Hari Pearl Heights

UPRERARegistered

Hari Pearl Heights is a RERA-registered residential project by Bhagwan Singh in Aligarh (RERA ID UPRERAPRJ729342). Registered with a completion deadline of 24 Nov 2025.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Oct–Dec 2025
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'24
—Q2'24
—Q3'24
—Q4'24
10%Q1'25
20%Q2'25
20%Q3'25
70%Q4'25

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ729342
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAligarh Development Authority
Proposed start25 Nov 2020
Project duration60 months
AddressF-12, Vikram Colony, Ramghat Road, Aligarh-202001, Aligarh, Koil, Aligarh
TehsilKoil
Applicant typeIndividual
Applicant addressF-12, Vikram Colony, Ramghat Road, Koil, Aligarh
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MAP-20191127124001543

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered29 Apr 2024
Original completion24 Nov 2025
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹22,000
Sanctioning authorityAligarh Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors66 · 1 · 9 (units from plan)
Homes · commercial units64 · 2 (shops and offices filed in the same plan)
  • 3 BHK49 74%
  • 4 BHK15 23%
  • SHOP2 3%
ConfigurationUnitsCarpet area
SHOP230
4 BHK15104-109
3 BHK4979-92
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower-1 · SHOP, 4 BHK, 3 BHK96630-109
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Sameep Garg
License CA/2000/26238
H.M.Complex, 1st Floor, Near axis Bank Janakpuri Ramghat Road, Aligarh, U.P.
Engineer
Ashraf Ali
Ash Plaxa, 1st Floor, Medical Road, Aligarh, U.P.
Contractor
Rohitash Kumar
Majurfarhi Aligarh
Sr.Development work declared to RERA
1Demarcation of Plots
The project land is demarcated as follows by North; Passage and house of other, To the South; Vacant plot of other, To the East; G.T Road, To the West; House of other
2Boundary Wall
2.40 meter high boundary wall in brickwork and one side olaster with R.C.C columns approx 4.50 meter center to center.
3Road Work
All the internal road/passage will be combination of R.C.C and concrete interlocking pavers, Roads will be laid over 225 mm water level.
4Footpaths
Not Applicable
5Water Supply Including Drinking Water Facilities
Drinking Water supply will be provided through over head tank connected with submersible.
6Sewer System
The sewerage will be collected through PVC/ Soll pipelines and connected to inspection chambers leading to septic tank.
7Drain
Rain water shall be collected in drains having width of 150mm connected underground pipeline. For discharge water will be collected in man hole to be constructed in periphery of complex and these man holes shall be finally connected to drain of harvesting pits and overflow to main Govt. drain.
8Parks
Not Applicable.
9Tree Planting
The tree will be planted as all suitable location of the project and along the boundary wall of the project.
10Design For Electric Supply Including Street Lighting
Electric supply provide through transformer installed near front boundary.
11Community Buildings
Not Applicable.
12Treatment and Disposal System of Sewage and Sullage water
The sewerage will be collected through PVC/Soil pipelines and connected to inspection chambers leading to septic tank.
13Solid Waste Management And Disposal System
Professional service provide shall be engaged for disposal of soil water outside the project premises.
14Water Conservation System
Rain water harvesting system shall be provide with ground water recharging and overflow to be discharge in Govt, drain.
15Energy Management System Including Use of Renewable Energy
Single point supply shall be taken that distributed through transformer through distribution panel and sub meters.
16Fire Protection And Fire Safety System
Fire sprinkler system in basement shall be provide. Hose reels and fire hydrants shall be provide as per National building code. Over head and underground fire tank shall be provided with fire pumps.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable.
18Emergency Evacuation Services
Not Applicable.
19Other Miscellaneous Work
Not Applicable.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 24 Nov 2025.

Sanctioned by Aligarh Development Authority · 3,342 sqm of land · an approved plan of 1 block and 66 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MAP-2019112712400154325 Nov 202024 Nov 202525 Nov 202524 Nov 2025
—24 Nov 202524 Nov 202824 Nov 2025
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
335A, 3343341.65Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 335A
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 334
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1428-1433(01 July 2020 to 30 June 2026)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433(01 July 2020 to 30 June 2026)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New18 Feb 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New17 Mar 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New17 Mar 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New18 Feb 2024 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New18 Feb 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Feb 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New18 Feb 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Feb 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Feb 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New18 Mar 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New18 Mar 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New17 Mar 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New18 Mar 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New18 Feb 2024 ↗

Quarterly progress reports

21 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

21 quarterly progress reports are on file with UPRERA, covering 2020-Q3 to 2025-Q3.

QuarterConstructionCertificates
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q410%CA ↗ · Arch ↗ · Eng ↗
2025-Q120%CA ↗ · Arch ↗ · Eng ↗
2025-Q220%CA ↗ · Arch ↗ · Eng ↗
2025-Q370%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameBhagwan Singh
RolePromoter · current
RERA IDUPRERAPRM271690
PANAGZPS3833J
Registered addressF-12, Vikram Colony, Ramghat Road, Koil, Aligarh
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Aligarh

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
BHAGWAN SINGH COLLECTION ACCOUNT FOR HARI PEARL HEIGHTSBankPUNJAB NATIONAL BANKBranchPNB BANNA DEVIBranch addressPNB, BANNA DEVI ALIGARHBranch districtAligarh, Uttar PradeshA/C no.IFSCPUNB0656200Branch emailb06562@pnb.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
BHAGWAN SINGH SEPARATE ACCOUNT FOR HARI PEARL HEIGHTSBankPUNJAB NATIONAL BANKBranchPNB BANNA DEVIBranch addressPNB BANNA DEVI ALIGARHBranch districtAligarh, Uttar PradeshA/C no.IFSCPUNB0656200
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
BHAGWAN SINGH TRANSACTION ACCOUNT FOR HARI PEARL HEIGHTSBankPUNJAB NATIONAL BANKBranchPNB BANNA DEVIBranch addressPNB BANNA DEVI ALIGARHBranch districtAligarh, Uttar PradeshA/C no.IFSCPUNB0656200
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

6 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Permit paperwork
2 · Project Specifications
Project Specifications
newly filed with RERA
23 Aug 2026
Permit paperwork
2 · Floor Plan Of All Types
Floor Plan Of All Types
newly filed with RERA
23 Aug 2026
Permit paperwork
2 · Approved Map
Approved Map
newly filed with RERA
23 Aug 2026
Permit paperwork
2 · Sanctioned Letter
Sanctioned Letter
newly filed with RERA
23 Aug 2026
Permit paperwork
2 · Approved Layout
Approved Layout
newly filed with RERA
23 Aug 2026
Sanctioning permit
no. 2
permit 2
newly filed with RERA
23 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Hari Pearl Heights

Is Hari Pearl Heights RERA registered?

Yes. Hari Pearl Heights is registered with UPRERA under registration number UPRERAPRJ729342, registered on 29 Apr 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Hari Pearl Heights?

The completion date filed with UPRERA is 24 Nov 2025. No completion certificate is on record yet.

Who is the builder of Hari Pearl Heights?

Bhagwan Singh is the promoter entity that filed Hari Pearl Heights with UPRERA (promoter RERA ID UPRERAPRM271690). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Hari Pearl Heights have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Hari Pearl Heights located?

Hari Pearl Heights is registered in Aligarh, Aligarh, as filed with UPRERA.

What configurations are available in Hari Pearl Heights?

The unit plan filed with UPRERA lists SHOP, 4 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Hari Pearl Heights?

The approved unit plan filed with UPRERA runs from 30 to 109 m² of carpet area (about 322 to 1,177 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Hari Pearl Heights?

The approved unit plan describes 1 block and 66 units of which 64 are homes and 2 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Hari Pearl Heights?

About 80 units per acre: 66 planned units across 0.83 acres (3,342 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗