Timeline Bar
Registered21 Jun 2018
Completed11 Oct 2021
Promised6 Jun 2023
Timeline
Promised completion6 Jun 2023
Revised completion6 Jun 2023
Actual completion11 Oct 2021
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹2,00,500
Project cost (in ₹ Lakhs)₹3,748.37 Lakhs
Project duration66 months
Project categoryResidential
Locality—
Original start date—
Proposed start date7 Jun 2018
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypePartnership Firm
Mobile8192001953
Emailbuilderscompetent@gmail.com
Coordinator8392921947
AddressVil- Nariyawal, behind Bichiachoti Temple, Post- PAC, Bareilly (U.P.)
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 140/01/LO/17 | 7 Jun 2018 | 6 Jun 2023 | 6 Jun 2023 | 6 Jun 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 50 | 322 | Khasra |
| 53 | 2022 | Khasra |
| 54 | 590 | Khasra |
| 71 | 660 | Khasra |
| 73 | 662.9 | Khasra |
| 74 | 1390 | Khasra |
| 75 | 344 | Khasra |
| 113 | 758 | Khasra |
| 114 | 1138 | Khasra |
| 115 | 2149 | Khasra |
| 116 | 700 | Khasra |
| 117 | 675 | Khasra |
| 118 | 927 | Khasra |
| 119 | 253.2 | Khasra |
| 120 | 420 | Khasra |
| 123 | 758 | Khasra |
| 124 | 662.91 | Khasra |
| 197 | 505 | Khasra |
| 201 | 505.5 | Khasra |
| 222 | 120 | Khasra |
| 223 | 316 | Khasra |
| 226 | 450 | Khasra |
| 227 | 885 | Khasra |
| 229 | 206 | Khasra |
| 230 | 190 | Khasra |
| 231 | 410 | Khasra |
| 232 | 885 | Khasra |
| 234 | 493.24 | Khasra |
| 256 | 2000 | Khasra |
| 257 | 1505 | Khasra |
| 258 | 2275 | Khasra |
| 262 | 234 | Khasra |
| 269 | 70 | Khasra |
| 537 | 82 | Khasra |
| 570 | 40 | Khasra |
| 573 | 70 | Khasra |
| 576 | 300 | Khasra |
| 577 | 126.5 | Khasra |
| 578 | 550 | Khasra |
| 579 | 506 | Khasra |
| 580 | 2402 | Khasra |
| 581 | 711 | Khasra |
| 582 | 1011 | Khasra |
| 583 | 758.4 | Khasra |
| 584 | 838 | Khasra |
| 585 | 1000 | Khasra |
| 586 | 885 | Khasra |
| 587 | 1200 | Khasra |
| 588 | 1050 | Khasra |
| 598 | 1200 | Khasra |
| 599 | 880 | Khasra |
Frequently Asked Questions
What is the RERA registration number of INTERNATIONAL CITY-SOUTHERN COUNTY?
The RERA registration number of INTERNATIONAL CITY-SOUTHERN COUNTY is UPRERAPRJ16632, as recorded on the UP-RERA portal.
What is the RERA status of INTERNATIONAL CITY-SOUTHERN COUNTY?
As reported by UP-RERA, the status of INTERNATIONAL CITY-SOUTHERN COUNTY is "Registered".
Where is INTERNATIONAL CITY-SOUTHERN COUNTY located?
As reported to UP-RERA, INTERNATIONAL CITY-SOUTHERN COUNTY is located at Bareilly, Bareilly, Uttar Pradesh.
Is INTERNATIONAL CITY-SOUTHERN COUNTY completed?
As reported to UP-RERA, INTERNATIONAL CITY-SOUTHERN COUNTY was completed on 11 Oct 2021.
Is INTERNATIONAL CITY-SOUTHERN COUNTY delayed?
Measured against the latest completion date reported to UP-RERA, INTERNATIONAL CITY-SOUTHERN COUNTY is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026