Timeline Bar

Registered11 Jun 2019
Promised4 Dec 2024
Completed8 Jul 2026

Timeline

Promised completion4 Dec 2024
Revised completion4 Dec 2024
Actual completion8 Jul 2026
Possession delay19 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,72,500
Project cost (in ₹ Lakhs)₹53,428 Lakhs
Project duration70 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Sept 2019

Inventory

Total units451
Unit TypeUnitsCarpet Area (sqm)
1 BHK2055.81–58.02
2 BHK13871.62–109.98
3 BHK180111.68–135.17
4 BHK92176.75
SHOP2110.29–30.97

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8588806417
Emailsumit.tuli@acegroupindia.com
Coordinator8800010790
Helpline01202487200
Address01-B, Sector-126, Noida, U.P.

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Noida/MU.VA.NI/2019/IV-1485/112115 May 201914 May 20244 Dec 202413 May 2029

Land Parcels

Khasra No.AreaPlot Type
SC-02/F58064.71Plot

Approved Unit Plan

Unit plan rows on file201
Total flats (sum of rows)451
Total shops21
BlocksTOWER A5, TOWER B1, TOWER B2, TOWER B3, TOWER A1, TOWER A3, TOWER A4, TOWER B5, TOWER E, TOWER ICONIC A2, TOWER ICONIC B4
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, SHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Godrej Palm Retreat 1?

The RERA registration number of Godrej Palm Retreat 1 is UPRERAPRJ745601, as recorded on the UP-RERA portal.

What is the RERA status of Godrej Palm Retreat 1?

As reported by UP-RERA, the status of Godrej Palm Retreat 1 is "Registered".

Where is Godrej Palm Retreat 1 located?

As reported to UP-RERA, Godrej Palm Retreat 1 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Godrej Palm Retreat 1 completed?

As reported to UP-RERA, Godrej Palm Retreat 1 was completed on 8 Jul 2026.

Is Godrej Palm Retreat 1 delayed?

Measured against the latest completion date reported to UP-RERA, Godrej Palm Retreat 1 is 19 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026