Imperial Heights (Phase 1)

UPRERARegistered

Imperial Heights (Phase 1) is a RERA-registered residential project by RAMPRASTHA URBAN DEVELOPMENT PVT. LTD. in Gautam Budh Nagar (RERA ID UPRERAPRJ504323). Registered with a completion deadline of 30 Jan 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
81.99%Q3'25
84.63%Q4'25
87.49%Q1'26
91.22%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ504323
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Aug 2019
Project duration90 months
AddressGata ARAZI No.: 69m, 70m, 70mi, 71m, 71mi, 72m, 72mi, 73m, 73mi, 76m, 76mi, 77/2, 79mi at VILL-CHAJARSI Tehsil: Dadari District: Gautam Buddh Nagar U.P., Dadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant addressD-194, 1ST FLOOR, GATE NO.2 (BACK SIDE) OKHLA INDUSTRIAL AREA, PHASE - 1, NEW DELHI - 110020
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MAP20190212172638183

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. valid to

    Permit revalidated

    GDA/BP/21-22/0999

  5. Permit revalidated

    Group Housing/05573/GDA/BP/22-23/1648/11092023

  6. Building permit sanctioned

    Group Housing/05573/GDA/BP/22-23/1648/11092023

  7. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  8. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  9. to

    Extension granted

  10. to

    Extension granted

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Aug 2019
Original completion1 Aug 2024
Revised completion30 Jan 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,48,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors600 · 4 · 30 (units from plan)
  • 3 BHK540 90%
  • 4 BHK60 10%
ConfigurationUnitsCarpet area
3 BHK54080-94
4 BHK60131
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER D · 4 BHK, 3 BHK3012094-131
TOWER E · 3 BHK3012094-94
Tower F · 3 BHK3018080-80
Tower G · 3 BHK3018080
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
RD Design Atrium- Rahul Gupta- Rohit Dabas
License CA/2010/48921, CA/2016/76810
D-1, First Floor, Sector-7, Noida, U.P.-201301
Engineer
Optimization Consultants- Dr. Rajeev Dua
202/203, Himliand House, commercial complex, Karampura, New Delhi
Contractor
VINAYAK CIVIL CONSTRUCTIONS , AYUSH CONSTRUCTIONS
New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
As per Layout attached.
2Boundary Wall
RCC COLUMN AND BEAM STR. WITH BRICK WORK & MS RAILING
3Road Work
Cement Concrete/ with Cement Concrete Pavers
4Footpaths
Cement Concrete/ with Cement Concrete Pavers
5Water Supply Including Drinking Water Facilities
Underground and overhead water tanks are provided
6Sewer System
Well – Laid interconnected sewer lines will be provided which are further connected to the municipal sewer.
7Drain
Rain water harvesting system will be provided as per design, overflow water will be transferred to municipal drains.
8Parks
Green areas planned as per norms.
9Tree Planting
Tree plantation as per norms.
10Design For Electric Supply Including Street Lighting
Electrical Supply System will be provided according to requirement based on the calculations.
11Community Buildings
Building will be provided.
12Treatment and Disposal System of Sewage and Sullage water
STP will be provided.
13Solid Waste Management And Disposal System
OWC will be provided.
14Water Conservation System
Rain Water Harvesting will be provided.
15Energy Management System Including Use of Renewable Energy
Provision of V.F.D. ( Variable Frequency Drive) in pump room for pumping the domestic and flushing water to minimize the energy requirement.
16Fire Protection And Fire Safety System
Fire fighting system and protection system will be provided as per NBC and NOC from UP fire service.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
Fire tender road and fire escape staircase will be provided.
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

4 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1DIVAKAR YADAVUPRERAAGT25843
2PRASHANT SHARMAUPRERAAGT21834
3PRAVEEN ARYAUPRERAAGT13652
4SHAURYA REALTY LLPUPRERAAGT20350
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 5 Oct 2028. 2 of them carry a revalidation, the latest valid to 4 Aug 2027.

Sanctioned by Ghaziabad Development Authority · 16,792 sqm of land · an approved plan of 4 blocks and 600 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
MAP201902121726381836 Jul 20195 Jul 20244 Jul 20271 Aug 2024—
—5 Jul 20244 Aug 202731 Jan 20255 Aug 2022
valid to 4 Aug 2027
as GDA/BP/21-22/0999
Group Housing/05573/GDA/BP/22-23/1648/110920236 Oct 20235 Oct 20284 Oct 203130 Jan 20266 Oct 2023
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 30 Jan 2027.

#Granted fromExtended uptoNote
11 Aug 202431 Jan 2025Six months extension in view of force majeure caused by covid-19 pandemic
231 Jan 202530 Jan 2026—
330 Jan 202630 Jan 2027—

Land & documents

30 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
73mi/003162460Khasra
73mi/001691405Khasra
73m/000522780Khasra
72mi/003162480Khasra
72m/000051390Khasra
71mi/003162400Khasra
71m/001693370Khasra
76m/003161260Khasra
76mi/001821520Khasra
79mi/001811340Khasra
77/2/002641140Khasra
70m/00316820Khasra
70mi/00189870Khasra
69m/001765462Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1421-1426
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 3780
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New2 Aug 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New24 Jul 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New24 Jul 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New2 Aug 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New24 Jul 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New24 Jul 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New24 Jul 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 Jul 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New2 Aug 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Aug 2019 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New23 Dec 2022 ↗

Quarterly progress reports

26 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

26 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q281.99%CA ↗ · Arch ↗ · Eng ↗
2025-Q384.63%CA ↗ · Arch ↗ · Eng ↗
2025-Q487.49%CA ↗ · Arch ↗ · Eng ↗
2026-Q191.22%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameRAMPRASTHA URBAN DEVELOPMENT PVT. LTD.
RolePromoter · current
RERA IDUPRERAPRM8884
PANAAECR1141G
CIN / TANU45200DL2008PTC181294
Name of chairmanSURAT SINGH YADAV
Registered addressD-194, 1ST FLOOR, GATE NO.2 (BACK SIDE) OKHLA INDUSTRIAL AREA, PHASE - 1, NEW DELHI - 110020
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
RUDPL MASTER COLL RERA A/C IH PH-1BankHDFC BANK LTDBranchSECTOR 63 NOIDABranch addressH 1A/12, SECTOR 63, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000975Branch emailTARU.GUPTA[at]HDFCBANK.COM
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
RUDPL SEPRATE RERA A/C IH PH-1BankHDFC BANK LTDBranchSECTOR-63 NOIDABranch addressH 1 A/12, SECTOR 63, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000975Branch emailTARU.GUPTA[at]HDFCBANK.COM
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
RUDPL TRANSACTION RERA A/C IH PH-1BankHDFC BANK LTDBranchSECTOR 63 NOIDABranch addressH 1A/12, SECTOR 63, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000975Branch emailTARU.GUPTA[at]HDFCBANK.COM
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
21 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Imperial Heights (Phase 1)

Is Imperial Heights (Phase 1) RERA registered?

Yes. Imperial Heights (Phase 1) is registered with UPRERA under registration number UPRERAPRJ504323, registered on 31 Aug 2019. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Imperial Heights (Phase 1)?

The completion date filed with UPRERA is 30 Jan 2027. No completion certificate is on record yet.

Who is the builder of Imperial Heights (Phase 1)?

RAMPRASTHA URBAN DEVELOPMENT PVT. LTD. is the promoter entity that filed Imperial Heights (Phase 1) with UPRERA (promoter RERA ID UPRERAPRM8884). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Imperial Heights (Phase 1) more time to complete?

UPRERA's record carries 3 completion extensions for Imperial Heights (Phase 1), the latest running to 30 Jan 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Imperial Heights (Phase 1) have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Imperial Heights (Phase 1) located?

Imperial Heights (Phase 1) is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Imperial Heights (Phase 1)?

The unit plan filed with UPRERA lists 3 BHK and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Imperial Heights (Phase 1)?

The approved unit plan filed with UPRERA runs from 80 to 131 m² of carpet area (about 860 to 1,408 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Imperial Heights (Phase 1)?

The approved unit plan describes 4 blocks and 600 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Imperial Heights (Phase 1)?

About 145 units per acre: 600 planned units across 4.15 acres (16,792 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗