Gomti Ganj

UPRERARegistered

Gomti Ganj is a RERA-registered commercial project by Nirmala Infradevelopers Limited in Lucknow (RERA ID UPRERAPRJ11286). Registered with a completion deadline of 31 Dec 2025.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Oct–Dec 2025
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'24
—Q2'24
—Q3'24
—Q4'24
77.35%Q1'25
78.92%Q2'25
81.35%Q3'25
92.35%Q4'25

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ11286
Project categoryCommercial
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Jul 2015
Original start1 Jul 2015
Project duration126 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant address2/12 Maa Bhawan, Vibhuti Khand, Gomtinagar, Lucknow-226010, Uttar Pradesh, India
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    38139

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered14 Aug 2017
Original completion30 Apr 2020
Revised completion31 Dec 2025
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹80,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors265 · 4 · 8 (units from plan)
Homes · commercial units5 · 260 (shops and offices filed in the same plan)
  • SHOP260 98%
  • OTHER5 2%
ConfigurationUnitsCarpet area
SHOP26011-273
OTHER51,568-2,410
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · SHOP, OTHER812211-61
B · SHOP, OTHER810911-191
Circle · SHOP72368-207
Cut Out · SHOP61114-30
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
REPL
License CA/2005/35401
Ground Floor, Yuva Bhawan, YMCA, 13, Rana Pratap Marg, Lucknow
Engineer
REPL
Ground Floor, Yuva Bhawan, YMCA, 13, Rana Pratap Marg, Lucknow
Contractor
M/s Shailendra Nath
Shop No. 9, Sadaphal Plaza, sector- I, LDA Colony, Kanpur Road, Lucknow
Sr.Development work declared to RERA
1Demarcation of Plots
completed
2Boundary Wall
completed
3Road Work
yet to be started
4Footpaths
yet to be started
5Water Supply Including Drinking Water Facilities
yet to be started
6Sewer System
yet to be started
7Drain
yet to be started
8Parks
yet to be started
9Tree Planting
yet to be started
10Design For Electric Supply Including Street Lighting
yet to be started
11Community Buildings
yet to be started
12Treatment and Disposal System of Sewage and Sullage water
yet to be started
13Solid Waste Management And Disposal System
yet to be started
14Water Conservation System
yet to be started
15Energy Management System Including Use of Renewable Energy
yet to be started
16Fire Protection And Fire Safety System
yet to be started
17Social Infrastructure And Other Public Amenities Including Public Health Services
yet to be started
18Emergency Evacuation Services
yet to be started
19Other Miscellaneous Work
na
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 13 May 2020.

Sanctioned by Lucknow Development Authority · 7,000 sqm of land · an approved plan of 4 blocks and 265 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
3813914 May 201513 May 202013 May 202030 Apr 2020
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 31 Dec 2025.

#Granted fromExtended uptoNote
130 Apr 202029 Oct 2020Six months extension in view of force majeure caused by covid-19 pandemic
229 Oct 202031 Dec 2025—

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Sector JSushant Golf City—
10.3982Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 18 Feb 2013.

Registry no.DateTypeArea
1802201318 Feb 2013other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · na
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · na
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Registry document · 6371
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New6 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New6 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Jul 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old14 Aug 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterRO Water for Common Areas
Fire safety (as filed with RERA)Fire UG Tanks, Diesel Fire Pumps, Sprinkler System , CO2 Flooder in Panel Rooms
Health serviceFirst Aid Box, Garbage Collection
Renewable energySolar Panels on Terrace
Other facilitiesAs per guidelines

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

23 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

23 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q477.35%CA ↗ · Arch ↗ · Eng ↗
2025-Q178.92%CA ↗ · Arch ↗ · Eng ↗
2025-Q281.35%CA ↗ · Arch ↗ · Eng ↗
2025-Q392.35%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameNirmala Infradevelopers Limited
RolePromoter · current
RERA IDUPRERAPRM18490
PANAAECN8167A
CIN / TANLKNN06683F
Name of chairmanMrs.Nirmala Dwivedi
Registered address2/12 Maa Bhawan, Vibhuti Khand, Gomtinagar, Lucknow-226010, Uttar Pradesh, India
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Proplarity Infrastructure Pvt LtdBankHDFC Bank Ltd.BranchHazratganjA/C no.IFSCHDFC0000078
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Gomti Ganj

Is Gomti Ganj RERA registered?

Yes. Gomti Ganj is registered with UPRERA under registration number UPRERAPRJ11286, registered on 14 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Gomti Ganj?

The completion date filed with UPRERA is 31 Dec 2025. No completion certificate is on record yet.

Who is the builder of Gomti Ganj?

Nirmala Infradevelopers Limited is the promoter entity that filed Gomti Ganj with UPRERA (promoter RERA ID UPRERAPRM18490). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Gomti Ganj more time to complete?

UPRERA's record carries 2 completion extensions for Gomti Ganj, the latest running to 31 Dec 2025. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Gomti Ganj have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Gomti Ganj located?

Gomti Ganj is registered in Lucknow, as filed with UPRERA.

What configurations are available in Gomti Ganj?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Gomti Ganj?

The approved unit plan filed with UPRERA runs from 11 to 2,410 m² of carpet area (about 113 to 25,936 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Gomti Ganj?

The approved unit plan describes 4 blocks and 265 units of which 5 are homes and 260 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Gomti Ganj?

About 153 units per acre: 265 planned units across 1.73 acres (7,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗