Timeline Bar
Registered23 Sept 2021
Completed30 Jul 2025
Promised31 Aug 2025
Timeline
Promised completion31 Aug 2025
Revised completion31 Aug 2025
Actual completion30 Jul 2025
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹4,37,500
Project cost (in ₹ Lakhs)₹11,000 Lakhs
Project duration48 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Sept 2021
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypePartnership Firm
Mobile7800435555
Emailcrm.babainfra@gmail.com
Coordinator7800435555
AddressG 83/201, 2nd Floor, Vijay Chowk, Laxmi Nagar, Delhi-110092
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| LDA/LD/20-21/1370 | 27 Aug 2021 | 26 Aug 2026 | 31 Aug 2025 | 26 Aug 2029 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| Proposed residential township Kailasha enclave at khasra no. 258, 258, 265VA, 262, 256,261, 261,263, 264, 259, 261, 256, 268, 263 and 264, at village madharmau kalan, khasra no. 326, 327, 328,330, 323, 315, 324, 333, 334, 331, 311, 310, 332, 326, 327, 328, 330, 332, 312, 332 at Village Madharmau khurd, Khasra no. 3012, 3000, 3013, 3025, 3006, 3016, 3017, 3018, 3001, 3002, 3004, 3005, 3022, 3023, 3020, 3019 S, 3009, 3010, 3011, 3014, 3015 at village Bakkas, Khasta no. 2 and 1 MA at Village Pahad Nagar Tikariya, Tehsil Mohanlalganj, Lucknow | 94301.3 | Khasra |
Frequently Asked Questions
What is the RERA registration number of KAILASHA ENCALVE?
The RERA registration number of KAILASHA ENCALVE is UPRERAPRJ418011, as recorded on the UP-RERA portal.
What is the RERA status of KAILASHA ENCALVE?
As reported by UP-RERA, the status of KAILASHA ENCALVE is "Registered".
Where is KAILASHA ENCALVE located?
As reported to UP-RERA, KAILASHA ENCALVE is located at Mohanlalganj, Lucknow, Uttar Pradesh.
Is KAILASHA ENCALVE completed?
As reported to UP-RERA, KAILASHA ENCALVE was completed on 30 Jul 2025.
Is KAILASHA ENCALVE delayed?
Measured against the latest completion date reported to UP-RERA, KAILASHA ENCALVE is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026