Timeline Bar
Registered15 Aug 2017
Promised19 Oct 2019
Today4 Aug 2026
Timeline
Promised completion19 Oct 2019
Revised completion19 Oct 2019
Actual completion—
Possession delay82 mo delay
Registration & Cost Details
Registration fee (in ₹)₹6,15,500
Project cost (in ₹ Lakhs)₹2,840 Lakhs
Project duration37 months
Project categoryResidential
Locality—
Original start date14 Oct 2011
Proposed start date14 Oct 2016
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeAssociation Of Persons (AOP)
Mobile7351448000
Emaildwarikabalaji@gmail.com
Coordinator7351448000
Address2, Park End, Vikas Marg, Delhi-110092
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 143 Revalidated: 143 (18 Oct 2016) | 19 Oct 2011 | 18 Oct 2016 Revalidated upto: 19 Oct 2019 | 19 Oct 2019 | 19 Oct 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 38 BIBIPUR | 1615 | — |
| 39 BIBIPUR | 1630 | — |
| 40 BIBIPUR | 2870 | — |
| 41 BIBIPUR | 2360 | — |
| 42 BIBIPUR | 540 | — |
| 82 BIBIPUR | 2360 | — |
| 83 BIBIPUR | 1790 | — |
| 84 BIBIPUR | 990 | — |
| 85 BIBIPUR | 1910 | — |
| 86 BIBIPUR | 590 | — |
| 23 SHERNAGAR | 9180 | — |
| 24 SHERNAGAR | 3460 | — |
| 15/2 SHERNAGAR | 15480 | — |
| 13 SHERNAGAR | 8640 | — |
| 27 SHERNAGAR | 7030 | — |
| 37 SHERNAGAR | 8650 | — |
| 30 SHERNAGAR | 6690 | — |
| 32 SHERNAGAR | 6730 | — |
| 35 SHERNAGAR | 3340 | — |
| 34 SHERNAGAR | 3380 | — |
| 10/1 SHERNAGAR | 3390 | — |
| 10/2 SHERNAGAR | 13200 | — |
| 35 BIBIPUR | 1640 | — |
| 37 BIBIPUR | 1553 | — |
| 74 BIBIPUR | 2640 | — |
| 8 SHERNAGAR | 2910 | — |
| 9 SHERNAGAR | 10770 | — |
| 36 SHERNAGAR | 24150 | — |
| 41 SHERNAGAR | 15350 | — |
| 52 SHERNAGAR | 6410 | — |
| 53 SHERNAGAR | 7520 | — |
| 54 SHERNAGAR | 9250 | — |
| 60 SHERNAGAR | 1450 | — |
| 61 SHERNAGAR | 2340 | — |
| 63 SHERNAGAR | 1450 | — |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 12729 | 18 Nov 2010 | — | — |
| 6388 | 16 Jun 2007 | — | — |
| 11631 | 18 Nov 2014 | — | — |
| 6371 | 15 Jun 2007 | — | — |
| 9911 | 9 Jul 2013 | — | — |
| 6303 | 29 May 2010 | — | — |
| 10832 | 17 Oct 2007 | — | — |
| 5744 | 16 May 2008 | — | — |
| 5745 | 16 May 2008 | — | — |
| 6979 | 10 Jul 2009 | — | — |
| 4842 | 8 May 2007 | — | — |
| 7931 | 1 Jul 2010 | — | — |
| 7751 | 3 Aug 2009 | — | — |
| 4465 | 6 May 2009 | — | — |
| 6183 | 11 Jun 2007 | — | — |
| 16193 | 31 Dec 2008 | — | — |
| 5653 | 15 May 2008 | — | — |
| 7773 | 17 Jul 2007 | — | — |
| 14790 | 25 Oct 2012 | — | — |
| 4464 | 6 May 2009 | — | — |
| 12327 | 1 Dec 2007 | — | — |
| 7774 | 17 Jul 2007 | — | — |
| 1713 | 14 Feb 2008 | — | — |
| 1714 | 14 Feb 2008 | — | — |
| 2054 | 22 Feb 2008 | — | — |
| 4850 | 8 May 2007 | — | — |
| 6030 | 24 May 2011 | — | — |
| 4847 | 8 May 2007 | — | — |
| 16194 | 31 Dec 2008 | — | — |
Frequently Asked Questions
What is the RERA registration number of DWARIKA CITY PHASE I?
The RERA registration number of DWARIKA CITY PHASE I is UPRERAPRJ7137, as recorded on the UP-RERA portal.
What is the RERA status of DWARIKA CITY PHASE I?
As reported by UP-RERA, the status of DWARIKA CITY PHASE I is "Registered".
Where is DWARIKA CITY PHASE I located?
As reported to UP-RERA, DWARIKA CITY PHASE I is located at Muzaffarnagar, Muzaffarnagar, Uttar Pradesh.
When will DWARIKA CITY PHASE I be completed?
The latest completion date reported to UP-RERA for DWARIKA CITY PHASE I is 19 Oct 2019.
Is DWARIKA CITY PHASE I delayed?
Measured against the latest completion date reported to UP-RERA, DWARIKA CITY PHASE I is 82 months beyond that date.