Timeline Bar
Registered12 Mar 2021
Promised18 Jan 2023
Completed30 Mar 2023
Timeline
Promised completion18 Jan 2023
Revised completion18 Jan 2023
Actual completion30 Mar 2023
Possession delay2 mo delay
Registration & Cost Details
Registration fee (in ₹)₹40,500
Project cost (in ₹ Lakhs)₹350 Lakhs
Project duration24 months
Project categoryMixed
Locality—
Original start date—
Proposed start date19 Jan 2021
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9897073073
Emailjhminfrahomes@gmail.com
Coordinator6396119757
Addresskhasra no 498 and 500 Chandpur Bichpuri, Dohra Road, BAREILLY 243006
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| PRD/PH/00050/BDA/LD/20-21/0085/22092020 | 19 Jan 2021 | 18 Jan 2026 | 18 Jan 2023 | 18 Jan 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 494 | 2230 | Khasra |
| 495 | 2230 | Khasra |
Frequently Asked Questions
What is the RERA registration number of JHM JOY?
The RERA registration number of JHM JOY is UPRERAPRJ992048, as recorded on the UP-RERA portal.
What is the RERA status of JHM JOY?
As reported by UP-RERA, the status of JHM JOY is "Registered".
Where is JHM JOY located?
As reported to UP-RERA, JHM JOY is located at Bareilly, Bareilly, Uttar Pradesh.
Is JHM JOY completed?
As reported to UP-RERA, JHM JOY was completed on 30 Mar 2023.
Is JHM JOY delayed?
Measured against the latest completion date reported to UP-RERA, JHM JOY is 2 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026