UCHDPL-Sector-1-Oak Wood Enclave- Plots is a RERA-registered residential project by Uppal Chadha Hi-Tech Developers Pvt. Ltd. in Ghaziabad (RERA ID UPRERAPRJ229635). Registered with a completion deadline of 30 Jun 2021.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ229635 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Ghaziabad Development Authority |
| Proposed start | 1 Jul 2019 |
| Project duration | 24 months |
| Address | Ghaziabad, Ghaziabad |
| Tehsil | Ghaziabad |
| Applicant type | Company |
| Applicant address | M-4 Mezzanine Floor, South Extension Part II, New Delhi, Delhi 110049 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
227/zone-5/17-18
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 24 Aug 2020 |
| Original completion | 30 Jun 2021 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 25 May 2026 |
| Registration fee | ₹5,00,500 |
| Sanctioning authority | Ghaziabad Development Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Size, shape and orientation is demarcated as per Layout approved by Ghaziabad Development Authority vide its letter 258/MP/Z-5/19 dated 29/05/2019.
A concrete pillar of size 100x100x600mm at four corners of each plot is installed |
| 2 | Boundary Wall Boundary wall shall be constructed with following criteria
Width 230mm, Length 765m, height 1.8m made with standard brick with MS Grill |
| 3 | Road Work Roads as per IRC Norms with following Details
Width(m)Length(m)Carriageway(m)footpah(m)GSB(mm)WMM (mm)SDBC (mm)
9 m 341 5 4 150 100 30
12 m 2800 6 6 150 100 30
15 m 74 7.5 7 150 100 30 |
| 4 | Footpaths Footpaths as per following Details
Footpath
Width(m) Length (m) footpah (m)GSB (mm) Interlocking tiles over sand bed
9 m 682 4 75 60
12 m 5600 6 75 60
15 m 148 7 75 60 |
| 5 | Water Supply Including Drinking Water Facilities 4825 m long distribution pipe network has been laid for 24 x 7 water supply.
HDPE pipe PN-6, PE-80 has been used.
1600 KL storage (800KL UGT and 800 KL OHT) has been provided.
3 tub-wells (with total 45HP pump) used with piped network of HDPE PN-10, PE 100 pipes are used |
| 6 | Sewer System 3424 m long piped network has been laid at site to collect the sewage from each household with the help of 237 manholes and chambers and dispose off the same in trunk sewer line of Wave City
RCC pipe class NP2 has been used
Dia Length
150 573
200 2851
Total 3424
Manholes/CHambers
Dia No.
Chamber 450x450 66
900 131
1200 15
1500 25
Total 237 |
| 7 | Drain 3069 m long piped network has been laid at site to collect the storm water run off generating from roads, open areas and green areas with the help of 106 manholes and gully pits and dispose off the same in trunk storm water drainage line of Wave City
RCC pipe class NP2 has been used
Pipe
Dia Length
200 2059
250 273
300 258
350 124
400 55
450 68
500 145
700 87
Total 3069
Manholes
Manhole
Dia No.
900 106 |
| 8 | Parks As per the Approved layout, Green area and Open spaces is 8532.62 SQM (8.61 %). There are four parks with respective areas 4450 SQM, 1044 SQM , 1248 SQM , 904 SQM. All parks are Wire fencing along boundary, Grassing and tree Plantation |
| 9 | Tree Planting One tree on one side of 9m road
Both side trees on 12m and 15m road |
| 10 | Design For Electric Supply Including Street Lighting Total 3 no’s of Compact substation detail as 1000 KVA – 2nos and 1600 KVA -1 no. of make Ambit Switchgear.
7.5 meter long decorative street light poles with 90 watt LED light fixtures.
Feeder panels of 6 way, 8 –way and 12way. |
| 11 | Community Buildings There is no community building in this project. |
| 12 | Treatment and Disposal System of Sewage and Sullage water The scheme sewage shall be disposed in trunk sewer line which goes to Township level STP proposed in Sec-4, Wave City.
Township level STP shall be installed later when the sufficient sewage is available and pipe network is through upto STP.
In order to treat sewage till the township level STP comes up a modular type 200 KLD STP has been installed at site. |
| 13 | Solid Waste Management And Disposal System Solid waste shall be collected from each household and segregated a solid waste treatment facility developed at Sec-6 where organic waste is composted with the help of Automatic organic waste converter machine. |
| 14 | Water Conservation System A separate network comprising 4344 m long piped network has been developed to collect the rooftop rain water from each plot less than 300sqm and carry the same to RWH recharge structures developed in the nearby park.
Pipe
Dia Length
150 4011
200 43
250 135
300 96
350 9
400 21
450 29
Total 4344
Chamber
Dia No.
600x600 271
Total 271
Two RWH recharge structures of approx. 144 cum have been developed at site.
Modular type RWH pits have been developed with Rain Max recharge Tanks technology. |
| 15 | Energy Management System Including Use of Renewable Energy NA |
| 16 | Fire Protection And Fire Safety System NA |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services NA |
| 19 | Other Miscellaneous Work NA |
Registered agents
2 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | Amardeep platinum estates | UPRERAAGT18979 |
| 2 | INVESTORS CLINIC INFRATECH PRIVATE LIMITED | UPRERAAGT10052 |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 9 Jul 2019.
Sanctioned by Ghaziabad Development Authority · 99,041 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 227/zone-5/17-18 | 29 May 2019 | 9 Jul 2019 | 8 Jul 2022 | 30 Jun 2021 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
43 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 66 | 645.84 | Khasra |
| 67 | 2640.00 | Khasra |
| 68 | 2612.66 | Khasra |
| 69 | 1839.93 | Khasra |
| 74 | 145.00 | Khasra |
| 75 | 125.00 | Khasra |
| 76 | 2750.00 | Khasra |
| 77 | 20.00 | Khasra |
| 78 | 650.00 | Khasra |
| 79 | 4500.00 | Khasra |
| 80 | 4930.00 | Khasra |
| 81 | 1050.00 | Khasra |
| 82 | 1040.00 | Khasra |
| 83 | 1617.07 | Khasra |
| 84 | 50.00 | Khasra |
| 109 | 2626.33 | Khasra |
| 227 | 12346.13 | Khasra |
| 228 | 2790.08 | Khasra |
| 231 | 8391.65 | Khasra |
| 233 | 210.00 | Khasra |
| 234 | 25834.52 | Khasra |
| 235 | 18262.85 | Khasra |
| 236 | 153.67 | Khasra |
| 235/543 | 2878.50 | Khasra |
| 235/542 | 910.41 | Khasra |
| Lease deed · 134 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Khatauni extract · 1426-1431 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 2 Jul 2020 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 2 Jul 2020 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 2 Jul 2020 ↗ |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | New | 2 Jul 2020 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 2 Jul 2020 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 2 Jul 2020 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 29 Jul 2020 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 29 Jul 2020 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 10 Aug 2020 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 30 Jul 2020 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 11 Jul 2020 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 11 Jul 2020 ↗ |
Quarterly progress reports
17 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
17 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2024-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Uppal Chadha Hi-Tech Developers Pvt. Ltd. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM5538 |
| PAN | AAACU7200M |
| CIN / TAN | U45201DL2004PTC128784 |
| Registered address | M-4 Mezzanine Floor, South Extension Part II, New Delhi, Delhi 110049 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Ghaziabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Sec 1 Oak Wood Enclave PlotsBankYes Bank Ltd.BranchRajnagar GhaziabadA/C no.IFSCYESB0000038 |
What has changed on this record
3 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 1056 (Under Registration - 1 ) → 1056 (Under Registration - 0 ) changed in Estanzo’s record | 18 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 1055 (Under Registration - 0 ) → 1056 (Under Registration - 1 ) changed in Estanzo’s record | 5 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 1055 (Under Registration - 1 ) → 1055 (Under Registration - 0 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 18 Oct 2026 · 3 movements on record |
What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about UCHDPL-Sector-1-Oak Wood Enclave- Plots
Is UCHDPL-Sector-1-Oak Wood Enclave- Plots RERA registered?
Yes. UCHDPL-Sector-1-Oak Wood Enclave- Plots is registered with UPRERA under registration number UPRERAPRJ229635, registered on 24 Aug 2020. Estanzo reproduces that filing; it does not verify the work behind it.
Has UCHDPL-Sector-1-Oak Wood Enclave- Plots been completed?
UPRERA still lists UCHDPL-Sector-1-Oak Wood Enclave- Plots as Registered, so it is not shown as completed here. A completion certificate dated 25 May 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of UCHDPL-Sector-1-Oak Wood Enclave- Plots?
Uppal Chadha Hi-Tech Developers Pvt. Ltd. is the promoter entity that filed UCHDPL-Sector-1-Oak Wood Enclave- Plots with UPRERA (promoter RERA ID UPRERAPRM5538). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does UCHDPL-Sector-1-Oak Wood Enclave- Plots have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is UCHDPL-Sector-1-Oak Wood Enclave- Plots located?
UCHDPL-Sector-1-Oak Wood Enclave- Plots is registered in Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗