Timeline Bar
Registered15 Aug 2017
Promised15 Oct 2020
Today4 Aug 2026
Timeline
Promised completion15 Oct 2020
Revised completion15 Oct 2020
Actual completion—
Possession delay70 mo delay
Registration & Cost Details
Registration fee (in ₹)₹39,000
Project cost (in ₹ Lakhs)₹13,000 Lakhs
Project duration102 months
Project categoryResidential
Locality—
Original start date9 Mar 2010
Proposed start date15 Oct 2012
Inventory
Total units153
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 4 BHK | 153 | 14.81–177.07 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8130016877
Emailkanishkashobanleal@gmail.com
Coordinator+919718808500
AddressR-19, 3rd FLOOR, NEAR SHAKARPUR, LAXMI
NAGAR, VIKAS MARG DELHI East Delhi DL 110092
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| NOIDA/CAP/III-183/581 | 15 Oct 2012 | 15 Oct 2017 | 15 Oct 2020 | 15 Oct 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| nil | 0 | — |
| GH-01 | 51719 | Plot |
Approved Unit Plan
Unit plan rows on file114
Total flats (sum of rows)153
BlocksC1, C2, C3
Floor types4 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 2820 | 26 Oct 2009 | — | — |
Frequently Asked Questions
What is the RERA registration number of GLORY 46 (PHASE-6)?
The RERA registration number of GLORY 46 (PHASE-6) is UPRERAPRJ11626, as recorded on the UP-RERA portal.
What is the RERA status of GLORY 46 (PHASE-6)?
As reported by UP-RERA, the status of GLORY 46 (PHASE-6) is "Registered".
Where is GLORY 46 (PHASE-6) located?
As reported to UP-RERA, GLORY 46 (PHASE-6) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will GLORY 46 (PHASE-6) be completed?
The latest completion date reported to UP-RERA for GLORY 46 (PHASE-6) is 15 Oct 2020.
Is GLORY 46 (PHASE-6) delayed?
Measured against the latest completion date reported to UP-RERA, GLORY 46 (PHASE-6) is 70 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026