Registration & Cost Details
Inventory
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 297 | 30.45–55.2 |
| 3 BHK | 64 | 89.61 |
Promoters & Contact
Contact Details
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| SELF APPROVED | 23 Feb 2016 | 31 Mar 2020 | 30 Sept 2017 | 31 Mar 2021 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 18, 21, 22, 23 VILLAGE SABLI | 15432 | — |
| 18, 21, 23 | 15432 | Khasra |
Approved Unit Plan
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| ACQUIRED | 11 Jul 2008 | — | — |
Frequently Asked Questions
What is the RERA registration number of CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE?
The RERA registration number of CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE is UPRERAPRJ8355, as recorded on the UP-RERA portal.
What is the RERA status of CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE?
As reported by UP-RERA, the status of CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE is "Registered".
Where is CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE located?
As reported to UP-RERA, CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE is located at Hapur, Hapur, Uttar Pradesh.
When will CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE be completed?
The latest completion date reported to UP-RERA for CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE is 30 Sept 2017.
Is CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE delayed?
Measured against the latest completion date reported to UP-RERA, CONSTRUCTION OF LIG, MIG & HIG HOUSES UNDER SABKE is 106 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.