Estanzo

Timeline Bar

Registered4 Oct 2017
Promised6 Apr 2019
Completed20 Jul 2022

Timeline

Promised completion6 Apr 2019
Revised completion6 Apr 2019
Actual completion20 Jul 2022
Possession delay39 mo delay

Registration & Cost Details

Registration fee (in ₹)₹83,500
Project cost (in ₹ Lakhs)₹1,253 Lakhs
Project duration62 months
Project categoryResidential
Locality
Original start date7 Apr 2017
Proposed start date7 Apr 2017

Inventory

Total units44
Unit TypeUnitsCarpet Area (sqm)
3 BHK3275.16
OTHER1217.23–18.14

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9628372038
Emailgdagorakhpur@gmail.com
Coordinator9628372026
AddressTaramandal, Deoria Byepass Road, Gorakhpur

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
LOHIA/P/III/1103201611 Mar 201610 Mar 20216 Apr 201910 Mar 2024

Land Parcels

Khasra No.AreaPlot Type
7450.4
7460.7
7470.9
7480.16
7490.49
9100.29
9110.31
9120.66
9131.5
9140.53
9150.18
9160.24
9170.51
9180.19
9190.19
9200.97
9210.8
9220.79
9230.99
9240.61
9250.41
9261.24
9281.27
9290.20
9300.01
9310.20
10540.24
10551.21
10560.02
10570.22
10580.27
10591.26
10600.36
10610.37
10620.19
10630.77
10640.15
10650.48
10670.54
10710.86

Approved Unit Plan

Unit plan rows on file14
Total flats (sum of rows)44
Blocks1, 2, 3
Floor types3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
NIL30 Oct 1986

Frequently Asked Questions

What is the RERA registration number of LOHIA ENCLAVE - PHASE - III?

The RERA registration number of LOHIA ENCLAVE - PHASE - III is UPRERAPRJ9518, as recorded on the UP-RERA portal.

What is the RERA status of LOHIA ENCLAVE - PHASE - III?

As reported by UP-RERA, the status of LOHIA ENCLAVE - PHASE - III is "Registered".

Where is LOHIA ENCLAVE - PHASE - III located?

As reported to UP-RERA, LOHIA ENCLAVE - PHASE - III is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

Is LOHIA ENCLAVE - PHASE - III completed?

As reported to UP-RERA, LOHIA ENCLAVE - PHASE - III was completed on 20 Jul 2022.

Is LOHIA ENCLAVE - PHASE - III delayed?

Measured against the latest completion date reported to UP-RERA, LOHIA ENCLAVE - PHASE - III is 39 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026