Estanzo

Timeline Bar

Registered15 Aug 2017
Promised15 Oct 2020
Today4 Aug 2026

Timeline

Promised completion15 Oct 2020
Revised completion15 Oct 2020
Actual completion
Possession delay70 mo delay

Registration & Cost Details

Registration fee (in ₹)₹47,500
Project cost (in ₹ Lakhs)₹16,270 Lakhs
Project duration102 months
Project categoryResidential
Locality
Original start date9 Mar 2010
Proposed start date15 Oct 2012

Inventory

Total units110
Unit TypeUnitsCarpet Area (sqm)
3 BHK110100.4–106.37

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8130016877
Emailkanishkashobanleal@gmail.com
Coordinator+919718808500
AddressR-19, 3rd FLOOR, NEAR SHAKARPUR, LAXMI NAGAR, VIKAS MARG DELHI East Delhi DL 110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/III-183/58115 Oct 201215 Oct 201715 Oct 202015 Oct 2022

Land Parcels

Khasra No.AreaPlot Type
nil0
GH-0151719Plot

Approved Unit Plan

Unit plan rows on file38
Total flats (sum of rows)110
BlocksD
Floor types3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
282026 Oct 2009

Frequently Asked Questions

What is the RERA registration number of GLORY 46 (PHASE-7)?

The RERA registration number of GLORY 46 (PHASE-7) is UPRERAPRJ11633, as recorded on the UP-RERA portal.

What is the RERA status of GLORY 46 (PHASE-7)?

As reported by UP-RERA, the status of GLORY 46 (PHASE-7) is "Registered".

Where is GLORY 46 (PHASE-7) located?

As reported to UP-RERA, GLORY 46 (PHASE-7) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will GLORY 46 (PHASE-7) be completed?

The latest completion date reported to UP-RERA for GLORY 46 (PHASE-7) is 15 Oct 2020.

Is GLORY 46 (PHASE-7) delayed?

Measured against the latest completion date reported to UP-RERA, GLORY 46 (PHASE-7) is 70 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026