Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ14724
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAllahabad Development Authority
Proposed start30 Dec 2017
Project duration60 months
AddressPhulpur, Prayagraj
TehsilPhulpur
Applicant typePartnership Firm
Applicant addressSAHYOG BHAWAN, 1 MG MARG, CIVIL LINES, ALLAHABAD
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. 2 building permits sanctioned

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. to

    Extension granted

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  9. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered29 Dec 2017
Original completion30 Dec 2020
Revised completion21 Dec 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary17 Jun 2023
Registration fee₹42,000
Sanctioning authorityAllahabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 1 · 8 (from plan)
ConfigurationUnitsCarpet area
1 BHK—390-410
2 BHK—665
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
ONE · 1 BHK, 2 BHK8—390-665
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
MANISH GUJRAL
License CA/97/21380
DESIGN STUDIO, 52/25B, MUIR ROAD, ALLAHABAD
Engineer
DR SANTOSH KUMAR
7/120 (B), THE HERITAGE, SWAROOP NAGAR, KANPUR 208002
Sr.Development work declared to RERA
1Demarcation of Plots
Yes
2Boundary Wall
YES
3Road Work
YES
4Footpaths
YES
5Water Supply Including Drinking Water Facilities
Through borewell
6Sewer System
PACKEGED STP
7Drain
YES
8Parks
YES
9Tree Planting
50 nos trees to be planted
10Design For Electric Supply Including Street Lighting
YES
11Community Buildings
yes
12Treatment and Disposal System of Sewage and Sullage water
as per NBC norms
13Solid Waste Management And Disposal System
as per NBC norms
14Water Conservation System
as per NBC norms
15Energy Management System Including Use of Renewable Energy
as per NBC norms
16Fire Protection And Fire Safety System
as per NBC norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
Available in the vacinity
18Emergency Evacuation Services
as per NBC norms
19Other Miscellaneous Work
as per NBC norms
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 23 Nov 2022.

Sanctioned by Allahabad Development Authority · 7,363 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
37/PR AA (TA SA-2)/ZONE-5/GR HA/2015-1623 Dec 201723 Nov 202223 Nov 202530 Dec 2020
37/PR AA (TA SA-2)/ZONE-5/GR HA/2015-1623 Dec 201723 Nov 202223 Nov 202530 Dec 2020
Plans and approvals filed with RERA
DocumentFile
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 21 Dec 2022.

#Granted fromExtended uptoNote
130 Dec 202029 Jun 2021Six months extension in view of force majeure caused by covid-19 pandemic
229 Jun 202128 Jun 2022—
328 Jun 202221 Dec 2022—

Land & documents

8 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
432M9730—
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 10 Jun 2016.

Registry no.DateTypeArea
01/5833/317-442/494710 Jun 2016self—
Document checklist
DocumentStatusUploaded
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New30 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New9 May 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New9 May 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New9 May 2020 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old29 Dec 2017 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old29 Dec 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old8 Jan 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterYES
Fire safety (as filed with RERA)YES
Health serviceYES
Renewable energyYES
Other facilitiesSTP, LIFT, GYM

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2022-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameCITIZEN SHUBHALAY INFRABUILD LLP
RolePromoter · current
RERA IDUPRERAPRM32253
PANAAFCC8707J
Registered addressSAHYOG BHAWAN, 1 MG MARG, CIVIL LINES, ALLAHABAD
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
CITIZEN SHUBHALAY INFRABUILD LLPBankALLAHABAD BANKBranchHINDI SAHITYA SAMMELAN ALLAHABADA/C no.IFSCALLA0210695
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about CITIZEN SHUBHALAY

Is CITIZEN SHUBHALAY RERA registered?

Yes. CITIZEN SHUBHALAY is registered with UPRERA under registration number UPRERAPRJ14724, registered on 29 Dec 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has CITIZEN SHUBHALAY been completed?

UPRERA still lists CITIZEN SHUBHALAY as Registered, so it is not shown as completed here. A completion certificate dated 17 Jun 2023 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of CITIZEN SHUBHALAY?

CITIZEN SHUBHALAY INFRABUILD LLP is the promoter entity that filed CITIZEN SHUBHALAY with UPRERA (promoter RERA ID UPRERAPRM32253). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted CITIZEN SHUBHALAY more time to complete?

UPRERA's record carries 3 completion extensions for CITIZEN SHUBHALAY, the latest running to 21 Dec 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does CITIZEN SHUBHALAY have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CITIZEN SHUBHALAY located?

CITIZEN SHUBHALAY is registered in Prayagraj, as filed with UPRERA.

What configurations are available in CITIZEN SHUBHALAY?

The unit plan filed with UPRERA lists 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in CITIZEN SHUBHALAY?

The approved unit plan filed with UPRERA runs from 390 to 665 m² of carpet area (about 4,198 to 7,158 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗