Estanzo

Timeline Bar

Registered12 Jul 2023
Today4 Aug 2026
Promised27 Mar 2028

Timeline

Promised completion27 Mar 2028
Revised completion27 Mar 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹96,500
Project cost (in ₹ Lakhs)₹19,594 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date
Proposed start date28 Mar 2023

Inventory

Total units1040
Unit TypeUnitsCarpet Area (sqm)
1 BHK104026.24–32.89

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9628372038
Emailgdagorakhpur@gmail.com
Coordinator9628372038
AddressTaramandal, Deoria Byepass Road, Gorakhpur

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q40.0%
2023-Q10.0%
2023-Q20.0%
2023-Q30.0%
2023-Q42.5%
2024-Q10.0%
2024-Q20.0%
2024-Q30.0%
2024-Q40.0%
2025-Q10.0%
2025-Q258.0%
2025-Q365.0%
2025-Q472.9%
2026-Q176.5%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
448/NIYO./ANU./2023-2426 May 202325 May 202827 Mar 202824 May 2031

Land Parcels

Khasra No.AreaPlot Type
920,921,923,924MI,925,926,927,928,931,933,934,935,936,937,932,938MI18280.29Khasra

Approved Unit Plan

Unit plan rows on file58
Total flats (sum of rows)1040
BlocksBLOCK 1 EWS G+3, BLOCK 1 LIG G+14, BLOCK 2 EWS G+3, BLOCK 2 LIG G+14, BLOCK 3 EWS G+3, BLOCK 4 EWS G+3, BLOCK 5 EWS G+3, BLOCK 6 EWS G+3, BLOCK 7 EWS G+3
Floor types1 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Khorabar EWS/LIG Group Housing?

The RERA registration number of Khorabar EWS/LIG Group Housing is UPRERAPRJ800885, as recorded on the UP-RERA portal.

What is the RERA status of Khorabar EWS/LIG Group Housing?

As reported by UP-RERA, the status of Khorabar EWS/LIG Group Housing is "Registered".

Where is Khorabar EWS/LIG Group Housing located?

As reported to UP-RERA, Khorabar EWS/LIG Group Housing is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

When will Khorabar EWS/LIG Group Housing be completed?

The latest completion date reported to UP-RERA for Khorabar EWS/LIG Group Housing is 27 Mar 2028.

Is Khorabar EWS/LIG Group Housing delayed?

Measured against the latest completion date reported to UP-RERA, Khorabar EWS/LIG Group Housing is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026