Golghar CentralUPRERADelayed 15 mo
Home › Projects › Gorakhpur › Golghar Central

Golghar Central

UPRERADelayed 15 moRegisteredupdated 4 Aug 2026

Golghar Central is a RERA-registered real-estate project in Gorakhpur (RERA ID UPRERAPRJ403072). Its RERA-registered completion deadline (10 May 2025) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
15 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹37
Land area
not reported
Units (from plan)
221
Density (derived)
not reported
Towers
not reported
Config
SHOP/OTHER
Carpet
11–94
Registered
31 Dec 2020

Basic details

RERA IDUPRERAPRJ403072
Applicant typeCompany
Project categoryCommercial
Project typeother
RERA statusRegistered
Proposed start10 Dec 2020
Project duration54
AddressGorakhpur, Gorakhpur

Registration & timeline

RERA registered31 Dec 2020
Promised completion10 May 2025
Revised completion— none granted
Completion certificate filed7 Oct 2025
Registration fee₹53,000

Inventory

derived from unit plan
Total units · towers · floors221 · 1 · 10 (units from plan)
ConfigurationUnitsCarpet area
SHOP22111–94
Towers as filedGolghar Central
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

2 permits
Permit no.DateValid uptoRevised end
MAP2019012119554903018 May 202017 May 202510 May 2025
24827 Jun 202226 Jun 202710 May 2025

Land & documents

1 filing
KhasraAreaType
43 mi, 45 mi8094.05Khasra

Quarterly progress reports

19 filed reports
QuarterConstructionCertificatesSource
2020-Q3—CA · Arch · Engview ↗
2020-Q4—CA · Arch · Engview ↗
2021-Q1—CA · Arch · Engview ↗
2021-Q2—CA · Arch · Engview ↗
2021-Q3—CA · Arch · Engview ↗
2021-Q4—CA · Arch · Engview ↗
2022-Q1—CA · Arch · Engview ↗
2022-Q2—CA · Arch · Engview ↗
2022-Q3—CA · Arch · Engview ↗
2022-Q4—CA · Arch · Engview ↗
2023-Q1—CA · Arch · Engview ↗
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only.

Nearby projects

Gorakhpur

Other projects registered in Gorakhpur.

A D MALL
UPRERA ▲ 91 mo
AMBESHWARI BUILD CON
UPRERA ▲ 62 mo
ARBIT THE 25
UPRERA ▲ 7 mo
ASHTA SIDDHI TRADE CENTER
UPRERA ▲ 67 mo
Central Towers
UPRERA no delay on record
CHAUDHARY S S H MALL
UPRERA no delay on record

Common questions about Golghar Central

Is Golghar Central RERA registered?

Yes. Golghar Central is registered with UPRERA under registration number UPRERAPRJ403072, registered on 31 Dec 2020. Estanzo reproduces that filing; it does not verify the work behind it.

Has Golghar Central been completed?

UPRERA still lists Golghar Central as Registered, so it is not shown as completed here. A completion certificate dated 7 Oct 2025 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Where is Golghar Central located?

Golghar Central is registered in Gorakhpur, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 15 mo
QPR filingNo default reported
DistrictGorakhpur
Last updated4 Aug 2026

Location

AddressGorakhpur
View on map ↗

RERA buyer helpline

Coordinator9415822897
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=BM39ZATJg0k=&hfFlag=Vve7Vt7phxw2J45GP78XiQ==&NPJ6RAme=w82N9LwN+dlATtAqW/VXgg==&PaURJEMAN4=ZL9MNERkNdaAWIs7P8XuMA==&IRSAHEB=D6PY3lyims8=)