GSP Divine Homes

UPRERARegistered

GSP Divine Homes is a RERA-registered residential project by OZONE PROMOTERS PRIVATE LIMITED in Aligarh (RERA ID UPRERAPRJ396964). Registered with a completion deadline of 6 Jul 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
54.46%Q3'25
55.58%Q4'25
56.21%Q1'26
56.22%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ396964
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAny Other Competent Authority
Proposed start15 Nov 2021
Project duration56 months
AddressKoil, Aligarh
TehsilKoil
Applicant typeCompany
Applicant addressB-2/16 Mohan Cooperative Indl. Estate, Behind Badarpur Metro Station, New Delhi -110044
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    387/SIDA/ATP

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  7. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered21 Dec 2021
Original completion30 Jun 2026
Revised completion6 Jul 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary19 Aug 2026
Registration fee₹58,500
Sanctioning authorityAny Other Competent Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors167 · 5 · 11 (units from plan)
Homes · commercial units160 · 7 (shops and offices filed in the same plan)
  • 3 BHK80 48%
  • 4 BHK80 48%
  • SHOP7 4%
ConfigurationUnitsCarpet area
3 BHK8083
4 BHK80105
SHOP717-17
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · 3 BHK, 4 BHK, OTHER114083-105
B · 3 BHK, 4 BHK, OTHER114083-105
C · 3 BHK, 4 BHK, OTHER114083-105
COMMERCIAL AND COMMUNITY · OTHER, SHOP3717-17
D · 3 BHK, 4 BHK, OTHER114083-105
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Chander Mohan
License CA/86/9680
W- 139, First Floor, Greater Kailash - I, New Delhi - 110048
Engineer
Dr. Maqsud E Nazar
G 70, 2nd Floor, Jaswant Plaza - Shaheen Bagh, Okhla, New Delhi - 110025
Contractor
SELF
B-2/16, Mohan Cooperative Industrial Estate, New Delhi-110044
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation of plot was given by UPSIDA . It is a rectangular corner plot of 237mt. by 45 mt. situated on 24 mt. wide road and 18 mt road. As per the demarcation provided by UPSIDA permanent boundary wall on all four sides was raised.
2Boundary Wall
1.5 meter high boundary wall with brick masonry and MS Grill has been constructed on all four sides.
3Road Work
Six meter wide internal road finished in trimix / concrete pavers . Length of the road is around 490 mt.s and approximate area shall be 2950 sq.mt.
4Footpaths
Footpath shall have RCC curb stones and shall be finished with cement tiles / stone with an underlay of 100 mm thick PCC. All parking areas shall be finished with concrete paver / grass pavers as per design.
5Water Supply Including Drinking Water Facilities
Provision of 24 by 7 water supply to all the apartments and common area through 100 KLD underground and 30 KLD overhead tanks shall be provided.
6Sewer System
Under ground sewerage system has .been proposed. The sewerage system shall be connected to STP. The capacity of STP shall be 65 KLD approximately
7Drain
Covered storm water drain is being provided on the 6mt wide peripheral road which is connected to rain water harvesting pits with provision of water over flow to the external drains.
8Parks
Green area has been provided well distributed with in the plot. The total area of the green is about 1890 sq.mt.
9Tree Planting
More than 80 trees will be provided along the boundary. Out of this about fifty percent will be ornamental and balance fifty percent shall be evergreen type.
10Design For Electric Supply Including Street Lighting
External lighting shall comprise of LED based light fixtures with desired lux level as per NBC norms . Electrical system shall consist of supply through 850 KVA transformer. Individual connections in each apartment shall be provided by state electricity board.
11Community Buildings
Community facilities have been provided above the commercial area. First floor of the community area has lounge with common toilets, gymnasium and indoor games. Second floor shall have multi-purpose hall and spill out terrace.
12Treatment and Disposal System of Sewage and Sullage water
About 65 KLD capacity of STP has been provided at ground level to take care of the sewage and waste water. The treated water will be used for gardening, flushing of WC etc.
13Solid Waste Management And Disposal System
The expected solid waste generation is 0.6 kg/ day/ capita . In order to treat this, a composture shall be provided.
14Water Conservation System
Recharging of ground water will be through rain water harvesting system. Treated water from STP will be re used for flushing of WC and horticulture etc.
15Energy Management System Including Use of Renewable Energy
Adequate use of LED lights in street lighting and common area has been proposed. To save energy, solar panels shall be installed as per norms. Some part of the hot water demand in the commercial area will be met through solar energy and in this regard due norms will be followed.
16Fire Protection And Fire Safety System
Fire hose cabinet has been provided on every floor as per NBC which is connected to over head fire tank.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Shops, pool, steam, sauna, community hall, gymnasium, kids play area, basket ball and badminton provided with in the complex.
18Emergency Evacuation Services
Two stair case in each tower has been provided out of which one is a fire stair case planned as per NBC norms. Each floor has only four apartments for whom two stair cases are available for exit in case of emergency. The stair case leads to internal peripheral roads on ground floor.
19Other Miscellaneous Work
Rest all work to be done as per sanctioned drawings and approvals.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 6 Jul 2026.

Sanctioned by Any Other Competent Authority · 10,665 sqm of land · an approved plan of 5 blocks and 167 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
387/SIDA/ATP7 Jul 20216 Jul 20266 Jul 202630 Jun 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 6 Jul 2026.

#Granted fromExtended uptoNote
130 Jun 20266 Jul 2026—

Land & documents

23 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-A (GH-6 to GH-13)10575Plot
GH-A (GH-6 to GH-13) Additional Area90Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 3861
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 8181
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New15 Dec 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New23 Nov 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New23 Nov 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New23 Nov 2021 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New13 Oct 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New15 Dec 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New15 Dec 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New15 Dec 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New15 Dec 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New15 Dec 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New21 Nov 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New15 Dec 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New15 Dec 2021 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2021-Q3 to 2026-Q1.

QuarterConstructionCertificates
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q254.46%CA ↗ · Arch ↗ · Eng ↗
2025-Q355.58%CA ↗ · Arch ↗ · Eng ↗
2025-Q456.21%CA ↗ · Arch ↗ · Eng ↗
2026-Q156.22%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameOZONE PROMOTERS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM135287
PANAAJCA3431D
CIN / TANU70101DL2011PTC216409
Name of chairmanSUNIL PRAKASH
Registered addressB-2/16 Mohan Cooperative Indl. Estate, Behind Badarpur Metro Station, New Delhi -110044
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Aligarh

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
OPPL-COLLECTION A/C FOR GSP DIVINE HOMESBankHDFC BANK LIMITEDBranchSECTOR 14 FARIDABADBranch addressSECTOR 14 FARIDABADBranch districtAligarhA/C no.IFSCHDFC0001466
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
OPPL-SEPARATE A/C FOR GSP DIVINE HOMESBankHDFC BANK LIMITEDBranchSECTOR 14 FARIDABADBranch addressSECTOR 14 FARIDABADBranch districtAligarhA/C no.IFSCHDFC0001466
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
OPPL-RERA TRANS A/C FOR GSP DIVINE HOMESBankHDFC BANK LIMITEDBranchSECTOR 14 FARIDABADBranch addressSECTOR 14 FARIDABADBranch districtAligarhA/C no.IFSCHDFC0001466
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

2 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Revised completion date on file2026-06-30 → 2026-07-06
changed in Estanzo’s record
7 Oct 2026
Actual completion2026-08-19
first recorded by Estanzo
23 Aug 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 7 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about GSP Divine Homes

Is GSP Divine Homes RERA registered?

Yes. GSP Divine Homes is registered with UPRERA under registration number UPRERAPRJ396964, registered on 21 Dec 2021. Estanzo reproduces that filing; it does not verify the work behind it.

Has GSP Divine Homes been completed?

UPRERA still lists GSP Divine Homes as Registered, so it is not shown as completed here. A completion certificate dated 19 Aug 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of GSP Divine Homes?

OZONE PROMOTERS PRIVATE LIMITED is the promoter entity that filed GSP Divine Homes with UPRERA (promoter RERA ID UPRERAPRM135287). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted GSP Divine Homes more time to complete?

UPRERA's record carries 1 completion extension for GSP Divine Homes, the latest running to 6 Jul 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does GSP Divine Homes have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is GSP Divine Homes located?

GSP Divine Homes is registered in Aligarh, as filed with UPRERA.

What configurations are available in GSP Divine Homes?

The unit plan filed with UPRERA lists 3 BHK, 4 BHK, OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in GSP Divine Homes?

The approved unit plan filed with UPRERA runs from 17 to 105 m² of carpet area (about 179 to 1,131 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in GSP Divine Homes?

The approved unit plan describes 5 blocks and 167 units of which 160 are homes and 7 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is GSP Divine Homes?

About 63 units per acre: 167 planned units across 2.64 acres (10,665 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗