Estanzo

Timeline Bar

Registered1 Aug 2017
Promised31 Dec 2021
Today3 Aug 2026

Timeline

Promised completion31 Dec 2021
Revised completion31 Dec 2021
Actual completion
Possession delay55 mo delay

Registration & Cost Details

Registration fee (in ₹)₹95,000
Project cost (in ₹ Lakhs)₹31,797 Lakhs
Project duration88 months
Project categoryResidential
Locality
Original start date1 Mar 2016
Proposed start date1 Mar 2016

Inventory

Total units352
Unit TypeUnitsCarpet Area (sqm)
3 BHK336105.82–111.67
4 BHK8221.3–224.83
PENTHOUSE8394.93

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailhousing@atsgreens.com
Coordinator9643007884
AddressATS Tower, Plot-16, Sector-135, Noida-201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/2015/IV-1398/82315 Sept 201514 Sept 202031 Dec 202114 Sept 2025

Land Parcels

Khasra No.AreaPlot Type
PLOT NO-SC-1/A-1, SECTOR-150, NOIDA, UP17967Plot

Approved Unit Plan

Unit plan rows on file28
Total flats (sum of rows)352
BlocksTower P1, P2,P3 & P4
Floor types3 BHK, 4 BHK, PENTHOUSE, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
39339 Apr 2013

Frequently Asked Questions

What is the RERA registration number of ATS PRISTINE-PHASE-II?

The RERA registration number of ATS PRISTINE-PHASE-II is UPRERAPRJ2875, as recorded on the UP-RERA portal.

What is the RERA status of ATS PRISTINE-PHASE-II?

As reported by UP-RERA, the status of ATS PRISTINE-PHASE-II is "Registered".

Where is ATS PRISTINE-PHASE-II located?

As reported to UP-RERA, ATS PRISTINE-PHASE-II is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will ATS PRISTINE-PHASE-II be completed?

The latest completion date reported to UP-RERA for ATS PRISTINE-PHASE-II is 31 Dec 2021.

Is ATS PRISTINE-PHASE-II delayed?

Measured against the latest completion date reported to UP-RERA, ATS PRISTINE-PHASE-II is 55 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026