Estanzo

Timeline Bar

Registered14 Sept 2020
Promised25 Jun 2025
Today4 Aug 2026

Timeline

Promised completion25 Jun 2025
Revised completion25 Jun 2025
Actual completion
Possession delay13 mo delay

Registration & Cost Details

Registration fee (in ₹)₹42,500
Project cost (in ₹ Lakhs)₹1,732 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date
Proposed start date26 Jun 2020

Inventory

Total units264
Unit TypeUnitsCarpet Area (sqm)
1 BHK26422.7–22.77

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile7455025100
Emailhpda_1@rediffmail.com
Coordinator9068673222
AddressPREET VIHAR DELHI ROAD HAPUR UP 245101 INDIA

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2022-Q1
2022-Q2
2022-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
286/C.E./HPDA/2020 Dated-03/09/202026 Jun 202025 Jun 202525 Jun 202525 Jun 2028

Land Parcels

Khasra No.AreaPlot Type
538000.00Khasra

Approved Unit Plan

Unit plan rows on file24
Total flats (sum of rows)264
BlocksA, B, C, D, E, F
Floor types1 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Construction of 264 EWS Houses Hindalpur Hapur Under PMAY?

The RERA registration number of Construction of 264 EWS Houses Hindalpur Hapur Under PMAY is UPRERAPRJ805692, as recorded on the UP-RERA portal.

What is the RERA status of Construction of 264 EWS Houses Hindalpur Hapur Under PMAY?

As reported by UP-RERA, the status of Construction of 264 EWS Houses Hindalpur Hapur Under PMAY is "Registered".

Where is Construction of 264 EWS Houses Hindalpur Hapur Under PMAY located?

As reported to UP-RERA, Construction of 264 EWS Houses Hindalpur Hapur Under PMAY is located at Dhaulana, Hapur, Uttar Pradesh.

When will Construction of 264 EWS Houses Hindalpur Hapur Under PMAY be completed?

The latest completion date reported to UP-RERA for Construction of 264 EWS Houses Hindalpur Hapur Under PMAY is 25 Jun 2025.

Is Construction of 264 EWS Houses Hindalpur Hapur Under PMAY delayed?

Measured against the latest completion date reported to UP-RERA, Construction of 264 EWS Houses Hindalpur Hapur Under PMAY is 13 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026