Registered31 Jul 2017
Promised15 Dec 2017
Completed2 Apr 2019

Timeline

Promised completion15 Dec 2017
Revised completion15 Dec 2017
Actual completion2 Apr 2019
Possession delay16 mo delay

Registration & Cost Details

Registration fee (in ₹)₹39,500
Project cost (in ₹ Lakhs)₹6,800 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date1 Nov 2011
Proposed start date14 Jan 2013

Inventory

Total units295
Unit TypeUnitsCarpet Area (sqm)
2 BHK16056.46–71.66
3 BHK11672.17–105.73
PENTHOUSE1123.07
SHOP1119.02–24.56
OTHER73.04–12.42

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9891766678
Emailzenith@expressbuildersltd.com
Coordinator9312832920
Address810, Surya Kiran Building, 19, K.G. Marg, New Delhi- 110001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/VRI.N.NI/III-231/43426 Jul 201125 Jul 20161 Aug 201814 Jul 2021
NOIDA/VRI.N.NI/III-231/434

Revalidated: NOIDA/VRI.N.NI/III-231/434 (26 Jul 2011)

26 Jul 201125 Jul 2016

Revalidated upto: 1 Jan 1900

15 Dec 201714 Jul 2021

Land Parcels

Khasra No.AreaPlot Type
Plot No. 2A, Sector 77, Noida21700
GH-02A, SECTOR 7721700Plot

Approved Unit Plan

Unit plan rows on file164
Total flats (sum of rows)295
Total shops11
BlocksB, C
Floor types2 BHK, 3 BHK, PENTHOUSE, SHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
I-36081 Sept 2010

Frequently Asked Questions

What is the RERA registration number of Express Zenith (Phase 2, Tower B and C)?

The RERA registration number of Express Zenith (Phase 2, Tower B and C) is UPRERAPRJ3393, as recorded on the UP-RERA portal.

What is the RERA status of Express Zenith (Phase 2, Tower B and C)?

As reported by UP-RERA, the status of Express Zenith (Phase 2, Tower B and C) is "Registered".

Where is Express Zenith (Phase 2, Tower B and C) located?

As reported to UP-RERA, Express Zenith (Phase 2, Tower B and C) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Express Zenith (Phase 2, Tower B and C) completed?

As reported to UP-RERA, Express Zenith (Phase 2, Tower B and C) was completed on 2 Apr 2019.

Is Express Zenith (Phase 2, Tower B and C) delayed?

Measured against the latest completion date reported to UP-RERA, Express Zenith (Phase 2, Tower B and C) is 16 months beyond that date.