Estanzo

Timeline Bar

Registered23 Aug 2017
Promised31 Mar 2023
Today29 Jul 2026

Timeline

Promised completion31 Mar 2023
Revised completion31 Mar 2023
Actual completion
Possession delay40 mo delay

Registration & Cost Details

Registration fee (in ₹)₹65,000
Project cost (in ₹ Lakhs)₹17,500 Lakhs
Project duration67 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Mar 2018

Inventory

Total units240
Unit TypeUnitsCarpet Area (sqm)
2 BHK12081.99
3 BHK120112.14–137.08

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile7290017743
Emailrera@alpha-corp.com
Coordinator7840080123
AddressT-2, 3rd Floor, Manish Corner Plaza, Sector - 11, Dwarka, New Delhi - 110075

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/M.V.N./2017/IV-1501/97625 May 201724 May 202231 Mar 202324 May 2025

Land Parcels

Khasra No.AreaPlot Type
012000
SC-01/C-A812000Plot

Approved Unit Plan

Unit plan rows on file45
Total flats (sum of rows)240
BlocksTOWER A, TOWER B, TOWER C
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
54097 Jun 2014

Frequently Asked Questions

What is the RERA registration number of EMINENCE - PHASE 1?

The RERA registration number of EMINENCE - PHASE 1 is UPRERAPRJ11733, as recorded on the UP-RERA portal.

What is the RERA status of EMINENCE - PHASE 1?

As reported by UP-RERA, the status of EMINENCE - PHASE 1 is "Registered".

Where is EMINENCE - PHASE 1 located?

As reported to UP-RERA, EMINENCE - PHASE 1 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will EMINENCE - PHASE 1 be completed?

The latest completion date reported to UP-RERA for EMINENCE - PHASE 1 is 31 Mar 2023.

Is EMINENCE - PHASE 1 delayed?

Measured against the latest completion date reported to UP-RERA, EMINENCE - PHASE 1 is 40 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026