanctioned plan
7Drain
As per sanctioned plan
8Parks
As per sanctioned plan
9Tree Planting
As per sanctioned plan
10Design For Electric Supply Including Street Lighting
As per sanctioned plan
11Community Buildings
As per sanctioned plan
12Treatment and Disposal System of Sewage and Sullage water
As per sanctioned plan
13Solid Waste Management And Disposal System
As per sanctioned plan
14Water Conservation System
As per sanctioned plan
15Energy Management System Including Use of Renewable Energy
As per sanctioned plan
16Fire Protection And Fire Safety System
As per sanctioned plan
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per sanctioned plan
18Emergency Evacuation Services
As per sanctioned plan
19Other Miscellaneous Work
As per sanctioned plan
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

4 permits

An approval and the date it runs to - not proof the work matching it was done.

4 sanctioning permits are on record with UPRERA, the latest valid to 30 Jun 2019. 2 of them carry a revalidation, the latest valid to 30 Jun 2022.

Sanctioned by Ghaziabad Development Authority · 5,176 sqm of land · an approved plan of 2 blocks and 228 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
65/ZONE-5/2014-151 Jul 201430 Jun 201930 Jun 202228 Mar 2024—
65/ZONE-5/2014-151 Jul 201430 Jun 201930 Jun 202228 Mar 2024—
65/ZONE-5/2014-151 Jul 201430 Jun 201930 Jun 202228 Mar 20241 Jul 2014
65/ZONE-5/2014-151 Jul 201430 Jun 201930 Jun 202328 Mar 202430 Jun 2022
valid to 30 Jun 2022
as G.O.N/4/2020/693
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 28 Mar 2024.

#Granted fromExtended uptoNote
131 Dec 202130 Jun 2022Six months extension in view of force majeure caused by covid-19 pandemic
230 Jun 202229 Jun 2023—
329 Jun 202328 Mar 2024—

Land & documents

24 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1461146—
1463790—
14741140—
15001500—
15011600—
1461146Khasra
1463790Khasra
14741140Khasra
15001500Khasra
15011600Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 30 Jan 2015.

Registry no.DateTypeArea
62830 Jan 2015self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 628
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 Mar 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New26 Dec 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New26 Dec 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New26 Dec 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New26 Dec 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New26 Dec 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New26 Dec 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New27 Dec 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New1 Mar 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New1 Mar 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New1 Mar 2021 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old26 Oct 2017 ↗

Quarterly progress reports

16 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

16 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePARAKH INFRASTRUCTURE PVT LTD
RolePromoter · current
RERA IDUPRERAPRM4558
PANAAECP5324R
CIN / TANU45400DL2008PTC172982
Name of chairmanNEERAJ GOEL-DIRECTORRAVI JAIN -DIRECTOR
Registered addressThe Golden Gate, H-1, NH-24, Jaipuria Sunrise Greens, Opp Columbia Aisa Hospital, Ghaziabda, UP-201002
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
PARAKH INFRASTRUCTURE PVT LTDBankIDBI BANK LTDBranchC-1 LOHIYA NAGAR GHAZIABAD 201001A/C no.IFSCIBKL0001121
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about THE GOLDEN GATE

Is THE GOLDEN GATE RERA registered?

Yes. THE GOLDEN GATE is registered with UPRERA under registration number UPRERAPRJ2833, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has THE GOLDEN GATE been completed?

UPRERA still lists THE GOLDEN GATE as Registered, so it is not shown as completed here. A completion certificate dated 4 Feb 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of THE GOLDEN GATE?

PARAKH INFRASTRUCTURE PVT LTD is the promoter entity that filed THE GOLDEN GATE with UPRERA (promoter RERA ID UPRERAPRM4558). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted THE GOLDEN GATE more time to complete?

UPRERA's record carries 3 completion extensions for THE GOLDEN GATE, the latest running to 28 Mar 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does THE GOLDEN GATE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is THE GOLDEN GATE located?

THE GOLDEN GATE is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in THE GOLDEN GATE?

The unit plan filed with UPRERA lists 2 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in THE GOLDEN GATE?

The approved unit plan filed with UPRERA runs from 61 to 95 m² of carpet area (about 656 to 1,025 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in THE GOLDEN GATE?

The approved unit plan describes 2 blocks and 228 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is THE GOLDEN GATE?

About 178 units per acre: 228 planned units across 1.28 acres (5,176 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗