Estanzo

Timeline Bar

Registered2 Aug 2017
Promised30 Sept 2017
Completed15 Sept 2021

Timeline

Promised completion30 Sept 2017
Revised completion30 Sept 2017
Actual completion15 Sept 2021
Possession delay48 mo delay

Registration & Cost Details

Registration fee (in ₹)₹49,000
Project cost (in ₹ Lakhs)₹2,714 Lakhs
Project duration30 months
Project categoryResidential
Locality
Original start date16 Apr 2015
Proposed start date16 Apr 2015

Inventory

Total units198
Unit TypeUnitsCarpet Area (sqm)
1 BHK7232.27
2 BHK12646.63–52.77

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile7455025100
Emailhpda_1@rediffmail.com
Coordinator9761480602
AddressPREET VIHAR DELHI ROAD HAPUR UP 245101 INDIA

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
SELF APPROVED28 Jan 201531 Mar 201930 Sept 201731 Mar 2020

Land Parcels

Khasra No.AreaPlot Type
50, 52, 53 VILLAGE SABLI8703
50,52,538703Khasra

Approved Unit Plan

Unit plan rows on file18
Total flats (sum of rows)198
BlocksA, B, C
Floor types1 BHK, 2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
ACQUIRED11 Jul 2008

Frequently Asked Questions

What is the RERA registration number of CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT?

The RERA registration number of CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT is UPRERAPRJ7787, as recorded on the UP-RERA portal.

What is the RERA status of CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT?

As reported by UP-RERA, the status of CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT is "Registered".

Where is CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT located?

As reported to UP-RERA, CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT is located at Hapur, Hapur, Uttar Pradesh.

Is CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT completed?

As reported to UP-RERA, CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT was completed on 15 Sept 2021.

Is CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT delayed?

Measured against the latest completion date reported to UP-RERA, CONSTRUCTION OF AFFORDABLE MULTI STORIED HOUSES AT is 48 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026