Timeline Bar

Registered21 Dec 2021
Promised23 Jul 2026
Today4 Aug 2026

Timeline

Promised completion23 Jul 2026
Revised completion23 Jul 2026
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹40,000
Project cost (in ₹ Lakhs)₹6,783 Lakhs
Project duration55 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Jan 2022

Inventory

Total units180
Unit TypeUnitsCarpet Area (sqm)
SHOP1808.3–88.14

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9871716679
Emailgoldcoast.enquiries@gmail.com
Coordinator9910336682
AddressRegd. Office A-106, Pkt-4 Pandav Nagar Mayur Vihar East Delhi DL 110091 Corporate Office Khasra no. 976, 975 Plot no .Commerical Center - 05, Ansal Sushant Aquapolis Crossing Republic, Ghaziabad-201001 Site Office Khasra no. 976, 975 Plot no. Commerical Center - 05, Ansal Sushant Aquapolis Crossing Republic, Ghaziabad-201001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Commercial Building/01314/GDA/BP/21-22/0111/1005202124 Jul 202123 Jul 202623 Jul 202623 Jul 2029

Land Parcels

Khasra No.AreaPlot Type
976,9753000Khasra

Approved Unit Plan

Unit plan rows on file180
Total flats (sum of rows)180
Total shops180
BlocksCommercial
Floor typesSHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Gold Coast City Walk?

The RERA registration number of Gold Coast City Walk is UPRERAPRJ892294, as recorded on the UP-RERA portal.

What is the RERA status of Gold Coast City Walk?

As reported by UP-RERA, the status of Gold Coast City Walk is "Registered".

Where is Gold Coast City Walk located?

As reported to UP-RERA, Gold Coast City Walk is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will Gold Coast City Walk be completed?

The latest completion date reported to UP-RERA for Gold Coast City Walk is 23 Jul 2026.

Is Gold Coast City Walk delayed?

Measured against the latest completion date reported to UP-RERA, Gold Coast City Walk is on time.