Registered27 Jan 2022
Promised1 Dec 2023
Completed29 Jul 2024

Timeline

Promised completion1 Dec 2023
Revised completion1 Dec 2023
Actual completion29 Jul 2024
Possession delay8 mo delay

Registration & Cost Details

Registration fee (in ₹)₹17,600
Project cost (in ₹ Lakhs)₹500 Lakhs
Project duration24 months
Project categoryCommercial
Locality
Original start date
Proposed start date2 Dec 2021

Inventory

Total units55
Unit TypeUnitsCarpet Area (sqm)
SHOP555.176–130.041

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9311606012
Emailinfo@capitalathena.com
Coordinator9311606012
AddressPLOT NO- GH-12A-2, SECTOR-01, GREATER NOIDA (WEST), GAUTAM BUDH NAGAR, U.P.-201306

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP)-3090S/28325 Aug 20214 Aug 20261 Dec 20234 Aug 2026

Land Parcels

Khasra No.AreaPlot Type
GH-12A/2, SECTOR-1, GREATER NOIDA, U.P.33941.79Plot

Approved Unit Plan

Unit plan rows on file19
Total flats (sum of rows)55
Total shops55
BlocksCOMMERCIAL
Floor typesSHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of CAPITAL ATHENA PHASE-3 COMMERCIAL?

The RERA registration number of CAPITAL ATHENA PHASE-3 COMMERCIAL is UPRERAPRJ967323, as recorded on the UP-RERA portal.

What is the RERA status of CAPITAL ATHENA PHASE-3 COMMERCIAL?

As reported by UP-RERA, the status of CAPITAL ATHENA PHASE-3 COMMERCIAL is "Registered".

Where is CAPITAL ATHENA PHASE-3 COMMERCIAL located?

As reported to UP-RERA, CAPITAL ATHENA PHASE-3 COMMERCIAL is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is CAPITAL ATHENA PHASE-3 COMMERCIAL completed?

As reported to UP-RERA, CAPITAL ATHENA PHASE-3 COMMERCIAL was completed on 29 Jul 2024.

Is CAPITAL ATHENA PHASE-3 COMMERCIAL delayed?

Measured against the latest completion date reported to UP-RERA, CAPITAL ATHENA PHASE-3 COMMERCIAL is 8 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.