Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'25
—Q2'25
1.22%Q3'25
8.7%Q4'25
23.91%Q1'26
37%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ652847
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryHapur Pilkhuwa Development Authority
Proposed start12 Feb 2025
Project duration47 months
AddressK-2(2) BLOCK-K, ANAND VIHAR AAWASIYA YOJANA, Hapur, Hapur
TehsilHapur
Applicant typeCompany
Applicant address679, Sector 23, Sonipat, Haryana-131001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    GROUPHOUSING/01582/HPDA/BP/24-25/0118/22112024

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered26 Apr 2025
Original completion31 Dec 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹2,62,000
Sanctioning authorityHapur Pilkhuwa Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 5 · 14 (from plan)
ConfigurationUnitsCarpet area
SHOP—74
3 BHK—120-479
4 BHK—138-276
1 BHK—74
OTHER—418-7,157
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
BASEMENT · OTHER2—6,930-7,157
TOWER-A · SHOP, 3 BHK, 4 BHK, 1 BHK12—74-276
TOWER-B · 4 BHK, 3 BHK12—240-479
TOWER-C · 3 BHK, OTHER, 4 BHK12—120-418
TOWER-D · 3 BHK, 4 BHK12—240-479
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
PUSP KUMAR SHARMA
License CA/2015/67013
C 4102 SPRING VIEW FLOOR SHAHPURBAMHETA NH-24 GHAZABAD UP
Engineer
JITENDRA KUMAR
2ND FLOOR ACHRYA NIKETAN MAYUR VIHAR DELHI
Contractor
SUNIL NAGAR
A-102 INDRAPURAM GHAZIABAD UP
Sr.Development work declared to RERA
1Demarcation of Plots
The Plot has 9607.45 sqm of the area that will be demarcated as per sanction and survey drawing
2Boundary Wall
The boundary wall will be prepared with RCC and Bricks with plaster
3Road Work
7.5 m wide access road to all tower will be provide and the road will be designed to take up live lode as per approvals and NBC
4Footpaths
designed footpaths in the project as a walkway and jogging track
5Water Supply Including Drinking Water Facilities
YEIDA authority shall supply water for the entire society and shall be treated and pumped to all the flat
6Sewer System
CENTRALIZED STP TO TREATE THE SEWAGE WILL BE DESIGNED AND PROVIDE
7Drain
Rain water drain will be provided as per the design to carry all the rain water of the complex in a ringline .the same will be connected to rain
8Parks
beautiful parks will be made for all resident to enjoy.the park will be relaxing and entertainment zones along with spaces meant for senior citizen,kids,and enjoyment.
9Tree Planting
as per approved building plan an apt no of tree will be provided.the tree will be a mix of evergreen anf flowering tree.they will be themed treen plantation and the complex will have a luch green outlook
10Design For Electric Supply Including Street Lighting
Power supply from uppcl as per approved electric plan the lighting will be adequate to lit up the dark spaces and all pathways as well as driveways.
11Community Buildings
The club will be made as per approved building plan and it will have all the modern facilities .social gathering place are also being providing in the project the resident will be able to enjoy in the club as a place for social gathering and relaxation.
12Treatment and Disposal System of Sewage and Sullage water
STP will treat all the sewages generat from the society and will be maintained
13Solid Waste Management And Disposal System
collection,stroage,and disposal will be done as per sanction and NBC.good to too collection of solid waste in the segregated system will be done so that the recyclable waste gan be separated in an efficient way from the wet kitchen waste.
14Water Conservation System
Rainwater harvesting system is being provided to conserve rainwater and a duel flush system will also provided with water saving fittings. 12 no of RWH pits proposed
15Energy Management System Including Use of Renewable Energy
usage of LED lights will be used all over the project and the use of solar lights will also be explored.
16Fire Protection And Fire Safety System
As per the approved building plan we will designed the best fire protection system consisting of sprinkler, smoke detectors and fire alarms.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Social gathering place are being provided in the project,Thease place will be spread over the whole complex and residents will be able to enjoy the same Swimming pool,GYM,Indoor play areas ,playing courts,all these facilities will be provided in the complex
18Emergency Evacuation Services
As per approved building plan and fire approvals fire staircase are being provided .all fire exit passages shall be kept clear all the time and proper audits as well as fire drills will be done in the society
19Other Miscellaneous Work
As per approved building plan any and all the works will be done to make the projects very comfortable and of good quality for all residents,the water bodies will be made in the complex to make it look more beautiful as well as a place to feel calm and relaxed.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 5 May 2030.

Sanctioned by Hapur Pilkhuwa Development Authority · 9,607.45 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
GROUPHOUSING/01582/HPDA/BP/24-25/0118/221120245 Feb 20255 May 20306 May 203031 Dec 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
K-2(2) ANAND VIHAR AWASIYA YOJANA9607.45Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 202400740021202
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Allotment letter from the authority · 1568/SAMPATI/H.D.P.A/24
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Nov 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New20 Mar 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New20 Mar 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New20 Mar 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Mar 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Mar 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Mar 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New9 Feb 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Mar 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New20 Mar 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New20 Mar 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New20 Mar 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New9 Feb 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New20 Mar 2025 ↗

Quarterly progress reports

7 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

7 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q2.

QuarterConstructionCertificates
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q21.22%CA ↗ · Arch ↗ · Eng ↗
2025-Q38.7%CA ↗ · Arch ↗ · Eng ↗
2025-Q423.91%CA ↗ · Arch ↗ · Eng ↗
2026-Q137%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameM AND M PROTECH PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM288243
PANAAQCM1524N
CIN / TANU45400HR2022PTC106318
Name of chairmanRAJINDER KUMAR MALIK
Registered address679, Sector 23, Sonipat, Haryana-131001
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
M AND M PROTECH PRIVATE LIMITED COLLECTION FOR M AND M ANANTA PROJECT K2(2) BLOCK K ANAND VIHAR AWAYSIYA YOJNA HAPURBankUNION BANK OF INDIABranchHAPUR MAIN BRANCHBranch addressNH 24 GARH ROAD PUCCA BAGH HAPURBranch districtHapur, Uttar PradeshA/C no.IFSCUBIN0530620Branch emailUBIN0530620@UNIONBANKOFINDIA.BANK
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
M AND M PROTECH PRIVATE LIMITED SEPARATE ACCOUNT FOR M AND M ANANTA PROJECT K 2 (2) BLOCK K ANAND VIHAR AAWASIYA YOJNA HAPURBankUNION BANK OF INDIABranchMAIN HAPURBranch addressNH 24 GARH ROAD PUCCA BAGH HAPURBranch districtHapur, Uttar PradeshA/C no.IFSCUBIN0530620
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
M AND M PROTECH PVT LTD TRANSACTION ACCOUNT FOR M AND M ANANTA PROJECT K 2 (2) BLOCK K ANAND VIHAR AAWASIYA YOJNA HAPURBankUNION BANK OF INDIABranchMAIN HAPURBranch addressNH 24 GARH ROAD PUCCA BAGH HAPURBranch districtHapur, Uttar PradeshA/C no.IFSCUBIN0530620
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
11 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR

Is M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR RERA registered?

Yes. M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR is registered with UPRERA under registration number UPRERAPRJ652847, registered on 26 Apr 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR?

The completion date filed with UPRERA is 31 Dec 2028. No completion certificate is on record yet.

Who is the builder of M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR?

M AND M PROTECH PRIVATE LIMITED is the promoter entity that filed M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR with UPRERA (promoter RERA ID UPRERAPRM288243). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR located?

M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR is registered in ANAND VIHAR AAWASIYA YOJANA, Hapur, as filed with UPRERA.

What configurations are available in M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR?

The unit plan filed with UPRERA lists SHOP, 3 BHK, 4 BHK, 1 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in M AND M ANANTA PROJECT K-2(2) BLOCK-K ANAND VIHAR AAWASIYA YOJNA HAPUR?

The approved unit plan filed with UPRERA runs from 74 to 7,157 m² of carpet area (about 800 to 77,037 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗