Timeline Bar

Registered14 Aug 2017
Promised31 Dec 2019
Today4 Aug 2026

Timeline

Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹86,000
Project cost (in ₹ Lakhs)₹16,200 Lakhs
Project duration184 months
Project categoryResidential
Locality
Original start date11 Mar 2013
Proposed start date11 Mar 2013

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile9971099901
Emailgreenviewsamiti@gmail.com
Coordinator9213789541
AddressPlot No-4, Sector Pi-1, Greater Noida, Gautam Budh Nagar, U.P. Pin Code - 201310

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q263.7%
2025-Q365.0%
2025-Q467.7%
2026-Q170.2%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP) BP-2896/24-51056 Aug 20135 Aug 201831 Dec 20195 Aug 2023
PLG/(BP) BP-2896/24-5105

Revalidated: PLG/(BP) BP-2896/24-5105 (6 Aug 2013)

6 Aug 20135 Aug 2018

Revalidated upto: 5 Aug 2023

31 Dec 20195 Aug 2023

Land Parcels

Khasra No.AreaPlot Type
Plot No. 416140

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
40347 Mar 2011

Frequently Asked Questions

What is the RERA registration number of Green View- II Sahakari Awas Samiti Limited?

The RERA registration number of Green View- II Sahakari Awas Samiti Limited is UPRERAPRJ9720, as recorded on the UP-RERA portal.

What is the RERA status of Green View- II Sahakari Awas Samiti Limited?

As reported by UP-RERA, the status of Green View- II Sahakari Awas Samiti Limited is "Registered".

Where is Green View- II Sahakari Awas Samiti Limited located?

As reported to UP-RERA, Green View- II Sahakari Awas Samiti Limited is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Green View- II Sahakari Awas Samiti Limited be completed?

The latest completion date reported to UP-RERA for Green View- II Sahakari Awas Samiti Limited is 31 Dec 2019.

Is Green View- II Sahakari Awas Samiti Limited delayed?

Measured against the latest completion date reported to UP-RERA, Green View- II Sahakari Awas Samiti Limited is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026