Estanzo

Timeline Bar

Registered2 Mar 2024
Today29 Jul 2026
Promised31 Oct 2028

Timeline

Promised completion31 Oct 2028
Revised completion31 Oct 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹57,000
Project cost (in ₹ Lakhs)₹9,820 Lakhs
Project duration59 months
Project categoryResidential
LocalityChandler Bichpuri, Bareilly
Original start date
Proposed start date1 Dec 2023

Inventory

Total units372
Unit TypeUnitsCarpet Area (sqm)
1 BHK12030.02–35.45
2 BHK14347.88–57.16
3 BHK8172.8–78.11
4 BHK2789.09–89.58
SHOP175.02

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9837090006
Emailambersunshinehomes@gmail.com
Coordinator9837090006
Helpline9837054455
AddressBisalpur Road, Opp. Sai Mandir, Bareilly

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q218.3%
2025-Q321.5%
2025-Q423.1%
2026-Q124.4%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
02132/BDA/BP/23-24/0283/0711202316 Nov 202315 Nov 202831 Oct 202815 Nov 2028

Land Parcels

Khasra No.AreaPlot Type
1246850Khasra
1234060Khasra

Approved Unit Plan

Unit plan rows on file372
Total flats (sum of rows)372
Total shops1
BlocksAQUA, AROMA
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of CITY TOWERS?

The RERA registration number of CITY TOWERS is UPRERAPRJ388540, as recorded on the UP-RERA portal.

What is the RERA status of CITY TOWERS?

As reported by UP-RERA, the status of CITY TOWERS is "Registered".

Where is CITY TOWERS located?

As reported to UP-RERA, CITY TOWERS is located at Khasra no. 124, 123(part), Vill Chandler Bichpuri, Adjacent Ram Ganga Nagar, BAREILLY, Chandler Bichpuri, Bareilly, Bareilly, Bareilly, Uttar Pradesh.

When will CITY TOWERS be completed?

The latest completion date reported to UP-RERA for CITY TOWERS is 31 Oct 2028.

Is CITY TOWERS delayed?

Measured against the latest completion date reported to UP-RERA, CITY TOWERS is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026