Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ2051
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Sept 2015
Original start1 Sept 2015
Project duration142 months
AddressSector 128, Noida, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressA-19, Sector-63, Noida, Uttar Pradesh-201301
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    NOIDA/CTP/2015/III-293/785

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. to

    Extension granted

  9. valid to

    Permit revalidated

    Noida/Niyojan/2026/1320

  10. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered27 Jul 2017
Original completion31 Dec 2021
Revised completion30 Jun 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹83,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors386 · 6 · 44 (units from plan)
  • 3 BHK156 40%
  • 4 BHK152 39%
  • 5 BHK78 20%
ConfigurationUnitsCarpet area
4 BHK152174-192
3 BHK156130
5 BHK78273-328
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
WING-A RICHMOND PALACE · 4 BHK4376176-192
WING-B BRIDEWELL PALACE · 4 BHK4376174
WING-C WHITEHALL PALACE · 3 BHK4478130
WING-D WESTMINSTER PALACE · 3 BHK4478130
WING-E KENSINGTON PALACE · 5 BHK4439273-328
WING-F BUCKINGHAM PALACE · 5 BHK4439273-328
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Peeyush Chaudhry
License CA/93/16189
Office no- 44, Plot no- A41, The Corenthum Building, Tower B, Sector 62, Noida
Engineer
Mahimtura Consultants Pvt. Ltd.
Unique House, 25, S.A. Brelvi Road, Fort, Mumbai-400001
Contractor
Mahagun India Pvt. Ltd.
B-66, 1st floor, Vivek Vihar, Delhi-95
Sr.Development work declared to RERA
1Demarcation of Plots
NORTH SIDE- ROAD, EAST SIDE- ROAD ,WEST SIDE-JAY PEE TOWN SHIP, SOUTH SIDE- JAY PEE TOWN SHIP
2Boundary Wall
BOUNDARY WALL- A COMBINE OF RCC, BRICK WALL & MS RAILING
3Road Work
PROVIDED
4Footpaths
PROVIDED
5Water Supply Including Drinking Water Facilities
WATER TREATMENT PLANT IS PROVIDED FOR PORTABLE WATER
6Sewer System
SEWER LINE WITH REQUIRED SLOPE AND ADEQUATE MANHOLES
7Drain
ADEQUATE CATCH BASINS AND MANHOLES ARE PROVIDED TO COLLECT RAIN WATER
8Parks
GREEN AREA PROVIDED
9Tree Planting
A VARIETY OF GREEN TREES
10Design For Electric Supply Including Street Lighting
PROVIDED AS PER NORMS
11Community Buildings
COMMUNITY IN WING-A & WING B TOP FLOORS
12Treatment and Disposal System of Sewage and Sullage water
PROVIDED AS PER NORMS
13Solid Waste Management And Disposal System
PROVIDED AS PER AUTHORITY NORMS
14Water Conservation System
RAIN WATER HARVESTING PITS ARE PROVIDED AS PER AUTHORITY NORMS
15Energy Management System Including Use of Renewable Energy
ELEVATORS IN GROUP CONTROL & SOLAR WATER HEATERS ARE PROVIDED AS PER NORMS
16Fire Protection And Fire Safety System
FIRE SPRINKLERS,SMOKE DETECTORS,FHC WITH PUMPS ARE PROVIDED AS PER NORMS
17Social Infrastructure And Other Public Amenities Including Public Health Services
PROVIDED
18Emergency Evacuation Services
FIRE STAIRCASE IN EACH WING/TOWER ARE IN PROVIDED
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

7 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1BULLMEN REALTY INDIA PRIVATE LIMITEDUPRERAAGT10138
2Cushman & Wakefield India Private LimitedUPRERAAGT11043
3FINDMYPROPERTY PRIVATE LIMITEDUPRERAAGT11867
4INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
5PRIME ESTATESUPRERAAGT11881
6RAJ NANDINI ESTATES PRIVATE LIMITEDUPRERAAGT10793
7SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 5 May 2020. 2 of them carry a revalidation, the latest valid to 4 May 2025.

Sanctioned by Noida Authority · 15,580 sqm of land · an approved plan of 6 blocks and 386 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
NOIDA/CTP/2015/III-293/7856 May 20155 May 20204 May 202331 Dec 2021—
NOIDA/CTP/2015/III-293/7856 May 20155 May 20204 May 202529 Mar 20246 May 2015
valid to 4 May 2025
NOIDA/CTP/2015/III-293/7856 May 20155 May 20204 May 202529 Mar 20249 Apr 2025
valid to 4 May 2025
as Noida/Niyojan/2026/1320
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 30 Jun 2027.

#Granted fromExtended uptoNote
131 Dec 202130 Jun 2022Six months extension in view of force majeure caused by covid-19 pandemic
230 Jun 202229 Mar 2024—
329 Mar 202430 Jun 2027—

Land & documents

24 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
B-9B, WISH TOWN, SECTOR 128, NOIDA15580Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

2 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 30 Jan 2015.

Registry no.DateTypeArea
53430 Jan 2015self—
53430 Jan 2015other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · Reg No. 534, Book 1, Zild 4500, Page 171-264
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · Reg No. 534, Book 1, Zild 4500, Page 171-264
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · Reg No. 534, Book 1, Zild 4500, Page 171-264
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New4 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New4 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New4 Jul 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New1 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New1 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New1 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New1 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New1 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New1 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New30 Jun 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New30 Jun 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New30 Jun 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old15 Jan 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old15 Jan 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old15 Jan 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old15 Jan 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old15 Jan 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old15 Jan 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old15 Jan 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old15 Jan 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old15 Jan 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old15 Jan 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking wateryes
Fire safety (as filed with RERA)yes
Health serviceyes
Renewable energyPartial

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

16 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

16 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMAHAGUN (INDIA) PVT. LTD.
RolePromoter · current
RERA IDUPRERAPRM4786
PANAAACM6572A
CIN / TANU74899DL1995PTC072752
Name of chairmanMR. AMIT JAIN,C-215, VIVEK VIHAR, DELHI-110095
Registered addressA-19, Sector-63, Noida, Uttar Pradesh-201301
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
MIPL Collection Bank A/c for Mahagun ManorialBankHDFC Bank Ltd.BranchSector 63, Noida Branch, Gautam Budh NagarBranch addressH 1 / A 12, Sector 63, Noida, District Gautam Budh Nagar, Uttar Pradesh-201306Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000975Branch emailtaru.gupta (at) hdfc.bank.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
MIPL Separate Bank A/c for Mahagun ManorialBankHDFC Bank LtdBranchSector 63, NoidaBranch addressH 1 A/ 12, Sector 63, Noida, District -Gautam Budh Nagar, Uttar Pradesh-201306Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000975Branch emailtaru.gupta(at)hdfc.bank.in
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
MIPL RERA Transaction Bank A/c for Mahagun ManorialBankHDFC BankBranchSector 63, Noida, Gautam Budh NagarBranch addressH 1 A/12, Sector 63, Noida, District - Gautam Budh Nagar, Uttar Pradesh -201306Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000975Branch emailtaru.gupta(at)hdfc.bank.in
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

9 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)374 (Under Registration - 4 ) → 374 (Under Registration - 3 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)373 (Under Registration - 3 ) → 374 (Under Registration - 4 )
changed in Estanzo’s record
13 Oct 2026
Promoter’s complaints tally (all their projects)373 (Under Registration - 4 ) → 373 (Under Registration - 3 )
changed in Estanzo’s record
7 Oct 2026
Promoter’s complaints tally (all their projects)372 (Under Registration - 5 ) → 373 (Under Registration - 4 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)372 (Under Registration - 6 ) → 372 (Under Registration - 5 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)370 (Under Registration - 4 ) → 372 (Under Registration - 6 )
changed in Estanzo’s record
17 Sept 2026
Promoter’s complaints tally (all their projects)369 (Under Registration - 3 ) → 370 (Under Registration - 4 )
changed in Estanzo’s record
11 Sept 2026
Promoter’s complaints tally (all their projects)369 (Under Registration - 4 ) → 369 (Under Registration - 3 )
changed in Estanzo’s record
23 Aug 2026
Promoter’s complaints tally (all their projects)368 (Under Registration - 3 ) → 369 (Under Registration - 4 )
changed in Estanzo’s record
10 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 9 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Mahagun Manorial

Is Mahagun Manorial RERA registered?

Yes. Mahagun Manorial is registered with UPRERA under registration number UPRERAPRJ2051, registered on 27 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Mahagun Manorial?

The completion date filed with UPRERA is 30 Jun 2027. No completion certificate is on record yet.

Who is the builder of Mahagun Manorial?

MAHAGUN (INDIA) PVT. LTD. is the promoter entity that filed Mahagun Manorial with UPRERA (promoter RERA ID UPRERAPRM4786). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Mahagun Manorial more time to complete?

UPRERA's record carries 3 completion extensions for Mahagun Manorial, the latest running to 30 Jun 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Mahagun Manorial have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Mahagun Manorial located?

Mahagun Manorial is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Mahagun Manorial?

The unit plan filed with UPRERA lists 4 BHK, 3 BHK and 5 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Mahagun Manorial?

The approved unit plan filed with UPRERA runs from 130 to 328 m² of carpet area (about 1,401 to 3,535 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Mahagun Manorial?

The approved unit plan describes 6 blocks and 386 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Mahagun Manorial?

About 100 units per acre: 386 planned units across 3.85 acres (15,580 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗