Timeline Bar
Registered4 Oct 2017
Promised6 Apr 2019
Completed20 Jul 2022
Timeline
Promised completion6 Apr 2019
Revised completion6 Apr 2019
Actual completion20 Jul 2022
Possession delay39 mo delay
Registration & Cost Details
Registration fee (in ₹)₹83,500
Project cost (in ₹ Lakhs)₹1,253 Lakhs
Project duration62 months
Project categoryResidential
Locality—
Original start date7 Apr 2017
Proposed start date7 Apr 2017
Inventory
Total units44
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 3 BHK | 32 | 75.16 |
| OTHER | 12 | 17.23–18.14 |
Promoters & Contact
Contact Details
Applicant TypeCompetent authority
Mobile9628372038
Emailgdagorakhpur@gmail.com
Coordinator9628372026
AddressTaramandal, Deoria Byepass Road, Gorakhpur
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| LOHIA/P/III/11032016 | 11 Mar 2016 | 10 Mar 2021 | 6 Apr 2019 | 10 Mar 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 745 | 0.4 | — |
| 746 | 0.7 | — |
| 747 | 0.9 | — |
| 748 | 0.16 | — |
| 749 | 0.49 | — |
| 910 | 0.29 | — |
| 911 | 0.31 | — |
| 912 | 0.66 | — |
| 913 | 1.5 | — |
| 914 | 0.53 | — |
| 915 | 0.18 | — |
| 916 | 0.24 | — |
| 917 | 0.51 | — |
| 918 | 0.19 | — |
| 919 | 0.19 | — |
| 920 | 0.97 | — |
| 921 | 0.8 | — |
| 922 | 0.79 | — |
| 923 | 0.99 | — |
| 924 | 0.61 | — |
| 925 | 0.41 | — |
| 926 | 1.24 | — |
| 928 | 1.27 | — |
| 929 | 0.20 | — |
| 930 | 0.01 | — |
| 931 | 0.20 | — |
| 1054 | 0.24 | — |
| 1055 | 1.21 | — |
| 1056 | 0.02 | — |
| 1057 | 0.22 | — |
| 1058 | 0.27 | — |
| 1059 | 1.26 | — |
| 1060 | 0.36 | — |
| 1061 | 0.37 | — |
| 1062 | 0.19 | — |
| 1063 | 0.77 | — |
| 1064 | 0.15 | — |
| 1065 | 0.48 | — |
| 1067 | 0.54 | — |
| 1071 | 0.86 | — |
Approved Unit Plan
Unit plan rows on file14
Total flats (sum of rows)44
Blocks1, 2, 3
Floor types3 BHK, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| NIL | 30 Oct 1986 | — | — |
Frequently Asked Questions
What is the RERA registration number of LOHIA ENCLAVE - PHASE - III?
The RERA registration number of LOHIA ENCLAVE - PHASE - III is UPRERAPRJ9518, as recorded on the UP-RERA portal.
What is the RERA status of LOHIA ENCLAVE - PHASE - III?
As reported by UP-RERA, the status of LOHIA ENCLAVE - PHASE - III is "Registered".
Where is LOHIA ENCLAVE - PHASE - III located?
As reported to UP-RERA, LOHIA ENCLAVE - PHASE - III is located at Gorakhpur, Gorakhpur, Uttar Pradesh.
Is LOHIA ENCLAVE - PHASE - III completed?
As reported to UP-RERA, LOHIA ENCLAVE - PHASE - III was completed on 20 Jul 2022.
Is LOHIA ENCLAVE - PHASE - III delayed?
Measured against the latest completion date reported to UP-RERA, LOHIA ENCLAVE - PHASE - III is 39 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026