Timeline Bar
Registered23 Aug 2017
Promised31 Mar 2023
Today29 Jul 2026
Timeline
Promised completion31 Mar 2023
Revised completion31 Mar 2023
Actual completion—
Possession delay40 mo delay
Registration & Cost Details
Registration fee (in ₹)₹65,000
Project cost (in ₹ Lakhs)₹17,500 Lakhs
Project duration67 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Mar 2018
Inventory
Total units240
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 120 | 81.99 |
| 3 BHK | 120 | 112.14–137.08 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile7290017743
Emailrera@alpha-corp.com
Coordinator7840080123
AddressT-2, 3rd Floor, Manish Corner Plaza, Sector - 11, Dwarka, New Delhi - 110075
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| NOIDA/M.V.N./2017/IV-1501/976 | 25 May 2017 | 24 May 2022 | 31 Mar 2023 | 24 May 2025 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 0 | 12000 | — |
| SC-01/C-A8 | 12000 | Plot |
Approved Unit Plan
Unit plan rows on file45
Total flats (sum of rows)240
BlocksTOWER A, TOWER B, TOWER C
Floor types2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 5409 | 7 Jun 2014 | — | — |
Frequently Asked Questions
What is the RERA registration number of EMINENCE - PHASE 1?
The RERA registration number of EMINENCE - PHASE 1 is UPRERAPRJ11733, as recorded on the UP-RERA portal.
What is the RERA status of EMINENCE - PHASE 1?
As reported by UP-RERA, the status of EMINENCE - PHASE 1 is "Registered".
Where is EMINENCE - PHASE 1 located?
As reported to UP-RERA, EMINENCE - PHASE 1 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will EMINENCE - PHASE 1 be completed?
The latest completion date reported to UP-RERA for EMINENCE - PHASE 1 is 31 Mar 2023.
Is EMINENCE - PHASE 1 delayed?
Measured against the latest completion date reported to UP-RERA, EMINENCE - PHASE 1 is 40 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.