Timeline Bar

Registered31 Jul 2017
Promised31 Dec 2018
Revised30 Jun 2019
NCLT20 Sept 2022

Timeline

Promised completion31 Dec 2018
Revised completion30 Jun 2019
Actual completion
Possession delay85 mo delay

Registration & Cost Details

Registration fee (in ₹)₹34,500
Project cost (in ₹ Lakhs)₹9,400 Lakhs
Project duration64 months
Project categoryResidential
Locality
Original start date22 Dec 2015
Proposed start date22 Dec 2015

Inventory

Total units310
Unit TypeUnitsCarpet Area (sqm)
2 BHK26251.8–62.06
3 BHK4869.54

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582006011
Emailail@ajnara.com
Coordinator9582006011
Address1. B-189, YOJNA VIHAR, DELHI-92 2. B-189, YOJNA VIHAR, DELHI-92 3. B-189, YOJNA VIHAR, DELHI-92 4

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
141/GH/Zone-1/14-1522 Jul 201522 Jul 202030 Jun 201922 Jul 2023

Land Parcels

Khasra No.AreaPlot Type
977, 978, 979, 981, 983, 1049, 105074966.18
9771343Khasra
9782270Khasra
9792360Khasra
98150576Khasra
9835060Khasra
10494930Khasra
10509840Khasra

Approved Unit Plan

Unit plan rows on file286
Total flats (sum of rows)310
BlocksTOWER L, TOWER M
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
57888 May 2006
46520 Jan 2010
108015 Feb 2008
57788 May 2006
108515 Feb 2008
13113 Feb 2006
98513 Oct 2011
19510 Jan 2011

Frequently Asked Questions

What is the RERA registration number of INTEGRITY (Phase - 1: Tower L & M)?

The RERA registration number of INTEGRITY (Phase - 1: Tower L & M) is UPRERAPRJ5025, as recorded on the UP-RERA portal.

What is the RERA status of INTEGRITY (Phase - 1: Tower L & M)?

As reported by UP-RERA, the status of INTEGRITY (Phase - 1: Tower L & M) is "NCLT".

Where is INTEGRITY (Phase - 1: Tower L & M) located?

As reported to UP-RERA, INTEGRITY (Phase - 1: Tower L & M) is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will INTEGRITY (Phase - 1: Tower L & M) be completed?

The latest completion date reported to UP-RERA for INTEGRITY (Phase - 1: Tower L & M) is 30 Jun 2019.

Is INTEGRITY (Phase - 1: Tower L & M) delayed?

Measured against the latest completion date reported to UP-RERA, INTEGRITY (Phase - 1: Tower L & M) is 85 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026