Timeline Bar
Registered1 Aug 2017
Promised31 Dec 2019
Today29 Jul 2026
Timeline
Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion—
Possession delay79 mo delay
Registration & Cost Details
Registration fee (in ₹)₹21,000
Project cost (in ₹ Lakhs)₹4,400 Lakhs
Project duration120 months
Project categoryResidential
Locality—
Original start date1 Jun 2012
Proposed start date1 Dec 2013
Inventory
Total units192
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 144 | 58.73–72.45 |
| 3 BHK | 48 | 76.76 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9650589629
Emailinfo@adwikgroup.com
Coordinator9560997000
AddressD-550, Ashok Nagar, Delhi
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 487/ZONE5/2016 | 25 Mar 2017 | 25 Mar 2022 | 31 Dec 2019 | 25 Mar 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1038 | 3200 | — |
Approved Unit Plan
Unit plan rows on file96
Total flats (sum of rows)192
BlocksA, B, C, D
Floor types2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of La Casa Ansal Aquapolis?
The RERA registration number of La Casa Ansal Aquapolis is UPRERAPRJ5399, as recorded on the UP-RERA portal.
What is the RERA status of La Casa Ansal Aquapolis?
As reported by UP-RERA, the status of La Casa Ansal Aquapolis is "Registered".
Where is La Casa Ansal Aquapolis located?
As reported to UP-RERA, La Casa Ansal Aquapolis is located at Ghaziabad, Ghaziabad, Uttar Pradesh.
When will La Casa Ansal Aquapolis be completed?
The latest completion date reported to UP-RERA for La Casa Ansal Aquapolis is 31 Dec 2019.
Is La Casa Ansal Aquapolis delayed?
Measured against the latest completion date reported to UP-RERA, La Casa Ansal Aquapolis is 79 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026