Timeline Bar

Registered15 Aug 2017
Promised13 Oct 2020
Today4 Aug 2026

Timeline

Promised completion13 Oct 2020
Revised completion
Actual completion
Possession delay70 mo delay

Registration & Cost Details

Registration fee (in ₹)₹3,86,000
Project cost (in ₹ Lakhs)₹1,574 Lakhs
Project duration72 months
Project categoryResidential
Locality
Original start date14 Oct 2011
Proposed start date14 Oct 2016

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeAssociation Of Persons (AOP)
Mobile7351448000
Emaildwarikabalaji@gmail.com
Coordinator7351448000
Address2, Park End, Vikas Marg, Delhi-110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q126.0%
2020-Q239.5%
2020-Q354.1%
2020-Q462.6%
2021-Q154.7%
2021-Q274.0%
2021-Q381.1%
2021-Q4
2022-Q1
2022-Q2
2022-Q3

Land Parcels

Khasra No.AreaPlot Type
22 SHERNAGAR39140
15/2 SHERNAGAR15480
32 SHERNAGAR6730
34 SHERNAGAR3380
36 SHERNAGAR24150
41 SHERNAGAR15350
42 SHERNAGAR28040
51 SHERNAGAR6430
52 SHERNAGAR6410
53 SHERNAGAR7520

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
670223 Jun 2007
777417 Jul 2007
12236 Feb 2015
1189120 Oct 2010
73723 Jan 2016
572724 Apr 2013
841914 Jun 2013
1479025 Oct 2012
1746226 Dec 2012
44646 May 2009
123271 Dec 2007
1021925 Sept 2007
171314 Feb 2008
171414 Feb 2008

Frequently Asked Questions

What is the RERA registration number of DWARIKA CITY PHASE-III?

The RERA registration number of DWARIKA CITY PHASE-III is UPRERAPRJ11319, as recorded on the UP-RERA portal.

What is the RERA status of DWARIKA CITY PHASE-III?

As reported by UP-RERA, the status of DWARIKA CITY PHASE-III is "Registered".

Where is DWARIKA CITY PHASE-III located?

As reported to UP-RERA, DWARIKA CITY PHASE-III is located at Muzaffarnagar, Muzaffarnagar, Uttar Pradesh.

When will DWARIKA CITY PHASE-III be completed?

The latest completion date reported to UP-RERA for DWARIKA CITY PHASE-III is 13 Oct 2020.

Is DWARIKA CITY PHASE-III delayed?

Measured against the latest completion date reported to UP-RERA, DWARIKA CITY PHASE-III is 70 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026