Timeline Bar

Registered4 Apr 2024
Revised13 Dec 2025
Today4 Aug 2026

Timeline

Promised completion
Revised completion13 Dec 2025
Actual completion
Possession delay8 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,30,000
Project cost (in ₹ Lakhs)₹9,571 Lakhs
Project duration25 months
Project categoryResidential
LocalitySECTOR 77
Original start date
Proposed start date1 Mar 2024

Inventory

Total units147
Unit TypeUnitsCarpet Area (sqm)
3 BHK112100–101.83
4 BHK6211.79–227
PENTHOUSE2175.03
SHOP1720.76–40.73
OTHER1012.3–19.93

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9891766678
Emailzenith@expressbuildersltd.com
Coordinator9811263619
Address810, Surya Kiran Building, 19, K.G. Marg, New Delhi- 110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q266.0%
2025-Q373.0%
2025-Q485.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/MVN/2017/III-231/99628 Feb 202424 Mar 202613 Dec 202524 Mar 2031

Land Parcels

Khasra No.AreaPlot Type
2A21700Plot

Approved Unit Plan

Unit plan rows on file93
Total flats (sum of rows)147
Total shops17
BlocksA, COMMERCIAL-A, NON TOWER
Floor types3 BHK, 4 BHK, PENTHOUSE, SHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
I/36081 Sept 2010

Frequently Asked Questions

What is the RERA registration number of EXPRESS ZENITH (TOWER A)?

The RERA registration number of EXPRESS ZENITH (TOWER A) is UPRERAPRJ980703, as recorded on the UP-RERA portal.

What is the RERA status of EXPRESS ZENITH (TOWER A)?

As reported by UP-RERA, the status of EXPRESS ZENITH (TOWER A) is "Registered".

Where is EXPRESS ZENITH (TOWER A) located?

As reported to UP-RERA, EXPRESS ZENITH (TOWER A) is located at PLOT GH-02A, SECTOR 77, NOIDA, SECTOR 77, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will EXPRESS ZENITH (TOWER A) be completed?

The latest completion date reported to UP-RERA for EXPRESS ZENITH (TOWER A) is 13 Dec 2025.

Is EXPRESS ZENITH (TOWER A) delayed?

Measured against the latest completion date reported to UP-RERA, EXPRESS ZENITH (TOWER A) is 8 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026