Timeline Bar
Registered15 Aug 2017
Promised15 Oct 2020
Today4 Aug 2026
Timeline
Promised completion15 Oct 2020
Revised completion15 Oct 2020
Actual completion—
Possession delay70 mo delay
Registration & Cost Details
Registration fee (in ₹)₹38,000
Project cost (in ₹ Lakhs)₹12,598 Lakhs
Project duration102 months
Project categoryResidential
Locality—
Original start date9 Mar 2010
Proposed start date15 Oct 2012
Inventory
Total units148
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 3 BHK | 148 | 74.69 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8130016877
Emailkanishkashobanleal@gmail.com
Coordinator+919718808500
AddressR-19, 3rd FLOOR, NEAR SHAKARPUR, LAXMI
NAGAR, VIKAS MARG DELHI East Delhi DL 110092
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| NOIDA/CAP/III-183/581 | 15 Oct 2012 | 15 Oct 2017 | 15 Oct 2020 | 15 Oct 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| NIL | 0 | — |
| GH-01 | 51719 | Plot |
Approved Unit Plan
Unit plan rows on file37
Total flats (sum of rows)148
BlocksB8, B9
Floor types3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 2820 | 26 Oct 2009 | — | — |
Frequently Asked Questions
What is the RERA registration number of GLORY 46 (PHASE-5)?
The RERA registration number of GLORY 46 (PHASE-5) is UPRERAPRJ11614, as recorded on the UP-RERA portal.
What is the RERA status of GLORY 46 (PHASE-5)?
As reported by UP-RERA, the status of GLORY 46 (PHASE-5) is "Registered".
Where is GLORY 46 (PHASE-5) located?
As reported to UP-RERA, GLORY 46 (PHASE-5) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will GLORY 46 (PHASE-5) be completed?
The latest completion date reported to UP-RERA for GLORY 46 (PHASE-5) is 15 Oct 2020.
Is GLORY 46 (PHASE-5) delayed?
Measured against the latest completion date reported to UP-RERA, GLORY 46 (PHASE-5) is 70 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026