GLORY GARDEN PHASE II TO VUPRERADelayed 7 mo
Home › Projects › Hathras › GLORY GARDEN PHASE II TO V

GLORY GARDEN PHASE II TO V

UPRERADelayed 7 moRegisteredConstruction 100% · 2025 Q3updated 4 Aug 2026

GLORY GARDEN PHASE II TO V is a RERA-registered real-estate project in Hathras (RERA ID UPRERAPRJ392359). Its RERA-registered completion deadline (29 Dec 2025) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
7 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹6
Land area
not reported
Units
not reported
Density (derived)
not reported
Towers
not reported
Config
not reported
Carpet
not reported
Registered
31 Mar 2021

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2025 Q3
—Q4'23
—Q1'24
—Q2'24
—Q3'24
—Q4'24
—Q1'25
100%Q2'25
100%Q3'25

Basic details

RERA IDUPRERAPRJ392359
Applicant typePartnership Firm
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start1 Jan 2021
Project duration60
AddressHathras, Hathras

Registration & timeline

RERA registered31 Mar 2021
Promised completion29 Dec 2025
Revised completion— none granted
Completion certificate filed6 Jan 2024
Registration fee₹1,76,000

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
139/2020-21,140/2020-21,148/2020-21,149/2020-2111 Jan 202129 Dec 202529 Dec 2025

Land & documents

3 filings
KhasraAreaType
501/2/12750Khasra
501/2/28300Khasra
501/2/323370Khasra

Quarterly progress reports

20 filed reports
QuarterConstructionCertificatesSource
2020-Q4—CA · Arch · Engview ↗
2021-Q1—CA · Arch · Engview ↗
2021-Q2—CA · Arch · Engview ↗
2021-Q3—CA · Arch · Engview ↗
2021-Q4—CA · Arch · Engview ↗
2022-Q1—CA · Arch · Engview ↗
2022-Q2—CA · Arch · Engview ↗
2022-Q3—CA · Arch · Engview ↗
2022-Q4—CA · Arch · Engview ↗
2023-Q1—CA · Arch · Engview ↗
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q2100%CA · Arch · Engview ↗
2025-Q3100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3.

Nearby projects

Hathras

Other projects registered in Hathras.

GLORY GARDEN PHASE 6
UPRERA ▲ 7 mo
ROSHAN ENCLAVE
UPRERA ▲ 61 mo
Roshan Vihar
UPRERA ▲ 91 mo
UTKARASHT LOTUS GREENS
UPRERA ▲ 70 mo
VASUNDHARA ESTATE
UPRERA ▲ 56 mo

Common questions about GLORY GARDEN PHASE II TO V

Is GLORY GARDEN PHASE II TO V RERA registered?

Yes. GLORY GARDEN PHASE II TO V is registered with UPRERA under registration number UPRERAPRJ392359, registered on 31 Mar 2021. Estanzo reproduces that filing; it does not verify the work behind it.

Has GLORY GARDEN PHASE II TO V been completed?

UPRERA still lists GLORY GARDEN PHASE II TO V as Registered, so it is not shown as completed here. A completion certificate dated 6 Jan 2024 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Where is GLORY GARDEN PHASE II TO V located?

GLORY GARDEN PHASE II TO V is registered in Hathras, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 7 mo
QPR filingNo default reported
DistrictHathras
Last updated4 Aug 2026

Location

AddressHathras
View on map ↗

RERA buyer helpline

Coordinator9897599177
official grievance contact, as published by RERA