KARYAN SQUARE

UPRERARegistered

KARYAN SQUARE is a RERA-registered commercial project by KARYAN INFRACOM LLP in Ghaziabad (RERA ID UPRERAPRJ678096). Registered with a completion deadline of 22 Mar 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
64.45%Q3'25
69.6%Q4'25
77.64%Q1'26
96.17%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ678096
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start30 Mar 2023
Project duration60 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typePartnership Firm
Applicant addressD-49, DEFENCE COLONY, SOUTH DELHI -110024
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Commercial Building/04616/GDA/BP/22-23/1244/10032023

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. 2 completion certificates filed

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered25 Apr 2023
Original completion22 Mar 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary13 Jul 2026
Registration fee₹46,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors257 · 1 · 5 (units from plan)
Homes · commercial units13 · 244 (shops and offices filed in the same plan)
  • SHOP244 95%
  • OTHER13 5%
ConfigurationUnitsCarpet area
SHOP2444-33
OTHER139-917
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Karyan Square · SHOP, OTHER52574-33
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
KAILASH CHANDER AGGARWAL
License CA-86-10069
J-16, SECTOR-41, NOIDA, U.P-201301
Engineer
RAMKRISHNA D.CHAUDHARI
B-1102, VASUDHA, DOSTI VIHAR, POKHRAN ROAD 1, VARTAK NAGAR, THANE-400606
Contractor
RADHA BUILDTECH PVT. LTD.
4/2885, GALI NO.1, BIHARI COLONY, SHAHDARA, DELHI-110032
Sr.Development work declared to RERA
1Demarcation of Plots
Commercial Plot No. 02, Sector-01, Oakwood Enclave, Wave City, having area 3597.90 Sq.Mtr, North- Other Plot, South-57 Meter Road, East-Other Plot, West-30 Meter Wide Road.
2Boundary Wall
Boundary Wall will be constructed in combination of reinforced cement/concrete with steel/iron railing work.
3Road Work
No Internal Road, Ramps and set back area with CC concrete / pavers blocks
4Footpaths
Foothpath to be provided in combination of concrete pavers/ heavy duty tiles/paver blocks
5Water Supply Including Drinking Water Facilities
Permanent water connection for domestic water and treated water to the project will be provided by the township developer/ municipal Authorities
6Sewer System
under ground system using uPVC(SN-4) pipes and utility connection with township developer sewer line for further treatment and disposal.
7Drain
Drain via Hanging uPVC lines in basement and ultimately connected with township drainage system
8Parks
it is a commercial plot admeasuring 3597.90 Sq.Mtr hence no park, however Land Space / open shall be provided as per approved Layout
9Tree Planting
As per the approved layout plan total no. of 60 trees proposed for the project comprising evergreen trees and ornamental trees.
10Design For Electric Supply Including Street Lighting
Single point connection from PVVNL/Uppal chaddha group project is a integral part of township where street lighting will be done by the township developer.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
The solid waste from toilets and kitchen will be connected in manholes in single network of RCC pipes laid underground having manholes/ inspection chambers at appropriate intervals and finaly connected with sewer and drainage for further treatment and disposal.
13Solid Waste Management And Disposal System
To be done in strict compliance of the rules, regulations, directions, condition , laid down in this regard by the competent authorities from time to time.
14Water Conservation System
Rain water harvesting System as per approved plan will be commisioned ,. water conservation using low flow fixtures, Flow Restrictors will be used to Restrict the flow of water to acheived the objective.
15Energy Management System Including Use of Renewable Energy
All high side equipment will be installed of energy efficient rating with requisite provision of renewable energy as the condition laid down by the competent authorities.
16Fire Protection And Fire Safety System
The fire protection and fire safety system will be implemented as per the proposed fire fighting plan in accordance to the fire norms as amended from time to time.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Commercial plot admeasuring 3597.90 Sq Mtr and Hence No special provision to social infrastructure and other public ameneties including public health services could be proposed within the project. However, Wheel chair Access for diferently abled and provision for lavatories with suitable provisions to accomodate them shall be kept in place. in addition thereof primary first aid shall be adequate non medical staff to assist in case of minor injuries.
18Emergency Evacuation Services
For providing easy n safe eggress in case of fire, Fires stair case has been planed. in addition to this fire safety machenism such as fire alarm, sprinklers, fire Fire Extinguishers/ Hydrants and other equipment shall be in strict compliance with the fire safty norms and approved fire fighting plan. all levels will be marked with fire exit directipons, Signages and Building Evacuation plan.
19Other Miscellaneous Work
Provision shall be done to make the entire building structure earthquake resistant as per the approved plans. The fascade of the building is planed in the manner that it makes the area beautifull and appealing.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

3 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1AGVG Infratech Private LimitedUPRERAAGT20389
2Global RealtyUPRERAAGT16138
3Trisol RED Infraventures Pvt LtdUPRERAAGT11579
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 22 Mar 2028.

Sanctioned by Ghaziabad Development Authority · 3,598 sqm of land · an approved plan of 1 block and 257 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Commercial Building/04616/GDA/BP/22-23/1244/1003202323 Mar 202322 Mar 202821 Mar 203122 Mar 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
COMMERCIAL PLOT NO. 2, SECTOR-1, OAKWOOD ENCLAVE, WAVE CITY, GZB3597.90Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · BOOK NO. 1, VOLUME- 19643, PAGENO. 203 TO 226 DOCUMENT NO. 424
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New31 Mar 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New31 Mar 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 Mar 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New31 Mar 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 Mar 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New31 Mar 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New31 Mar 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New31 Mar 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Mar 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Apr 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New31 Mar 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New31 Mar 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New31 Mar 2023 ↗

Quarterly progress reports

14 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

14 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q1.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q264.45%CA ↗ · Arch ↗ · Eng ↗
2025-Q369.6%CA ↗ · Arch ↗ · Eng ↗
2025-Q477.64%CA ↗ · Arch ↗ · Eng ↗
2026-Q196.17%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameKARYAN INFRACOM LLP
RolePromoter · current
RERA IDUPRERAPRM228494
PANAAQFK8356B
CIN / TANDELK25909C
Registered addressD-49, DEFENCE COLONY, SOUTH DELHI -110024
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
KARYAN INFRACOM LLP RERA COLLECTION ACCOUNT FOR KARYAN SQUAREBankICICI BANK LTD.BranchINDIRAPURAM GHAZIABADBranch addressAG-1, PLOT NO.1, ADITYA CITY CENTRE, GHAZIABAD, 201012Branch districtGhaziabad, Uttar PradeshA/C no.IFSCICIC0000718
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
KARYAN INFRACOM LLP RERA SEPARATE ACCOUNT FOR KARYAN SQUAREBankICICI BANK LTD.BranchINDIRAPURAM GHAZIABADBranch addressAG-1, PLOT NO.1, ADITYA CITY CENTRE, GHAZIABAD,201012Branch districtGhaziabad, Uttar PradeshA/C no.IFSCICIC0000718
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
KARYAN INFRACOM LLP RERA TRANSACTIONS ACCOUNT FOR KARYAN SQUAREBankICICI BANK LTD.BranchINDIRAPURAM GHAZIABADBranch addressAG-1, PLOT NO.1, ADITYA CITY CENTRE, GHAZIABAD,201012Branch districtGhaziabad, Uttar PradeshA/C no.IFSCICIC0000718
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)1 (Under Registration - 1 ) → 1 (Under Registration - 0 )
changed in Estanzo’s record
23 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 23 Sept 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about KARYAN SQUARE

Is KARYAN SQUARE RERA registered?

Yes. KARYAN SQUARE is registered with UPRERA under registration number UPRERAPRJ678096, registered on 25 Apr 2023. Estanzo reproduces that filing; it does not verify the work behind it.

Has KARYAN SQUARE been completed?

UPRERA still lists KARYAN SQUARE as Registered, so it is not shown as completed here. A completion certificate dated 13 Jul 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of KARYAN SQUARE?

KARYAN INFRACOM LLP is the promoter entity that filed KARYAN SQUARE with UPRERA (promoter RERA ID UPRERAPRM228494). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does KARYAN SQUARE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is KARYAN SQUARE located?

KARYAN SQUARE is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in KARYAN SQUARE?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in KARYAN SQUARE?

The approved unit plan filed with UPRERA runs from 4 to 917 m² of carpet area (about 44 to 9,873 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in KARYAN SQUARE?

The approved unit plan describes 1 block and 257 units of which 13 are homes and 244 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is KARYAN SQUARE?

About 289 units per acre: 257 planned units across 0.89 acres (3,598 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗