PARAS ESTATE

UPRERARegistered

PARAS ESTATE is a RERA-registered residential project by Rapid Buildtech Pvt.Ltd. in Village Maliyana, Meerut (RERA ID UPRERAPRJ240109). Registered with a completion deadline of 27 May 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
25%Q3'25
35%Q4'25
34.27%Q1'26
0%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ240109
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMeerut Development Authority
Proposed start1 Nov 2024
Project duration55 months
AddressKhasra no. 1733,1734,1784,,1806,1803/1,1805,1807,1813,1799,1814,1733,,1803/2,1798,1812, Village Maliyana pargana, Near Mata Brijeswari JI madir, Meerut, Village Maliyana, Meerut, Meerut
TehsilMeerut
Applicant typeCompany
Applicant address9 TH FLOOR , PARAS DOWN TOWN CENTRE, SECTOR ROAD, SECTOR-53,GURGAON,HARYANA, INDIA-122002
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered18 Mar 2025
Original completion27 May 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹4,91,500
Sanctioning authorityMeerut Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Nisar Ahmed Ansari
License CA/2005/36034
371, Yar Mohammed Plot, Satacnuz East, Mumbai-400055
Engineer
Ramkrishna Dongar
B-1102, DostiVihar, Pokhan Road -1, Vartak Nagar, Thane, Maharastra-400606
Contractor
Shri Ram Construction Company
Sadarpur Colony , Sector -44 Noida-20301
Sr.Development work declared to RERA
1Demarcation of Plots
AS PER APPROVED LAYLOT PLAN THE PLOT WILL BE DEMARCATED BY BRICK PILARS (LOW HIGHT 2 FEET) TO ALL FOUR SIDES OF THE PLOT BOUNDARY, TO THE EXACT SHAPE, SIZE AND ORIENTATION AS PER SANCTIONED MAP BY MEERUT DEVELOPMENT AUTHORITY
2Boundary Wall
AS PER APPROVED LAYOUT PLAN A 1-8 METER HIGH PRE-FABRICATED/ MS.BRICK BOUNDARY WALL.
3Road Work
AS PER APPROVED LAYOUT PLAN PAVER /BITUMEN ROADS WITH SUB-BASE WHEREVER APPLICATION AS PER APPROVED LAYOUT.
4Footpaths
AS PER APPROVED LAYOUT PLAN PAVER BLOCK/ INTERLOCKING TILES.
5Water Supply Including Drinking Water Facilities
AS PER APPROVED LAYOUT PLAN POTABLE GROUNT WATER SUPPLY.
6Sewer System
AS PER APPROVED LAYOUT PLAN SEWERAGE TREATMENT PLANT AND PIPES.
7Drain
AS PER APPROVED LAYOUT PLAN A SURFACE DRAIN WATER WILL BE COLLECTED THRIUGH A RCC-NC3 PIPE OF 450-600 MM.
8Parks
AS PER APPROVED LAYOUT PLAN THE GREEN AREAS WILL LANDSCAPED WITH HARD ANS SOFT LANDSCAPING AS PER DISIGN. THE PARK WILL HAVE FOOTPATH,SITTING AREA AND PLAY AREA FOR CHILDREN.
9Tree Planting
AS PER APPROVED LAYOUT PLAN THE TREES WILL BE PLANTED AT ALL SUITABLE LOCATION OF THE PROJECT AND ALONG WILL BOUNDARY WALL.
10Design For Electric Supply Including Street Lighting
AS PER APPROVED LAYOUT PLAN.
11Community Buildings
AS PER APPROVED LAYOUT PLAN, FRAME STRUCTURE BUILDING WITH FINISHES.
12Treatment and Disposal System of Sewage and Sullage water
AS PER APPROVED LAYOUT PLAN ALL WASTE OF SEWER LINE TO BE COLLECTED AT STP, AFTER TEATED WATER TO BE USED FOR WATERING OF THE IRRIGATION OF PLANT BY FLUSH WATER SYSTEM.
13Solid Waste Management And Disposal System
AS PER APPROVED LAYOUT PLAN ALL WASTE OF SERVICE TO BE COLLECTED AS STPGARBAGE COLLECTION TO BE DONE THROUGH AUTHORISED AGENCY.
14Water Conservation System
AS PER APPROVED LAYOUT PLAN RAIN WATER HARVESTING LINE TO BE LAID, IRRIGATION PLANTS BY FLUSH-WATER SYSTEM.
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
NA
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
AS PER APPROVED LAY LOT PLAN
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

4 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1Bhavya DevnaniUPRERAAGT18689
2M/s MONEYTREE REALTY SERVICES LIMITED formally known as (M/s Moneytree Reality Services Private Limited)UPRERAAGT25048
3REALTY ASSISTANT PRIVATE LIMITED (Formerly REALTY ASSISTANTS HUB PVT LTD)UPRERAAGT18286
4star estateUPRERAAGT10202
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 27 May 2029. 2 of them carry a revalidation, the latest valid to 13 Feb 2030.

Sanctioned by Meerut Development Authority · 1,01,009.93 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Plotted Resi Development/PlottedHousing/04388/MDA/LD/22-23/0902/1503202328 May 202427 May 202927 May 203227 May 2029—
Plotted Resi Development/plottedhousing/04388/MDA/LD/22-23/0902/1503202328 May 202427 May 202912 Feb 203327 May 202928 May 2024
valid to 13 Feb 2030
Plotted Resi Development/plottedhousing/07448/MDA/LD/24-25/1072/3101202528 May 202427 May 202912 Feb 203327 May 202928 May 2024
valid to 13 Feb 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

28 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1784 AND 18066200Khasra
1733 AND 173417027Khasra
1803/1, 1805,1807,181316440Khasra
17994430Khasra
18146490Khasra
17354170Khasra
17334433Khasra
1803/234520Khasra
179810620Khasra
18122150Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 1189
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1468 RAPID BUILDTECH PVT.LTD
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 954 RAPID BUILDTECH PVT.LTD.
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1188 RAPID BUILDTECH PVT.LTD.
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1467 RAPID BUILDTECH PVT.LTD.
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 185 CONSORTIUM AGREEMENT
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 3435 DIMOND FINANCE LIMITED AS A C0-PROMOTER
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3123 ELIXIR EXPORT PRIVATE LIMITED AS A CO-PROMOTER
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3011 UPVAN PROMOTERS PRIVATE LIMITED AS A CO-PROMOTER
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3046 UPVAN PROMOTERS PRIVATE LIMITED AS A CO-PROMOTER
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 10921 WOUNDERFUL REALTORS PRIVATE LIMITED AS A CO-PROMOTER
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 185 CONSORTIUM AGREEEMENT
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 8731
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · JULY2019 TO JUNE 2031
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Sale deed · upvan1798 khasra no.
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · wounderful khasar no.1812
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · khasar no. 1733 and 1734 year july 2019 to 30 june 2025
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · khasar no. 1814 july 2019 to 30 june 2025
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Sale deed · LAND TITLE SEARCH REPORT
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 479
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 479
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Other · 479
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
PDF ↗
Registry document · 3385
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Other · 3385
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
PDF ↗
Other · 3385
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
PDF ↗
Registry document · 3385
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 3385
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · ENCUMBRENCE
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · ENCUMBRENCE 2
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · JULY 2019 TO JUNE 2025
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · JULY 2019 TO JUNE 2025
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · JULY 2019 TO JUNE 2025
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New23 Oct 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New1 Oct 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New1 Oct 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New18 Oct 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New1 Oct 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New1 Oct 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New1 Oct 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New4 Oct 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New23 Oct 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New23 Oct 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New17 Oct 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New1 Oct 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New23 Oct 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New4 Oct 2024 ↗

Quarterly progress reports

8 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

8 quarterly progress reports are on file with UPRERA, covering 2024-Q3 to 2026-Q2.

QuarterConstructionCertificates
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q225%CA ↗ · Arch ↗ · Eng ↗
2025-Q335%CA ↗ · Arch ↗ · Eng ↗
2025-Q434.27%CA ↗ · Arch ↗ · Eng ↗
2026-Q10%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameRapid Buildtech Pvt.Ltd.
RolePromoter · current
RERA IDUPRERAPRM320111
PANAADCR5940G
CIN / TANDELR44860E
Name of chairmanKUNAL RISHI
Registered address9 TH FLOOR , PARAS DOWN TOWN CENTRE, SECTOR ROAD, SECTOR-53,GURGAON,HARYANA, INDIA-122002
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameWONDERFUL REALTORS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressM-130-131, 2ND FLOOR, OPPOSITE SUPER BAZAR, CONNAUGHT CIERCUS DELHI-110001
RERA contact
Legal nameDIAMOND FINANCE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressM-130/131, 2ND FLOORCONNAUGHT CIRCUS,DELHI-110001
RERA contact
Legal nameELIXIR EXPORTS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressFF-08,TOWER-1, PHASE-1,PEARLS OMAXE, NETAJI SUBHASH PLACE,NEW DELHI-110034
RERA contact
Legal nameUPVAN PROMOTERS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressFF-08,TOWER-1,PEARLS OMEX, NETAJI SUBHASH PALACE, NEW DELHI-110034
RERA contact

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
RAPID BUILDTECH PRIVATE LIMITED.COLLECTION ACCOUNT FOR PARAS ESTATEBankICICI BANKBranchSHATABDI NAGAR MEERUTBranch addressPLOT NO. BC-2,BC-3, SECTOR-1, SATABDI NAGAR MEERUT-250103Branch districtUttar PradeshA/C no.IFSCICICI0003581Branch emailaman.gandhi@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
RAPID BUILDTECH PRIVATE LIMITED SEPARATE BANK ACCOUNT FOR PARAS ESTATEBankICICI BANKBranchSATABDI NAGAR MEERUTBranch addressPLOT NO. BC-2,BC-3,SECTOR -1, SHATABDI NAGAR, MEERUT 250103Branch districtMeerut, Uttar PradeshA/C no.IFSCICICI0003581
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
RAPID BUILDTECH PRIVATE LIMITED RERA TRANSACTION ACCOUNT FOR PARAS ESTATEBankICICI BANKBranchSHATBDI NAGAR MEEERUTBranch addressPLOT NO. BC-2,BC-3, SECTOR -1, SHABDI NAGAR MEERUT-250103Branch districtMeerut, Uttar PradeshA/C no.IFSCICICI0003581
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about PARAS ESTATE

Is PARAS ESTATE RERA registered?

Yes. PARAS ESTATE is registered with UPRERA under registration number UPRERAPRJ240109, registered on 18 Mar 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for PARAS ESTATE?

The completion date filed with UPRERA is 27 May 2029. No completion certificate is on record yet.

Who is the builder of PARAS ESTATE?

Rapid Buildtech Pvt.Ltd. is the promoter entity that filed PARAS ESTATE with UPRERA (promoter RERA ID UPRERAPRM320111). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does PARAS ESTATE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PARAS ESTATE located?

PARAS ESTATE is registered in Village Maliyana, Meerut, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗