Timeline Bar
Registered28 Feb 2022
Promised30 Jun 2024
Today4 Aug 2026
Timeline
Promised completion30 Jun 2024
Revised completion30 Jun 2024
Actual completion—
Possession delay25 mo delay
Registration & Cost Details
Registration fee (in ₹)₹30,000
Project cost (in ₹ Lakhs)₹406 Lakhs
Project duration30 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Jan 2022
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypePartnership Firm
Mobile9358775269
Emailjhminfrahomes1@gmail.com
Coordinator9897073073
AddressJHM JOY SHOP NO. 3 KHASRA NO. 494-495
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| PRD/PH/00685/BDA/LD/21-22/0283/25102021 | 23 Dec 2021 | 22 Dec 2026 | 30 Jun 2024 | 22 Dec 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 505 | 5060 | Khasra |
Frequently Asked Questions
What is the RERA registration number of JHM ACE?
The RERA registration number of JHM ACE is UPRERAPRJ394914, as recorded on the UP-RERA portal.
What is the RERA status of JHM ACE?
As reported by UP-RERA, the status of JHM ACE is "Registered".
Where is JHM ACE located?
As reported to UP-RERA, JHM ACE is located at Bareilly, Bareilly, Uttar Pradesh.
When will JHM ACE be completed?
The latest completion date reported to UP-RERA for JHM ACE is 30 Jun 2024.
Is JHM ACE delayed?
Measured against the latest completion date reported to UP-RERA, JHM ACE is 25 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026