Estanzo

Timeline Bar

Registered26 Jul 2024
Today29 Jul 2026
Promised31 Dec 2028

Timeline

Promised completion31 Dec 2028
Revised completion31 Dec 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,14,000
Project cost (in ₹ Lakhs)₹53,493 Lakhs
Project duration57 months
Project categoryResidential
LocalityKhasra/Plot No. GH-01, Sector 2, Greater Noida
Original start date
Proposed start date1 Apr 2024

Inventory

Total units726
Unit TypeUnitsCarpet Area (sqm)
2 BHK28449.39–62.03
3 BHK44273.35–99.3

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9654522444
Emailsecretarial@eros-group.com
Coordinator9899383333
Helpline9899383333
Address8TH FLOOR, EROS CORPORATE TOWER, NEHRU PLACE, NEW DELHI-110019

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q24.4%
2025-Q35.7%
2025-Q48.6%
2026-Q110.8%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Planning/2024/10078 Jan 20247 Jan 202931 Dec 20287 Jan 2034

Land Parcels

Khasra No.AreaPlot Type
GH-0198373.75Plot

Approved Unit Plan

Unit plan rows on file561
Total flats (sum of rows)726
BlocksA2, B1, B2, G2, G3, G4, H2, Y10, Y11, Y8, Y9
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Eros Sampoornam 3?

The RERA registration number of Eros Sampoornam 3 is UPRERAPRJ512436, as recorded on the UP-RERA portal.

What is the RERA status of Eros Sampoornam 3?

As reported by UP-RERA, the status of Eros Sampoornam 3 is "Registered".

Where is Eros Sampoornam 3 located?

As reported to UP-RERA, Eros Sampoornam 3 is located at Khasra/ Plot No. GH-01, Sector 2, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh - 201305, Khasra/Plot No. GH-01, Sector 2, Greater Noida, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Eros Sampoornam 3 be completed?

The latest completion date reported to UP-RERA for Eros Sampoornam 3 is 31 Dec 2028.

Is Eros Sampoornam 3 delayed?

Measured against the latest completion date reported to UP-RERA, Eros Sampoornam 3 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026