Estanzo

Timeline Bar

Registered12 Aug 2017
Promised30 Sept 2018
Completed27 Jun 2023

Timeline

Promised completion30 Sept 2018
Revised completion30 Sept 2018
Actual completion27 Jun 2023
Possession delay57 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,22,000
Project cost (in ₹ Lakhs)₹6,413 Lakhs
Project duration50 months
Project categoryResidential
Locality
Original start date15 Jun 2011
Proposed start date11 Aug 2014

Inventory

Total units836
Unit TypeUnitsCarpet Area (sqm)
1 BHK83626.22

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9811005579
Emailceo@gnida.in
Coordinator9717597709
AddressPLOT NO-01, KNOWLEDGE PARK-04, GREATER NOIDA, G.B. NAGAR UP

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP-4044)/GH/520914 Aug 201713 Aug 202230 Sept 201813 Aug 2022

Land Parcels

Khasra No.AreaPlot Type
11
27919974Khasra
27820771Khasra
41111311Khasra
4136709Khasra
4082364Khasra

Approved Unit Plan

Unit plan rows on file209
Total flats (sum of rows)836
BlocksBlock A Tower 1, Block A Tower 10, Block A Tower 11, Block A Tower 12, Block A Tower 13, Block A Tower 14, Block A Tower 15, Block A Tower 16, Block A Tower 17, Block A Tower 18, Block A Tower 2, Block A Tower 3, Block A Tower 4, Block A Tower 5, Block A Tower 6, Block A Tower 7, Block A Tower 8, Block A Tower 9, Block B Tower 1, Block B Tower 10, Block B Tower 11, Block B Tower 12, Block B Tower 13, Block B Tower 14, Block B Tower 15, Block B Tower 16, Block B Tower 2, Block B Tower 3, Block B Tower 4, Block B Tower 5, Block B Tower 6, Block B Tower 7, Block B Tower 8, Block B Tower 9, Block C Tower 1, Block C Tower 10, Block C Tower 11, Block C Tower 12, Block C Tower 13, Block C Tower 14, Block C Tower 15, Block C Tower 16, Block C Tower 17, Block C Tower 18, Block C Tower 2, Block C Tower 3, Block C Tower 4, Block C Tower 5, Block C Tower 6, Block C Tower 7, Block C Tower 8, Block C Tower 9
Floor types1 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
NA1 Aug 2017
na1 Aug 2017

Frequently Asked Questions

What is the RERA registration number of BHS-14 EWS XU-3?

The RERA registration number of BHS-14 EWS XU-3 is UPRERAPRJ10006, as recorded on the UP-RERA portal.

What is the RERA status of BHS-14 EWS XU-3?

As reported by UP-RERA, the status of BHS-14 EWS XU-3 is "Registered".

Where is BHS-14 EWS XU-3 located?

As reported to UP-RERA, BHS-14 EWS XU-3 is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

Is BHS-14 EWS XU-3 completed?

As reported to UP-RERA, BHS-14 EWS XU-3 was completed on 27 Jun 2023.

Is BHS-14 EWS XU-3 delayed?

Measured against the latest completion date reported to UP-RERA, BHS-14 EWS XU-3 is 57 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026