CYBER HUB 2

UPRERARegistered

CYBER HUB 2 is a RERA-registered commercial project by Galactic City Private Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ436071). Registered with a completion deadline of 31 Dec 2027. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
21%Q3'24
30%Q4'24
30%Q1'25
32%Q2'25
42.93%Q3'25
48.51%Q4'25
50.88%Q1'26
52.04%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ436071
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Oct 2023
Project duration51 months
AddressDadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant address1- Registered office Address- 9/100, Shastri Gali, Vishwas Nagar Shahdara, East Delhi, Delhi-110032. 2- Corporate Office Address- A-19, Sector-64, NOIDA 3- Site Office Address- Plot No.-6, Knowledge Park -V, Greater NOIDA , Gautam Budha Nagar.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG(BP)/3625/Plot No- 06/KP-5/1103

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. valid to

    Permit revalidated

    PLG/BP-SM-04-DEC-2024;23257

  7. Building permit sanctioned

    PLG/BP-SM-04-DEC-2024;23257

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered5 Apr 2024
Original completion26 Nov 2024
Revised completion31 Dec 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹2,47,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors6 · 3 · 2 (units from plan)
ConfigurationUnitsCarpet area
OTHER61,277-5,108
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
CYBER PARK 2(7) · OTHER221,277-5,108
CYBER PARK 2(8) · OTHER221,277-5,108
CYBER PARK 2(9) · OTHER221,277-5,108
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Homefolio Management LLP
License CA/2008/42568
UGF 03, Shakti Khand -2, Indrapuram , Ghaziabad UP 201014
Engineer
Constructive Ideas
B-0501, Block -B, Sethi Group , Max Royal, Sec - 76, Noida , GB Nagar 201301
Contractor
RADHA BUILDTECH INDIA PVT LTD
4/2885, Street No 01, Bihari Colony, Shahdra Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
18324 Sq.ft. built-up area to be developed.
2Boundary Wall
NA
3Road Work
Yes, RCC TRIMIX ROAD OR BITUMAN ROAD WITH KARBSTONE ON SIAD. STONE PAVING IN FRONT OF TOWER.
4Footpaths
YES, CEMENT CONCRETE STONE AND GRASS PAVERS.
5Water Supply Including Drinking Water Facilities
Yes , as per approved plan. GNOIDA water supply system collected in under ground water reservoirs and pumped to terrace tanks filled with Hydro penumatic.
6Sewer System
Yes, as per approved plan, RCC/DWC hume pipe with manhole chambers and collections to intend STP as per GNIDA requirement.
7Drain
Yes, as per approved plan. RCC drain water line will be use on project.
8Parks
Yes, Beautiful land scape with civil work with masonary and stone with horticultuer work and various types of planation.
9Tree Planting
Tree planting all along road in the project.
10Design For Electric Supply Including Street Lighting
Yes, as per approved plan.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Yes, S.T.P and through GNIDA sewerage system as applicable.
13Solid Waste Management And Disposal System
Yes, Organic waste convertor, collection bins and segregation table as per master plan. approved by GNIDA.
14Water Conservation System
Rain water harvesting pits drip irrigation with sprinklers as per master plan approved by GNIDA.
15Energy Management System Including Use of Renewable Energy
Yes, Solar Energy Lights in common area sand external area.
16Fire Protection And Fire Safety System
yes, Sprinklers system, Yard and sanitary facilites on stilt floor of every tower.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Yes, proper water supply and sanitary facilities on stilt floor of every tower.
18Emergency Evacuation Services
Yes, as per approved plan.
19Other Miscellaneous Work
na
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1SUMIRAM SAI REALTORSUPRERAAGT21812
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 16 Mar 2030. 1 of them carries a revalidation, valid to 16 Mar 2030.

Sanctioned by Greater Noida Authority · 10,241 sqm of land · an approved plan of 3 blocks and 6 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG(BP)/3625/Plot No- 06/KP-5/110315 Feb 201815 Sept 202326 Nov 202426 Nov 2024—
PLG/BP-SM-04-DEC-2024;2325711 Apr 202516 Mar 203016 Mar 203326 Nov 202411 Apr 2025
valid to 16 Mar 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 31 Dec 2027.

#Granted fromExtended uptoNote
126 Nov 202431 Dec 2027—

Land & documents

22 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
680961Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · ITPO330537
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · ITP0330537
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Khatauni extract · Demarcation Cyber Hub -2
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Lease deed · JDA
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New20 Nov 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New13 Sept 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New13 Sept 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New13 Sept 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New23 Mar 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New13 Sept 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New13 Sept 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New13 Sept 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 Oct 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New18 Nov 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New23 Jan 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New29 Dec 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Dec 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New4 Nov 2023 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q3 to 2026-Q1.

QuarterConstructionCertificates
2023-Q313%CA ↗ · Arch ↗ · Eng ↗
2023-Q416%CA ↗ · Arch ↗ · Eng ↗
2024-Q117%CA ↗ · Arch ↗ · Eng ↗
2024-Q221%CA ↗ · Arch ↗ · Eng ↗
2024-Q330%CA ↗ · Arch ↗ · Eng ↗
2024-Q430%CA ↗ · Arch ↗ · Eng ↗
2025-Q132%CA ↗ · Arch ↗ · Eng ↗
2025-Q242.93%CA ↗ · Arch ↗ · Eng ↗
2025-Q348.51%CA ↗ · Arch ↗ · Eng ↗
2025-Q450.88%CA ↗ · Arch ↗ · Eng ↗
2026-Q152.04%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGalactic City Private Limited
RolePromoter · current
RERA IDUPRERAPRM89371
PANAAGCG8599R
CIN / TANU70109DL2017PTC318378
Name of chairmanRishabh Jain
Registered address1- Registered office Address- 9/100, Shastri Gali, Vishwas Nagar Shahdara, East Delhi, Delhi-110032. 2- Corporate Office Address- A-19, Sector-64, NOIDA 3- Site Office Address- Plot No.-6, Knowledge Park -V, Greater NOIDA , Gautam Budha Nagar.
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameELEGANT IT SOLUTIONS PVT. LTD.
RoleCo-promoter
Applicant typeCompany
AddressT-9, Green Park Extn. New Delhi - 110027
RERA contact

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
M/s GALACITY PRIVATE LIMITED - COLLECTION ACCOUNT FOR CYBER HUB-2BankICICIBranchICICI BANK PANCHSHEEL HYNISHBranch addressPHOP NO 30-35, PANCHSHEEL HYNISH, PLOT NO -GH08A, SEC-1, GR. NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0005388Branch emailcustomer.care@icici.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
M/s GALACTIC CITY PRIVATE LIMITED SEPARATE ACCOUNT FOR CYBER HUB-2BankICICIBranchICICI BANK PANCHSHEEL HYNISHBranch addressPANCHSHEEL HYNISH SHOP NO 30-35,PLOT NO -08A, SEC-1, GR.NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0005388
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
M/s GALACTIC CITY PRIVATE LIMITED TRASACTION ACCOUNT FOR CYBER HUB-2BankICICIBranchICICI BANK PANCHSHEELBranch addressPANCHSHEEL HYNISH SHOP 30-35,PLOT NO GH08A, SEC-1, GR. NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0005388
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

2 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)11 (Under Registration - 2 ) → 11 (Under Registration - 0 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)11 (Under Registration - 3 ) → 11 (Under Registration - 2 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 21 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about CYBER HUB 2

Is CYBER HUB 2 RERA registered?

Yes. CYBER HUB 2 is registered with UPRERA under registration number UPRERAPRJ436071, registered on 5 Apr 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for CYBER HUB 2?

The completion date filed with UPRERA is 31 Dec 2027. No completion certificate is on record yet.

Who is the builder of CYBER HUB 2?

Galactic City Private Limited is the promoter entity that filed CYBER HUB 2 with UPRERA (promoter RERA ID UPRERAPRM89371). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does CYBER HUB 2 show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted CYBER HUB 2 more time to complete?

UPRERA's record carries 1 completion extension for CYBER HUB 2, the latest running to 31 Dec 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does CYBER HUB 2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CYBER HUB 2 located?

CYBER HUB 2 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in CYBER HUB 2?

The unit plan filed with UPRERA lists OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in CYBER HUB 2?

The approved unit plan filed with UPRERA runs from 1,277 to 5,108 m² of carpet area (about 13,746 to 54,982 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in CYBER HUB 2?

The approved unit plan describes 3 blocks and 6 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is CYBER HUB 2?

About 2 units per acre: 6 planned units across 2.53 acres (10,241 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗