Green Reserve Tower 1 and 2 is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ459796). Registered with a completion deadline of 28 May 2028. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ459796 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Apr 2023 |
| Project duration | 62 |
| Address | Dadri, Gautam Budh Nagar |
| RERA registered | 2 Sept 2025 |
| Promised completion | 28 May 2028 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹67,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 5 BHK | 89 | 264–311 |
| 4 BHK | 90 | 195–195 |
| 3 BHK | 86 | 152–167 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 2023/02/21/8509 | 29 May 2023 | 28 May 2028 | 31 Mar 2029 |
| 2023/02/21/8509 | 29 May 2023 | 28 May 2028 | 28 May 2028 |
| Khasra | Area | Type |
|---|---|---|
| B-24 A, Jaypee Wishtown, Sector-128, Noida | 12394 | Plot |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2023-Q1 | 3.29% | CA · Arch · Eng | view ↗ |
| 2023-Q2 | 4.94% | CA · Arch · Eng | view ↗ |
| 2023-Q3 | 5.85% | CA · Arch · Eng | view ↗ |
| 2023-Q4 | 6.03% | CA · Arch · Eng | view ↗ |
| 2024-Q1 | 6.37% | CA · Arch · Eng | view ↗ |
| 2024-Q2 | 6.53% | CA · Arch · Eng | view ↗ |
| 2024-Q3 | 6.68% | CA · Arch · Eng | view ↗ |
| 2024-Q4 | 6.79% | CA · Arch · Eng | view ↗ |
| 2025-Q1 | 6.98% | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 7.25% | CA · Arch · Eng | view ↗ |
| 2025-Q3 | 7.56% | CA · Arch · Eng | view ↗ |
| 2025-Q4 | 11.49% | CA · Arch · Eng | view ↗ |
| 2026-Q1 | 17.85% | CA · Arch · Eng | view ↗ |
Other projects registered in Gautam Budh Nagar.
Yes. Green Reserve Tower 1 and 2 is registered with UPRERA under registration number UPRERAPRJ459796, registered on 2 Sept 2025. Estanzo reproduces that filing; it does not verify the work behind it.
The completion date filed with UPRERA is 28 May 2028. No completion certificate is on record yet, and that deadline has not passed.
Green Reserve Tower 1 and 2 is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 3 Aug 2026. official source ↗