GAUR AERO MALL (POCKET-1)

UPRERARegistered

GAUR AERO MALL (POCKET-1) is a RERA-registered commercial project by UP Township Infrastructure Private Limited in Ghaziabad (RERA ID UPRERAPRJ663149). Registered with a completion deadline of 27 Apr 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
34.5%Q3'25
46.3%Q4'25
51.9%Q1'26
51.9%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ663149
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryU.P. Awas Evam Vikas Parishad
Proposed start1 Sept 2022
Project duration56 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressGaur Biz Park Plot No-1 , Abhay Khand-II, Indirapuram, Ghaziabad. U.P. Pin-201014
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    959/VN-5/OFFLINE/134/PART-V

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Sept 2022
Original completion27 Apr 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹2,23,000
Sanctioning authorityU.P. Awas Evam Vikas Parishad

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors908 · 2 · 14 (units from plan)
Homes · commercial units313 · 595 (shops and offices filed in the same plan)
  • SHOP595 66%
  • STUDIO270 30%
  • OTHER43 5%
ConfigurationUnitsCarpet area
SHOP5952-29
OTHER436-51
STUDIO27025-44
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
COMMERCIAL · SHOP, OTHER36142-588
RESIDENTIAL/COMMERCIAL · SHOP, OTHER, STUDIO1329412-86
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 587.99 m² for a SHOP, 360.92 m² for a SHOP, 199.49 m² for a SHOP and 19 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Anuj Agarwal
License CA/96/19503
OFFICE A-244 KAUSHAMBI GHAZIABAD (U.P)
Engineer
Optimum Design
B-24, Sector-67, Noida
Contractor
Ms Durga Buildwell Pvt Ltd
BHATTA COLONY NEAR RITA HOSPITAL, BHANGEL, NOIDA
Sr.Development work declared to RERA
1Demarcation of Plots
DEMARCATION OF PLOTS AS PER THE SANCTION LAYOUT PLAN
2Boundary Wall
BOUNDARY WALL AS PER THE SANCTION LAYOUT PLAN - (HEIGHT UP TO 1.8M)
3Road Work
INTERNAL ROAD WORK DESIGNED OF DIFFERENT RIGHT OF WAY (ROW) AS PER REQUIREMENT - INTERNAL ROAD PROPOSED 6 M WIDE AND 7.5 M WIDE.
4Footpaths
FOOTPATHS AS PER THE SANCTION LAYOUT PLAN
5Water Supply Including Drinking Water Facilities
MUNICIPAL WATER SUPPLY IS USED FOR DRINKING PURPOSE
6Sewer System
SEWERAGE SYSTEM IS USED AS PER THE DESIGNED CALCULATION
7Drain
SEPARATE DRAINAGE SYSTEM LINE IS USED AS PER THE DESIGNED REQUIREMENT
8Parks
LANDSCAPE AREA IS PROVIDED AS PER LOCAL BUILDING BYE LAWS
9Tree Planting
NUMBER OF TREES AS PER THE APPROVED DRAWING AND REQUIREMENT
10Design For Electric Supply Including Street Lighting
ELECTRICAL SUPPLY INCLUDING STREET LIGHTING IS PROVIDED AS PER THE LAYOUT PLAN
11Community Buildings
N.A
12Treatment and Disposal System of Sewage and Sullage water
DISPOSAL SYSTEM OF SEWAGE AND SULLAGE WATER IS BEING USED THROUGH SEWERAGE TREATMENT PLANT WHICH IS USED FOR LANDSCAPE AND FLUSHING PURPOSE - SEWERAGE TREATMENT PLAN PROPOSED 200 KLD APPROX
13Solid Waste Management And Disposal System
ALL THE SOLID WASTE MANAGED AS PER THE BIODEGRADABLE WASTE CONVERTED IN COMPOST AND NON BIODEGRADABLE DELIVERED TO REGISTERED RECYCLABLE ANGENCIES - SOLID WASTE GENERATED APPROX 1.185 TON PER DAY
14Water Conservation System
LOW FLOW WATER FIXTURES BEING USED FOR WATER CONSERVATION AND STP WATER IS USED FOR LANDSCAPE AND FLUSHING PURPOSE
15Energy Management System Including Use of Renewable Energy
N.A
16Fire Protection And Fire Safety System
FIRE SYSTEM AND FIRE SAFETY SYSTEM WILL BE INSTALLED IN BUILDING AS PER THE NBC NORMS - INCLUDING FIRE HOSE REEL AND SPRINKLER SYSTEM
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A
18Emergency Evacuation Services
AS PER THE MANAGEMENT PLAN AND DISASTER MANAGEMENT PLAN. ALL PROVISION ARE MADE INCLUDING FIRE ASSEMBLY POINT
19Other Miscellaneous Work
OTHER MISCELLANEOUS WORK IS PROVIDED AS PER THE LAYOUT PLAN
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 27 Apr 2027.

Sanctioned by U.P. Awas Evam Vikas Parishad · 21,258 sqm of land · an approved plan of 2 blocks and 908 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
959/VN-5/OFFLINE/134/PART-V28 Apr 202227 Apr 202726 Apr 203027 Apr 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

20 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Pocket-1 Land Development and Grahthan yojana (Ajantapuram) Loni District Ghaziabad UP21258.32Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 6876
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New16 Sept 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New22 Aug 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New22 Aug 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New22 Aug 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New22 Aug 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New22 Aug 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New4 Sept 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New22 Aug 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New22 Aug 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New12 Sept 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New22 Aug 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New4 Sept 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New4 Sept 2022 ↗

Quarterly progress reports

16 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

16 quarterly progress reports are on file with UPRERA, covering 2022-Q2 to 2026-Q1.

QuarterConstructionCertificates
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q234.5%CA ↗ · Arch ↗ · Eng ↗
2025-Q346.3%CA ↗ · Arch ↗ · Eng ↗
2025-Q451.9%CA ↗ · Arch ↗ · Eng ↗
2026-Q151.9%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameUP Township Infrastructure Private Limited
RolePromoter · current
RERA IDUPRERAPRM5788
PANAABCU5795Q
CIN / TANU45200DL2013PTC250025
Name of chairmanShailendra Raghav
Registered addressGaur Biz Park Plot No-1 , Abhay Khand-II, Indirapuram, Ghaziabad. U.P. Pin-201014
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameSHRI RAMA KRISHNA SEHKARI AWAS SAMITI LIMITED
RoleCo-promoter
Applicant typeSocieties
Address67, II NAVYUG MARKET, GHAZIABAD UP-201001
RERA contact

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
UP Township Infrastructure Pvt Ltd-Collection A/C-Gaur Aero Mall (POCKET1)BankICICI BANKBranchICICI Bank Ltd, Noida Sector-61Branch addressICICI Bank Ltd, Supertech Shopprix, C134 B, Sector-61, Noida, UP 201307Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0000253
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
UP Township Infrastructure Pvt Ltd-Seperate A/C-Gaur Aero Mall (POCKET1)BankICICI BANKBranchICICI Bank Ltd, Noida, Sector-61Branch addressICICI Bank Ltd, Supertech Shopprix, C134 B Sector-61, Noida UP-201307Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0000253
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
UP Township Infrastructure Pvt Ltd-RERA Transaction A/C- Gaur Aero Mall (POCKET1)BankICICI BANKBranchICICI Bank Ltd, Noida, Sector-61Branch addressICICI Bank Ltd, Supertech Shopprix, C134 B Sector-61, Noida UP-201307Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0000253
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about GAUR AERO MALL (POCKET-1)

Is GAUR AERO MALL (POCKET-1) RERA registered?

Yes. GAUR AERO MALL (POCKET-1) is registered with UPRERA under registration number UPRERAPRJ663149, registered on 24 Sept 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for GAUR AERO MALL (POCKET-1)?

The completion date filed with UPRERA is 27 Apr 2027. No completion certificate is on record yet.

Who is the builder of GAUR AERO MALL (POCKET-1)?

UP Township Infrastructure Private Limited is the promoter entity that filed GAUR AERO MALL (POCKET-1) with UPRERA (promoter RERA ID UPRERAPRM5788). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does GAUR AERO MALL (POCKET-1) have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is GAUR AERO MALL (POCKET-1) located?

GAUR AERO MALL (POCKET-1) is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in GAUR AERO MALL (POCKET-1)?

The unit plan filed with UPRERA lists SHOP, OTHER and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in GAUR AERO MALL (POCKET-1)?

The approved unit plan filed with UPRERA runs from 2 to 51 m² of carpet area (about 22 to 549 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in GAUR AERO MALL (POCKET-1)?

The approved unit plan describes 2 blocks and 908 units of which 313 are homes and 595 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is GAUR AERO MALL (POCKET-1)?

About 173 units per acre: 908 planned units across 5.25 acres (21,258 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗