Estanzo

Timeline Bar

Registered25 Jun 2018
Promised6 Dec 2022
Today4 Aug 2026

Timeline

Promised completion6 Dec 2022
Revised completion6 Dec 2022
Actual completion
Possession delay44 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,17,000
Project cost (in ₹ Lakhs)₹28,608 Lakhs
Project duration63 months
Project categoryResidential
Locality
Original start date
Proposed start date22 Mar 2018

Inventory

Total units720
Unit TypeUnitsCarpet Area (sqm)
1 BHK340.74–41.41
2 BHK38552.69–69.65
3 BHK20555.95–105.27
4 BHK11140.23
SHOP189.04–13.67
STUDIO9829.21–29.59

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile9650013324
Emailkoyalenclavedmwo@gmail.com
Coordinator9650050625
AddressGround Floor, H-Block, Metro Enclave, Sector-6, Pushp Vihar, New Delhi-110017

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
137/445/GH/Zone-8/167 Dec 20176 Dec 20226 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
GH-13, Koyal Enclave, Ghaziabad22392Plot

Approved Unit Plan

Unit plan rows on file506
Total flats (sum of rows)720
Total shops18
BlocksTower A, Tower B1, Tower B2, Tower C, Tower D1, Tower D2, Tower D3, Tower E
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, SHOP, STUDIO, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of PEARL Residency?

The RERA registration number of PEARL Residency is UPRERAPRJ16196, as recorded on the UP-RERA portal.

What is the RERA status of PEARL Residency?

As reported by UP-RERA, the status of PEARL Residency is "Registered".

Where is PEARL Residency located?

As reported to UP-RERA, PEARL Residency is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will PEARL Residency be completed?

The latest completion date reported to UP-RERA for PEARL Residency is 6 Dec 2022.

Is PEARL Residency delayed?

Measured against the latest completion date reported to UP-RERA, PEARL Residency is 44 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026